ML19253C564
| ML19253C564 | |
| Person / Time | |
|---|---|
| Site: | Braidwood |
| Issue date: | 10/23/1979 |
| From: | Clint Jones, Schweibinz E, Williams C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | |
| Shared Package | |
| ML19253C554 | List: |
| References | |
| 50-456-79-12, 50-457-79-12, NUDOCS 7912060063 | |
| Download: ML19253C564 (7) | |
See also: IR 05000456/1979012
Text
.
.
.
U.S. NUCLEAR REGULATORY COMMISSION
-
OFFICE OF INSPECTION AND ENFORCEMENT
.
REGION III
4C7
Report No. 50-456/79-12; 50- % 9/79-12
yn
9I7
,
Docket No. 50-SCb"', 50-547
Lice.. e No. CPPR-132; CPPR-133
Licenste:
Commonwealth Edison Company
P. O. Box 767
Chicago, IL 60690
Facility Name:
Braidwood Nuclear Power Station, Units 1 and 2
Inspection At: Braidwoon Site, Braidwood, IL
Inspection Conducted:
September 25-28, 1979
f. [ ' < ': , ( c
,u u
Inspectors:f
'E. R. Schweibinz
// !2 ~~'/ k,
i
,
( ' . -),
x ,_
7.---
-
C. E. Jones
11 h :,' / ~' ')
/
p,Q ' ;, r
. --
Approved By:
C. C Williams, Chief
// N .T'/)
Projects Section 2
'
Inspection Summary
W7
Inspection on September 25-28, 1979 (Report No. 50-456/79-12; 50- % 7/79-12)
Areas Inspected:
Quality assurance plans and procedures for extended
shutdown; storage of equipment; site staffing considerations; extended
shutdown QA implementing procedures; extended shutdown work activities;
and storage of steam generators.
The inspection involved 54' inspector-
hours by two hTC inspectors.
Results: Of the four areas inspected, no items of noncompliance or
deviations were identified in three areas.
One apparent item of noncom-
pliance was identified in one area (Infraction - failure to have procedures
for the control of safety related activities during the extended shutdown -
Section I, Paragraph 1).
1509
298
29 ao co OO
.
.
.
.
DETAILS
Persons Contacted
Commonwealth Edison Company (CECO)
R. Cosaro, Project Superintendent
,
- J. T. Merwin, Lead Mechanical Engineer
- J. W. Schlunz, Lead Structural Engineer
- R. J. Parr, QA Engineer
- J. A. Homoly, QA Supervisor
- H. T. Cobbs, QA Engineer
- S. L. Gaconis, QA Engineer
- W. Carlsen, Construction Supervisor
- R.
C. Schleiter, Administrative Assistant
- N. P. Tomis, QA Engineer
W. Casillo, Engineer, Station Construction
Napoleon Steel
C. Zaveda
Westinghouse Electric Corporation (W)
R. E. Shoults, W Site Manager
L. K. Comstock and Company Inc.
M. R. Williams, QA/QC Manager
'
- Denotes those present at the exit meeting.
The inspectors also contacted and interviewed other licensee and contractor
personnel including craftsmen, QA/QC, technical and engineering staff
members.
Functional or Program Areas Inspected
Details of functional or program areas inspected are documented in Sections
I and lI as follows.
-2-
1509
799
.
.
.
Section I
Prepared by E. R. Schweibiuz
Reviewed by C. C. Williams, Chief
Projects Section 2
s
1.
Quality Assurance Plans and Procedures for Extended Shutdown
The RIII inspector inquired if an overall QA plan and implementing
procedures had been developed for this extended shutdown. The
licensee stated that they had not yet developed a plan or procedures
for these activities but that it was under consideration. The
inspector inquired if quality related records of the piping contractor
had been turned over to Commonwealth Edison Company (CECO) since a
large number of the people have left the site.
(Construction workers
on site on September 13, 1979 - 1750, September 17, 1979 - 46L,
September 21, 1979 - 342 people). The licensee stated that the
piping contractor had not turned over any of these records as yet.
When asked if any of the contractors had turned over quality related
records, the licensee stated that the electrical contractor,
L. K. Comstock and Company, Inc., had turned over a portion of their
quality related records.
The document that was used for this turnover, dated September 17,
1979, was reviewed by the RIII inspector.
Subject:
L. K. Comstock
and Company, Inc. and E. C. Ernst, Documentation.
The cover letter
reads as follows, "The attached inventory of L. K. Comstock and
Company, Inc. and E. C. Ernst documentation lists documents turned
over to Commonwealth Edison Company; except for drawings and equipment
storage surveillances." It was prepared and accepted by a Quality
Assurance Engineer for CECO and was accepted by the Quality Assurance
and Quality Control Manager for L. K. Comstock.
A handwritten note
on the cover page to the inventory stated, "This documentation is to
be kept in locked file cabinets maintained in the L. K. Comstock
Office Building." The RIII inspector did a random verification of
some of the documents in this inventory.
Results of this verification
indicated that not all of the documentation listed in September 17,
1979, was located in the file cabinets maintained in the L. K. Comstock
Office Building. Seven documents listed on the inventory had been
turned over to the Station Construction Department after the completion
of the inventory and without knowledge of the quality assurance
department.
In addition, at least four other documents were not
located in the file cabinets, but were in the general vicinity,
although they were listed on the inventory. This lack of control of
these documents further indicates that procedures are needed for the
control of these activities.
-
-
1509
500
.
.
.
This failure to have plans and procetires to control these safety
related activities is an item of noncompliance with 10 CFR 50,
Appendix B, Criterion V.
(456/79-12-01; 457/79-12-01)
2.
Storage of Equipment
The RIII inspectors took an extensive tour of the site to observe
storage of equipment in place.
A problem was identifi:J during this
,
tour in that the storage of the reactor coolant pump motors was
-
inadequate.
Several motors did not have their motor winding heaters
energized and they had not been rotated on a weekly basis as required
by the manufacturer's instructions. These problems were corrected
in a timely manner by the licensee.
No items of noncompliance or deviations were identified.
3.
Site Staffing Considerations
The ultimate size of the site staff during the extended shutdown has
not been clearly established. NRC is concerned relative to the
ad2quacy of the size of the surveillance staff, and will pursue this
issue during subsequent inspection. This matter is unresolved.
(456/79-12-02; 457/79-12-02)
No items of noncompliance or deviations were identified.
.
-4-
1509
301
.
.
"
Section II
Prepared by C. E. Jones
Reviewed by C. C. Williams, Chief
Projects Section 2
s
1.
Extended Construction Delay - Review of Quality Assurance Implementing
Procedures
The inspector reviewed a general procedure, " Commonwealth Edison
Company - Phillips, Getchow Company Quality Assurance Interface for
Requisitioning, Purchasing and Receiving Material", BM-101, Revision 2,
dated April 18, 1979. The stated purpose of the procedure was to
clarify responsibilities for the purchase, receipt and storage of
ASME,Section III materials, parts, components, and the control of
the associated documentation as required by Section III.
The licensee was informed that the lack of such an approved QA
Program was considered to be an element of noncompliance as identified
in Section I of this report.
2.
Extended Construction Delay - Observation of Work and Work Activities
The inspector reviewed the storage of Category I heat exchangers and
compared storage conditions with those recommended by y in their
Instruction Manual for Auxiliary Heat Exchanges.
In addition, the
storage recommendations were revieved for the steam generators. The
licensee stated QA Procedures were being reviewed and revised to
meet manufacturer's recommendations and owner's requirements.
The
licensee agreed to document these instances where manufacturer's
recommendations were not followed.
In general, storage condition for the heat exchangers, met y recommenda-
tions. The majority of the heat exchangers have been mounted on
pe rmanent foundations and piping connections completed. The heat
exchangers observed by the inspector are listed below.
The licensee stated that present plans include closing the turbine
building and temporary openings in the containment and auxiliary
buildings prior to cold weather.
The heating boiler is being installed
and should be available to supply heat for the turbine and auxiliary
buildings.
Electric heaters are to be installed in the containment
buildings to maintain temperatures of 40 F or higher.
The Category I Heat Exchangers were listed in the y Instruction
Manual Auxiliary Heat Exchangers. This manual included nine general
instructions with "Special Instructions" for specific heat exchangers.
-5-
1509
402
.
.
A
"
The status of the Category I heat exchangers observed by the inspector
is as follows:
a.
Component Cooling Heat Exchanger
W Standard Plant Item No. (S.P.I.N.) CCAHCC
Quantity Supplied 3 each
Manufacturer's Data Sheet AH-CC 654
s
All three units were positioned on permanent pads and all
piping connections had been connected. The layup of these heat
-
exchangers appeared to comply with the suppliers recommendations.
b.
Seal Water Heat Exchangers
W Standard Plant Item No (S.P.I.N.) CSAHSW
Quantity Supplied, 2 each, CCE-one, CDE-one
Manufacturer's Data Sheet AH-SW652
Purchase Order No. CCE-546-CAZ-215333
CDE-546-CAZ-215334
Piping to shell side welded to nozzles.
Flanges to tube side are
protected by plywood and plastic coverings. Exchangers have been
permanently mounted and aligned.
Storage meets manufacturer's
recommendations.
c.
Letdown Reheat Heat Exchanger
,
W Standard Plant Item No. (S.P.I.N.) TRAHLR
Quantity Supplied, 2 each, CCE-one, CDE-one
Manufacturer's Data Sheet AH-LR630
Purchase Order No. CDE-546-CAZ-214814
Heat exchanger mounted in permanent location and final piping
connections completed.
d.
Moderating Heat Exchanger
W Standard Plant Item No. (S.P.I.N.) TRAHHM
Quantity Supplied, 2 each, CCE-one, CDE-one
Manufacturer's Data Sheet AH-M629
Purchase Order No. CCE-546-CAZ-214813
CDE-546-CAZ-214814
The Unit 1 exchanger has been permanently mounted and piping
connections have been completed. The Unit 2, CDE, exchanger
has on pipe connection on the shell side completed by welding.
The remaining three pipe connections have been covered and
sealed.
e.
Residual Heat Exchanger
W Standard Plant Item No. (S.P.I.N.) RHAHRS
quantity Supplied, 4 each, CCE-two, CDE-two
-6-
1509
303
.
.
&
Manufacturer's Data Sheet aS-653
Purchase Order No. 546-CAZ-215353-(CCE)
546-CAZ-215354-(CDE)
National Board No. 840 and 841 (CCE)
842 and 843 (CDE)
All four exchangers were permanently mounted and piping connections
completed.
,
f.
Letdown Chiller Heat Exchanger
.
W Standard Plant Item No. (S.P.I.N.) TRAHLC
Quantity Supplied, 2 each, CCE-one, CDE-one
Manufacturet's Data Sheet AH-LC 631
Purchase Order No. LCE-540-CAZ-214813
CDE-546-CAZ-214814
Exchangers permanently mounted. Shell side piping connections
complete. Tube side flanges protected with plywood plate and
plastic seal one unit CDE. Piping connections complete on unit
CCE, Unit 1.
Unit covered with plastic.
No items of noncompliance or deviations were identified.
3.
Storage of Steam Generators
The four steam generators have been placed in their cells in the
Unit I containment and have been aligned. W issued a " Procedure for
Long Term Storage of Steam Generators and Pressurizers," on September 20,
1979.
The licensee indicated the W recommendations would be followed
or included in the CECO QA procedure for generator lay up.
The inspector observed No. 2 and No. 3 steam generators positioned
in place. No work was in progress on either.
Steam generator No.
1714 that was damaged during the loading operations at Savanna,
Illinois is now identified as steam generator No. I at Braidwood.
No items of noncompliance or deviations were identified.
'
Unresolved Items
Unresolved items are matters about which more information is required in
order to ascertain whether they are acceptable items, items of noncompliance
or deviations.
Unresolved items disclosed during the inspection are
discussed in Section II, Paragraph 3.
Exit Meeting
The inspectors met with the site staff representatives (denoted in the
Persons Contacted paragraph) at the conclusion of the inspction on
September 28, 1979. The inspectors summarized the scape and findings of
the inspection including the one apparent item of noncompliance identified
the Section I, Paragraph 1 of the Details section of this report. The
licensee acknowledged the finding.
-7-
1509
304