Text
'
L
,
g,
UNITED STATES
ATOMIC ENERGY COMMISSION
DIRECTOR ATE OF REGut.ATORY OPER ATIONS
,
'
. I'
q. sB (. a
" " " '
,
s*
I UCue o: m v e crJ
~_
'
tXfDDWt:COUDCiEMXXXXXXft!t
631 Park Avenue
King of Prussia, Pennsylvania 19406 UAE 8
,074
"
Metropolitan Edison Company
Docket No. 50-289
Attention: Mr. J. G. Miller
License No. CPPR-40
Vice President
Box 542
Reading, Pennsylvania 19603
,
Gentlemen:
This refers to the inspection conducted by Mr. Folsom of this
office on February 19-21, 1974 at Middletown, Pennsylvania of
activities authorized by AEC License No. CPPR-40 and to the
discussions of our findings held by Mr. Folsom with Mr. Guna and
Mr. Stromberg of your staff at the conclusion of the inspection.
Areas examined during this inspection are described in the Regulatory
Operations Inspection Report which is enclosed with this letter.
-
Within these areas, the inspection consisted of selective examinations
of procedures and representative records, interviews with personnel,
and observations by the inspector.
Within the scope of this inspection, no violations or safety
items were observed.
,
In accordance with Section 2.790 of the AEC's " Rules of Practice",
Part 2, Title 10, Code of Federal Regulations, a copy of this
letter and the enclosed inspection report will be placed in the
AEC's Public Document Room.
If this report contains any information
that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to
this office to withhold such information from public disclosure.
Any such application must include a full statement of the
reasons on the basis of which it is claimed that the information
is proprietary, and should be prepared so that proprietary
information identified in the application is contained in a
separate part of the document.
If we do not hear from you in
this regard within the specified period, the report will be
placed in the Public Document Room.
.
, . .
,,
.
.
- . - - - - -
.
.
!
'
-
.
i
-
4
4*
Metropolitan Edison Company
-2-
No reply to this letter is required; however, should you have any
questions concerning this inspection, we will be pleased to discuss
.
them with you.
Sincerely,
f
n
Robert T. Carlson, Chief
Facility Construction and Engineering
Support Branch
Enclosure:
,
RO Inspection Report No. 50-289/ 4-06
.
,
.
.
bec (w/encis):
RO Chief, FS&EB
RO:HQ (5)
DL (4 w/encls plus 9 cys ,of Report Only)
DR Central Files -
RS (3)
.
Local PDR
R0 Files
IrrIE
State of Pennsylvania
.
.
!
.