i VraornzA EI.ECTRIC AND Powns COMPAFfY Racuwonn.Vamorw xA 2026 October 11, 1978 Mr. James P. O'Reilly, Director Serial No. 550/091978 Office of Inspection and Enforcement POSM/DLB:sej U. S. Nuclear Regulatory Cor: mission Docket No.
50-338 Region II License No.
NPF-4 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
We have reviewed your letter of September 19, 1978 in reference to the inspection conducted at North Anna Power Station on July 17-28, 1978 and reported in IE Inspection Report No. 50-338/78-21. Our response to the speci-fic violation is attached.
We have determined that no propr1 *ary information is contained in the report.
Accordingly, the Virginia Electric and Power Company interposes no objection to the inspection report being made r. matter of public disclosure.
Very truly yours, d. 7 n. J w L[
C. M. Stallings Vice President-Power Supply and Production Operations Attachment ee:
Mr. Albert Schwencer g,21a El M N g/o/3 IW m o 3 3 0_-a r e itt ytth!6
.'7
- 1. 14010 s,-
RESPONSE TO VIOLATION LISTED IN IE INSPECTION REPORT No. 50-338/78-21 NRC COMMENT that Unit 1 Technical Specification 6.9.1.9 requires, in part, written reports of the types of eve'nts listed in that specification be submitted to the Director of the Regional Office within 30 days of the Similarly, Specification 6.9.1.8 requires occurrence of the event.
that written reports for evente of the types in that specification be submitted within 14 days of the event occurrence.
Contrary to the above, eleven of the first thirty-eight Licensee Event Reports for calendar year 1978 were submitted from one to four days Three of these were 14 day reports and eight were later than requited.
30 day reports.
This is an infraction.
RESPONSE
Corrective steps which have been taken by the licensee and the 1.
results achieved:
Internal review and routing in the corporate office has been reduced in the pre-transmittal stage of LER preparation such to the NRC that finalized reports now are prepared and sent on or before the date required.
Additionally, the corporate office has developed a schedule f or LER preparation, SNSOC review and corporate of fice handling.
This schedule is a guideline and will further imor n e the ability to meet the appropriate transmittal date.
2.
Corrective steps which will be taken:
No future corrective steps are required at this time.
3.
The date when full compliance will be achieved:
Full compliance has been achieved.
d