Forwards IE Bulletin 79-23, Potential Failure of Emergency Diesel Generator Field Exciter Transformer. Action Required
ML19254B323
Person / Time
Site: Waterford 
Issue date: 09/12/1979
From: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Aswell D
LOUISIANA POWER & LIGHT CO.
References
NUDOCS 7909270313
Download: ML19254B323 (1)


Text

-.

UNITED STATES

[An arov,#'o,^

NUCLEAR REGULATORY COMMISSION

()/

l' 'i REGION IV 7

o 611 RY AN PLAZA DRIVE, SUITE 1000 5, '

/.:. j ARLINGTON, TEXAS 76012

  • s; - )

September 12, 1979 In Reply Refer To:

RIV Docket No.

50-382/IE Bulletin No. 79-23 Louisiana Power and Light Co.

ATTN:

Mr. D. L. Aswell Vice President of Power Production 142 Delaronde Street New Orleans, Louisiana 70174 Gentlemen:

Enclosed is IE Bulletin 79-23 which requires action by you uith regard to your power reactor facility with an operating license or a construction permit.

Should you have questions regarding this IE Bulletin or the actions required of you, please contact this office.

Sincerely,

/

r

+

,7fg[1 ;. g /

'l as ' <

t Karl V. Seyfrit Director f

Enclosures:

1.

IE Bulletin No. 79-23 2.

List of IE Bulletins Issued in the Last Six Months 7909270 4

1046 060

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 IE Bulletin No. 79-23 Date:

September 12, 1979 Page 1 of 3 POTENTIAL FAILURE OF EMERGENCY DIESEL GENERATOR FIELD EXCITER TRANSFORMER Description of Circumstances:

Florida Power and Light Company recently reported a problea encountered during a 24-hour full load test of the emergency diesel generators (EDG) at their Turkey Point facility. Approximately 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> into the test, the A-EDG tripped due to a differential-relay lockout on B and C phases; the B-EDG was manually stopped, thus interrupting the test at that point in time.

Subsequent investigation and testing by the licensee revealed a design error on both the A and B EDGs which resulted in overheating of the Exciter Power Transformers (EPTs) at sustained high load operation.

The following nameplate data applies to the equipment installed at Turkey Point:

Emergency Diesel Generator General Motors (Electro-Motive Division)

Model EMD-999-20 Engine-turbocharged, 2 cycle, EMD design 20-645E4 Generator-EMD-design Model A-20 Exciter Power Transformer GE-single phase Model-9T24Y1004 Serial-MD Cycles-60 KVA 15 Insulation-4160 V The cianufacturer's findings and recommendations regarding the above problem are described below:

um "A potential problem can exist if the nc DUPLICATE DOCUMENT the primary windings of the excitation I to as the control power transformer (CP']

Entire document previously entered into system under:

b ANO 1046 oft m

No. of pages: