Forwards Third Interim Deficiency Rept Re Possible Unconservative Pressurizer Relief & Safety Line Blowdown Analysis
Date released: 09/27/2019 Download: ML19256B207


Third Interim Rept Re Possible Unconservative Pressurizer Relief & Safety Line Blowdown Analysis.Reanalysis & Support Design of Sys Complete,But Some Components of Nozzle Loads Are Too Great
ML19256B208
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 12/28/1978
From:
TENNESSEE VALLEY AUTHORITY
To:
References
Download: ML19256B208 (1)
Forwards Third Interim Deficiency Rept Re Possible Unconservative Pressurizer Relief & Safety Line Blowdown Analysis
ML19256B206
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 12/28/1978
From: Gilleland J
TENNESSEE VALLEY AUTHORITY
To: OREILLY J P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19256B206 (1)