f JgRIS p m"Ec UNITED STATES oq[0, a

NUCLEAR REGULATORY COMMISSION f

'g([

REGloN lil e

~

t 799 ROOSEVELT RO AD 0,

4 CLEN ELLYN ILLINOIS 60937

/

I,1M 181979 Docket Nos. 50-295, 50-304, 50-10, 50-237, 50-249, 50-254 and 50-265 Commonwealth Edison Company ATTN:

Mr. Byron Lee, Jr.

Vice President P. O. Box 767 Chicago, IL 60690 Gentlemen:

The enclosed IE Circular No. 79-08, is forwarded to you for information.

If there are any questions related to the contents or intent of the Circular or its attachments, please contact this office.

Sincerely, SS James G. Keppler Director

Enclosure:

IE Circular No. 79-08 cc w/ encl:

N. Wandke, Plant Superintendent B. B. Stephenson, Station Superintendent N. Kalivianakis, Plant Superintendent Central Files Director, NRR/DPM Director, NRR/ DOR PDR Local PDR NSIC TIC Anthony Roisman, Esq., Attorney Mr. Dean Hansell, Office of Assistant Attorney General 7006080 /#l6

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION III May 18, 1979 IE Circular No. 79-08 ATTEMPTED EXTORTION - LOW ENRICHED URANIUM

Background

In January 1979, a temporary contractor employee who was working at the General Electric plant in Wilmington, North Carolina, allegedly entered the plant and removed a dru= containing two 5-gallon cans of low enriched uraniu= from the facility with the intention of extorting money for the return of the material. The Federal Bureau of Investigation conducted an intensive investigation leading to the arrest of the e=ployee on February 1, 1979.

All material was recovered and returned to the plant.

Discussion Based on preliminary information provided the NRC, the theft was allegedly carried out in the following manner:

On Friday, January 26, 1979, the subject worked the day shift.

10:50 p.m. the same day he drove back to the plant and entered At with the night shift. He showed his Florida driver's license at the entrance gate instead of his yellow contractor badge because it had a blue background similar to that on the picture badge which he thought was required to gain access to the area of the plant that he wanted to penetrate. He had allegedly gained access using his driver's license on previous occasions.

Once inside the plant, the subject would have be pided by gates and fences into a parking area had it not been ror the fact that one gate had been re=oved to allow installation of truck scales.

He proceeded down the unprotected road to an area adjacent to the building he wanted to enter.

Af ter the subject entered the building through a personnel door, he proceeded to hir normal workin station which was the Chem Tech Lab and entered, using his own key clothing, a two wheel cart use used to ship chemicals. The c DUPLICATE DOCUMENT He then proceeded to a door le Entire document previously entered into system u-ler:

ANO h

ghf)