UNITED STATES
- pa arouq'o,
NUCLEAR REGULATORY COMMISSION
y\\
,
/
R EGloN IV
,
n
<
o
611 RYAN PLAZA DRIVE, SUITE 1000
..
,
5
L[
ARLINGTON, TEXAS 76012
% ,,, g 8
November 1, 1979
In Reply Refer To:
RIV
Docket No.
50-445/Rpt 79-23
50-446/Rpt 79-22
Texas Utilities Generating Company
ATTN:
Mr. R. J. Gary, Executive Vice
President and General Manager
2001 Bryan Tower
Dallas, Texas 75201
Centlemen:
This refers to the inspection conducted by tk. C. R. Oberg of our staff
during the periods September 27-28 and October 3-4, 1979, of activities
authorized by NRC Construction Permits No. CPPR-126 and 127 for the
Comanche Peak facility, Units No. I and 2, and to the discussion of
our findings with Mr. R. G. Tolson and other members of your staff
at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection con-
sisted of selective examination of procedures and representative records,
interviews with personnel, and observations by the inspector.
Within the scope of the inspection, no items of noncompliance were identi-
fied.
Two new unresolved iteras are identified ir. paragraphs 2 and 5 of the
enclosed report.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC's Public Document Room.
If the report contains any information that you believe to be proprietary,
it is necessary that you submit a written application to this office, within
20 days of the date of this letter, requesting that such information be
withheld from public disclosure. The application must include a full state-
ment of the reasons why it is claimed that the information is proprietary.
The application should be prepared so that any proprietary information
identified is contained in an enclosure to the application, since the
application without the enclosure will also be placed in the Public Docu-
ment Room.
If we do not hear from you in this regard within the specified
period, the report will be placed in the Public Document Room.
79133oo
l
1444 W
.
.
..
._
__
.
Texas Utilities Generating Company
2
November 1, 1979
Should you have any questions concerning this inspection, we will be
pleased to discuss them with you.
Sincerely,
'
,
'gl. C. Seidle, Chief
/ Reactor Construction and
Engineering Support Branch
Enclosure:
IE Inspection Report No.
50-445/79-23
50-446/79-22
cc: w/ enclosure
Texas Utilities Generating Company
ATTN:
Str. II. C. Schmidt, Project !!anager
2001 Lcyan Tower
Dallas, Texas
75201
,
144tt J32