ML19256A081

From kanterella
Jump to navigation Jump to search
Insp Rept 50-466/78-02 on 780816-19 & 0901.Deviation Noted: Failure to Provide Approved Procedure for Processing Field Procurement Contracts,Training & Design Review
ML19256A081
Person / Time
Site: Allens Creek File:Houston Lighting and Power Company icon.png
Issue date: 09/22/1978
From: Crossman W, Randy Hall, Hubacek W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19256A077 List:
References
50-466-78-02, 50-466-78-2, NUDOCS 7811030040
Download: ML19256A081 (15)


See also: IR 05000466/1978002

Text

.

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REVION IV

Report No. 50-466/78-02

Docket No. 50-466

Category Al

Licensee: Houston Lighting a"

ver Company

Post Office Box 17

Houston, Texas

' , . ~ ' ' . ,

Facility Name: Allens Creek Nuclear Generating Station, Unit No.1

Inspection at: Houston, Texas

Inspection conducted: August 16 and August 29 - September 1,1978

Inspeetors G/, W9/,im 8.,

'7 /l2/ /7Vs'

W. G. Hubacek, Reactor Inspector, Projects Section

Date

(Paragraphs 1, 2, 3, 8 & 9)

7k/?r

g . I. Tapia, Reactor Inspector-Intern, Engineering

06te

'/

Support Section (Paragraphs 4, 5 & 6)

=v_ x

-

9/Z/f78

W. A. Crossman, Chief, Projects Section

Date

(Paragraph 7)

Approved:

F /!78

o=-

W. A. Crossman, Chief, Projects Section

Date

f /f77

R. E. Hall, Chief, Engineering Support Section

Date

ggi?_03 0

Inspection Summary:

Inspection on August 16 and August 29 - September 1,1978 (Report No.

50-466/78-02)

Areas Inspected:

Special, announced inspection of implementation of the QA

program for design, procurement and construction.

The inspection involved

one-hundred eight inspector-hours by three NRC inspectors.

Results:

Five deviations from commitments were identified in the three

areas inspected (failure to provide an approved procedure for processing

field procurement contracts, paragraph 2; failure to prescribe vendor

surveillance report format, paragraph 2; failure to provide training re-

quirements in departmental procedures, paragraph 4; failure to provide

approved procedures for design review, paragraph 7; failure to provide

procedures for control of the Design Review Worksheet, paragraph 7).

-2-

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • R. A. Frazar, QA Manager
  • F. W. Stoerkel, Project QA Supervisor
  • W. N. Phillips, Projects QA Manager
  • C. A. McClure, Supervisor, Support Division, QA
  • T. K. Logan, Site QA Supervisor
  • P. A. Horn, Project Manager, Allens Creek, Power Plant Engineering

and Construction (PPE&C)

R. E. Fulghum, Managt?, Engineering Division, PPE&C

H. P. Horelica, Construction Supervisor, PPE&C

J. R. Sumpter, Manager, Nuclear Division, PPE&C

  • J. W. Hanson, Principal Engineer, Nuclear, PPE&C
  • R. T. Beaubcnef, Principal Engineer, Mechanical, PPE&C
  • C. F. Brauer, Engineer, Construction, PPE&C

S. C. Schaeffer, Principal Engineer, Electric, PPE&C

J. N. Bailey, Engineer, Nuclear, PPE&C

R. T. McPhail, Engineer, Mechanical, PPE&C

  • T. L. Duoto, Principal Engineer, Civil Enginee ring Department

C. T. Howell, Supervising Engineer, Civil Engineering Department

R. R. Hernandez, Lead Engineer, Civil Engineering Dept.

C. M. Stripling, Supervising Engineer, Civil Engineering Department

R. A. Raymond, Engineer, Civil Engineering Department

W. C. Jones, Associate Engineer, Civil Engineering Department

P. A. Swearingen, General Supervisor, QA Records Management System

A. E. Schoeneberg, Supervisor, Project Coordinator, Purchasing

T. J. Floyd, Project Purchasing Coordinator

Other Personnel

L. F. Jones, Senior Resident Engineer, Ebasco

R. P. Grippardi, QC Site Supervisor, Ebasco

-

The IE inspectors also interviewed other licensee personnel including

members of the engineering and QA/QC staffs.

  • denotes those attending the exit interview.

2.

Procurement

a.

Review of Implementing Procedures

The IE inspector reviewed procedures related to procurement to

ascertain whether they were consistent with the status of the

project and PSAR commitments.

.

-3-

The following Purchasing Department Power Plant Procurement

Procedures were rcviewed:

Introduction, Rev. 1, 3/5/75

PP-1, " General Procurement Procedure," Rev. 5, 7/7/77

PP-2, " Procedure for Establishing Bidders Lists," Rev. 3,

5/2/77

PP-3, " Site Procurement," Rev. 2, 6/14/77

PP-4,

Inquiry Issuance," Rev. 2, 6/14/77

PP-5, " Proposal Evaluation and Supplier Selection," Rev. 2,

5/16/77

PP-6, " Procedures for Purchase Order Preparation, Changes,

Approval and Issuance," Rev. 3, 3/2/78

PP-7, " Procedure for Expediting and Procurement Status

Reports," Rev. 2, 6/14/77

PP-8, " Training," Rev. 2, 6/6/77

PP-9, " Preparation of Procedures," Rev. 2, 8/16/77

PP-10, " Power Plant Construction Procurement File System

and File Control," Rev. 5, 9/14/77

PP-ll, " Document Review," Rev. 2, 4/20/77

PP-12, " Document Control," Rev. 1, 4/20/77

PP-13, " Procedure for Processing Purchase Order Acknowledge-

ments," Rev. 3, 5/17/76

The IE inspector was informed that site procurement procedures we're

being developed.

These procedures will be reviewed during a future

inspection.

No deviations were identified except as noted in paragraph 4

related to training.

,

-4-

b.

Review of Procurement Activities

The IE inspector was informed that major procurement activities

in progress were related to reactivation of procurement actions

that were deactivated with the deferral of the Allens Creek

proj ect.

The following documents were selected for review to

detennine if procurement activities were conducted in accordance

with PSAR commitments and established precedures:

Purchase Order File No. AC-2013 for 125 volt batteries

Inquiry File No. HOU 5204 for containment piping penetra-

tions

Inquiry File No. HOU 5207 for centrifugal pumps

Documents related to a field construction cohtract for

concrete supply

The IE inspector was informed that the field construction contract

for concete supply was being processed by Ebasco in accordance with

Ebasco draft procedure ASP-4, " Field Construction Contracts," dated

May 16,1978, which has been submitted to HL&P for review but has

not yet been approved. The IE inspector informed the applicant

that processing procurement documents ir, accordance with an un-

approved procedure constitutes a deviation from commitments con-

tained in Section 17.1.5B of the PSAR and HL&P Procedure PP-3,

" Site Procurement."

During discussions with applicant purchasing representatives, the

IE inspector was informed that, for new procurements,10 CFR Part 21 requirements will be included in the terms and conditions of the

purchase orders and in the codes and standards sections of the

specifications.

Part 21 requirements will be included in old pro-

curements by issuing supplements to the purchase orders.

Implemen-

tation of 10 CFR Part 21 requirements for Allens Creek is addressed

in Allens Creek Project Directive AC-PDIR-01, which directs the use

of Nuclear Division Procedure NDP-130, " Procedure for Reporting

Design and Construction Deficiencies, Noncompliances, and Defects

to the NRC," for evaluation of reportable defects and deficiences.

The IE inspector observed that Part 21 notices were posted at

several conspicuous locations in the applicant's office buildings.

The procurement document related to concrete supply was observed

to contain Part 21 requirements.

-5-

c.

Vendor Surveillance

The IE inspector reviewed the applicant's vendor surveillance

activities to determine whether they were performed in accordance

with PSAR commitments and HL&P Procedure QAP-3, " Procedure for

Vendor Surveillance," Rev. 2, dated August 16, 1976. The IE

inspector was informed that HL&P is performing vendor surveillance

for NSSS items and that Ebasco has been assigned responsibility

for surveillance of most of the balance of plant items. The

planned vendor surveillance by the applicant is patterned after

that being used for another of the applicant's nuclear facilities.

The IE inspector also reviewed the notification lists for NSSS

equipment and the following vendor surveillance reports:

CBI-205-8998-1, Chicago Bridge and Iron, Nuclear, performed

February 8-9, 1978

AD-AG445-1, Anchor Darling Valve Company, performed

March 3, 1978

AD-AG445-2, Anchor Darling Valve Company, performed

April 11, 1978

AD-AG445-3, Anchor Darling Valve Company, performed

June 13-14,1978

The IE inspector observed that the format used to report the

above vendor surveillance activities was not consistent and

that Procedure QAP-3 refers to " Vendor Surveillence Report

Forms, Attachment A"; however, " Attachment A" v:as not included

with the procedure nor was it adequately described therein.

The applicant was informed that failure to provide " Attachment

A" or to adequately describe the report format was a deviation

from commitments contained in Section 17.1.5A of the Allens

Creek Quality Assurance Plan.

3.

Audits and Corrective Actions

-

The IE inspector reviewed the applicant's audit program to ascertain

whether audits were performed in accordance with commitments contained

in PEAR Section 17.1.18A and requirements in Procedure QAP-5, " Audit

Procedure," Rev. 4, dated February 1, 1978.

The following audit reports were reviewed:

HL-56, Audit of HL&P Engineering Department, Civil Division,

performed March 20, 1978

.

-6-

HL-57, Audit of HL&P Power Plant Engineeritig and Construction.

Engineering Division, performed July 20-21, 1978

ES-6, Audit of Ebasco records for Allen Creek, performed

October 12, 1976

ES-7, Audit of Ebasco QA Engineering Department, performed

July 6-7, 1977

ES-8, Audit of Ebasco QA internal audit system, performed

November 30 - December 2, 1977

ES-9, Audit of Ebasco QA vendor evaluation system, performed

May 26-27,1978

GE-9, Audit of General Electric Purchasing, perfomed

February 23-24, 1977

GE-10, Audit of General Electric Engineering and Product QA,

performed August 9-11, 1977

GE-li, Audit of General Electric QA program for procurement,

performed November 1-3, 1977

GE-12, Audit of General Electric QA program for design and

engineering, perfomed March 6-9, 1978

The IE inspector also reviewed corrective actions related to the reports

listed above.

No deviations were identified.

4.

Quality Assurance Indoctrination and Training .l./

The Houston Lighting & Power Company (HL&P) Quality Assurance Program

Manual (QAPM) implementation was reviewed by the IE inspector with

specific attention made to that section of Criterion II of 10 CFR 50, .

Appendix B which requires that the quality assurance program provide

for the indoctrination and training of personnel performing activities

affecting quality as necessary to assure that suitable proficiency is

achieved and maintained. The quality assurance program established

by HL&P is documented by written policies, procedures and instructions

contained or referenced in the QAPM, in Departmental Procedures and in

the Project Quality Assurance Plan (PQAP).

1/This portion of the inspection was performed under the direction of the

project inspector.

-7-

The Departmental Procedures were reviewed by the IE inspector for

confomance with Section 1.5 of the QAPM.

This section, entitled,

" Quality Assurance Indoctrination," delegates to the Quality Assurance

Department the responsibility for conducting an indoctrination for

new or transferred employees coming into departments where the em-

ployee's function within the department falls under the purview of the

QAPM.

The indoctrination is aimed at familiarizing the employee with

quality assurance, stressing the importance and meaning of quality

assurance as it applies to the employee's r.ew position.

The following Departmental Procedures were reviewed:

Civil Engineering Department Procedure 5.0, " Civil Design Training

a.

Program," Revisica 1.

b.

Nuclear Division Procedure NDP-50, " Nuclear Division Personnel

Training," Revision 2.

Environmental Protection Department Procedure NPSG-20, " Training

c.

and Continuing Education Program," Revision 3.

d.

Power Plant Engineering & Construction (PPE&C) Department,

Electrical Engineering Section Procedure EES-1, " Procedure for

Electrical Engineering Section Personnel Indoctrination, Train-

ing, and Continuing Education," Revision 5.

e.

PPE&C Department, Mechanical Engineering Division Procedure

MED-6, " Indoctrination, Training & Continuing Education,"

Revision 2.

f.

Quality Assurance Department Procedure QAP-2, " Procedure for

Qualification & Certification of Surveillance Personnel,"

Revision 2.

g.

Purchasing Department Procedure PP-8, " Training," Revision 2.

h.

Power Plant Construction Division Procedure PPC-3, "Indoctri-

'

nation and Training," Revision 1.

i.

Systems Engineering Procedure SYSE-70, " Training and Continuing

Education Program," Revision 1.

j.

Projects Division Procedures Manual.

-8 -

With the exception of f. and h., the listed procedures make no mention

of a Quality Assurance indoctrination as required by the QAPM and as

defined in Section 17.1.2A of the Allens Creek PSAR.

The definition

specifically stipulates that, "The Quality Assurance indoctrination

will be conducted by the Manager - QA or his designated representative."

Procedure f. addresses itself to the Quality ,hsurance department but

does not contain provisions for interdepartmental indoctrinations.

Section 1.5.3 of the QAPM states in part, "The Department Procedures

contain specific courses of action that establish the scope and

definition of the training program as well as indicating the frequency

requirements for retraining." The training involved follows the basic

QA indoctrination :ind is provided by each Department / Division in their

appropriate discipline areas to assure that suitable proficiency is

achieved and maintained.

It was verified by the Manager, QA, that the

defined training was not being provided.

The listed procedures do not address the requirement for retraining.

In the case of item j., a procedure does not exist to satisfy the

training and indoctrination requirements of the QAPM.

The failure to address the Quality Assurance indoctrination and the

retraining frequency requirement constitute a deviation from the PSAR

as expressed in the QAPM.

5.

Site Procedures and Staffing ]

2

The status of the HL&P Site Quality Assurance Procedures was discussed

with the HL&P Site Quality Assurance Manager.

Seven procedures have

been drafted and await review and approval.

Projected site staffing

of HL&P QA personnel was also discussed.

It is expected that three

civil engineers, three mechanical engineers, and three electrical

engineers will perform surveillance for HL&P during the construction

phase of the project.

The Ebasco QA Site Supervisor and Senior Resident Engineer were inter-

viewed for the purpose of establishing the status of site procedures

and staffing requirements.

Detailed Administrative Site Procedures,

Construction Site Procedures, and Quality Control Procedures are being

developed under the direction of the manager or supervisor responsible

!!This portion of the inspection was performed under the direction of the

project inspector.

_9_

s

s

gy,

ig,q y

,,,;g/,+p

'k,g,ge,

4

_E EmeA1,em

TEST TARGET (MT-3)

1.0

23

28

-

'32

p:ll 2 2

xm

33

,

.

P

I l.25

1.4

i

l

1.6

6"

>

MICROCOPY RESOLUTION TEST CHART

f

%

'

/?l3%

't?hh

,,

_. __

_

a

, .y,

.

.

,

.

,

e

,

'

,

\\ ._

..___. .

i,

-

, _ . _ _ . _ _ _ _ _ _ . ,

I

for their administration.

The preparation schedule for each category

of procedure was reviewed by the IE inspector.

As of this inspection,

no approved procedures were available for review.

Site staffing is

expected to involve ten QA and sixty-four QC personnel at the peak level

of activity in 1982.

Positior, requirements by discipline were identified

and reviewed.

fio deviations were identified.

6.

Field Change Requests _/

3

A review was conducted of the methods established by HL&P Puwer Plant

Constr! ction (PPC) Division for the control, review and approval of

changes identified at the construction site that modify or clarify the

established scope of work, design configuration, specifications or

Bills of Material. The PPC Division Procedure PPC-2, " Field Changes,"

Revision 1, sets forth the methods for the processing of field change

requests (FCRs) by the PPC Division so as to " ensure that appropriate

change and design control measures commensurate with those applied

to the original design are utilized."

Included in the scope of the

procedure are changes covered by nonconformances, by fiRC Reguladon

changes, and changes identified by HL&P engineers.

FCRs are reviewed

jointly by the Ebasco Site Chief Engineer and the PPC Project Engineer

to determine whether the recommended change needs Ebasco home office

engineering review. The criteria to be used in determining the re-

quirement for Ebasco home office review are listed in the procedure

and were reviewed by the IE inspector.

If the FCR does not require the Ebasco home office engineering revir:w,

as established using the criteria listed in the procedure, the review

is required to be conducted by the PPC Project Engineer and the Ebasco

Site Chief Engineer.

The procedure states that, "upon agreement with

the recommended disposition (or alternate), the PPC Construction

Supervisor will sign the FCR indicating concurrence with the recom-

mended disposition and authorization for implementation of the change."

Attached to the procedure is an example FCR which contains several

concurrence signature lines, one of which is designated as the Quality

Assurance Department.

This item, on the FCP form ,is not addressed in

the prccedure.

The stipulation of authorization by the PPC Construction Supervisor,

for implementation of field changes, is considered an unresolved item

due to the lack of correlation between the procedure and the example

form with respect to a concurring review by the Quality Assurance

~

Department.

fio deviations were identified.

2/ his portion of the inspection was performed under the direction of the

T

project inspector.

-10-

7.

Design Control

Design, design analysis and design verification are performed by

Ebasco (A/E) and General Electric (NSSS) and are audited by HL&P QA

Department. The system of controls governing design activities, for

which Ebasco is responsible, is described in the Ebasco NJClear Quality

Assurance Program Manual.

HL&P engineering functions for review of

the finished design are accomplished utilizing the methods described

in the Allens Creek Quality Assurance Plan.

Documents reviewed in regard to design control by HL&P included:

ACitGS PSAR, Section 3.2, " Classification of Structures, Com-

ponents and Systems," and Section 17.0, " Quality Assurance";

including 17.1.l A.2, "Other HL&P Departments Having Quality

Related Functions"; 17.1.l A.3.1.1, " Design Review Committee";

and 17.1.3A, " Design Control."

HL&P QA Manual, Section 2.0, " Organization," Rev. No. 5, 12/1/76;

Section 4.0, " Engineering," Rev. No. 2, 12/1/74; and Section 5.0,

" Construction and Fabrication."

HL&P Allens Creek Quality Assurance Plan, Section 4.0, " Engineering,"

Rev. No. 1, 2/1/78.

UL&P, " Outline of Procedures - Civil Engineering," Civil Design

Section, Rev. No. 1, 1/ 31/ 75.

Ebasco Nuclear Quality Assurance Program Manual, Section QA-I-4,

" Design Control," Rev. No. 1, 8/11/77.

a.

Document Review

The responsibility for conducting review of design documentation

within HL&P is assigned to the QA, Power Plant Engineering &

Construction (PPE&C) and the Engineering Departments.

The Manager, Nuclear Division of PPE&C is responsible for con-

'

ducting review of the NSSS; the Manager, Engineering of PPE&C

is responsible for conducting review of B0P and TG; the Manager,

Engineering Design and Development of the Engineering Depart-

ment is responsible for conducting review of the switchyard,

transformers,and generator as related to the transmission

system; and the Manager, Civil Engineering of the Engineering

Department is responsible for conducting review of the site

structures and buildings.

.

-11-

Within Ebasco, the various engineering departments are responsi-

ble for design review and verification.

For example, QA engineer-

ing performs independent reviews of specifications and drawings

to assure that appropriate quality requirements have been included,

and fluclear Licensing performs a review of safety related drawings

and specifications for compliance with flP,C regulations, the SAR

and Regulatory Guides.

The Division Managers within the engineering departments, who are

responsible for technical review of system, component or struc-

ture designs, are responible for ensuring that the system, compo-

nent or structure is included on a Design Review Requirements

List (DRRL).

On approval of the DRRL by the Design Review Committee, a

designated cognizant engineer (review coordinator) coordinates

review of the assigned system, component or structure within

the responsible engineering division.

Technical reviews are normally delegated to Principal or Super-

vising Engineers or other qualified personnel.

One of these is

usually designated as Review Coordinator.

Consultants may be

required to perform selected reviews.

The method for engineering review, approval and release of

design documents by HL&P is established in Project Division

Procedure fio. PP-5.0, " Design Review Procedure," Rev. No. 4,

9/23/77.

The design documents are transmitted to the review

coordinators and reviewers.

A cover sheet, Information Trans-

mittal Sheet, is attached which designates the review coordi-

nator, reviewers and action date for the review.

Also, a form

document, Document Review Sheet, is included for use in conveying

comments from the reviewer to the review coordinator and to

document final action on the design document.

In the case of the latter form document, it was observed by the

IE inspector, that although the form was referenced, it was not

appended to the reference procedure so as to receive the same

review and approval as the procedure.

Consequently, the form

document did not have review and approval status.

The IE inspector concluded that use of the unapproved forms was

in deviation to commitments contained in Section 1.6.2 of the

PQAP and Section 17.1.5A of the PSAR.

-12-

.

PQAP 4.5.4 requires that a Design Review Worksheet (DRW) be

completed by the cognizant engineer and updated as additional

or revised drawings are received.

The DRW is utilized during

_

the conduct of review.

The IE inspector reviewed DRRLs and DRWs of the Nuclear and

Mechanical Engineering Divisions of BPE&C and the Civil Engineer-

ing Division of the Engineering Department.

It was observed, during procedure review of the Nuclear and

Systems Engineering QC Manuals, that no formal procedure exists

to control the maintenance and use of the Design Review Worksheet.

The PQAP, Section i.6.2, requires that the managers of the HL&P

Departments who perform quality related activitier ire required

to develope written procedures necessary to implement the re-

quirements contained in the PQAP.

The IE inspector pointed out that failure to provide a procedure

for maintenance and use of the DRW is a deviation to commitments

contained in Section 1.6.2 of the PQAP and 17.1.5A of the PSAR.

During the review of the document review procedures of the Civil

Engineering Division of the HL&P Engineering Department, it was

observed that the procedures being utilized had not been approved.

The IE inspector informed the responsible engineers that failure

to utilize approved procedures during document review is a

deviation to commitments contained in Section 1.6.2 of the PQAP

and Section 17.1.5A of the PSAR.

b.

Design Change Control

(1) Design Change

The method by which design changes are reviewed and approved

is established in Section 4.7 of the PQAP.

The responsibility for controlling design changes to safety

related systems, components and structures is the same as

design review responsibility.

Design control measures

applied to design changes are required to be the same as

those for the original design.

The category of the design change document is identified by

the Review Coordinator who initiates a Design Change Control

Worksheet.

The Review Coordinator then reviews and obtains

approval for the design change.

-13-

.

The IE inspector reviewed the implementing procedures of HL&P

and Ebasco.

Nt deviations were identified.

(2)

Field Change

The methods for processing field change requests are identi-

fied in PPE&C Procedure PPC-12, " Field Changes," Rev. No. 1,

1/13/77.

Field changes identified during construction or testing

are processed utilizing a Field Change Request (FCR)

form.

FCRs may be initiated by HL&P or construction

personnel.

No deviations were identified.

c.

Audits

Two internal audits of HL&P were reviewed:

(1) QA audit of the Engineering Division of the PPE&C Depart-

ment on July 27-28, 1978.

It was observed by the IE

inspector that five audit deficiences were identified by

the auditors.

Acknowledgement and proposed corrective

and recurrence action were requested by September 5,1978.

(2) QA audit of the Civil Engineering Division of the HL&P

Engineering Department. One area of concern was identified.

A target date for corrective action was June 15, 1978.

The corrective action was inspected by the IE inspector during

inspection of these divisions.

No deviations were identified.

8.

Unresolved Items

-

Unresolved items are matters about which more information is required

in order to ascertain whether they are acceptable items, items of

noncompliance, or deviations.

An unresolved item disclosed during

the inspection is discussed in paragraph 6.

-14-

.

-

.

^

Exit Interview

The IE inspectors met with applicant representatives (denoted in

paragraph 1) at the conclusion of the inspection on August 1,1978.

The IE. inspectors summarized the purpose and scope of the inspection

and the findings.

An applicant representative acknowledged the

inspectors' findings concerning the deviations (paragraph 2, 4 and 7)

and the unresolved item (paragraph 6).

.

<

d

e

-15-