Text
'$
[)(
"'4 UNITED STATES
[
9[0,,
NUCLEAR REGULATORY COMMISSION i
3
?>
REGloN 111 E
"f 799 ROOSEVELT ROAD f
GLEN ELLYN, ILUNO15 60 eM SEP 17 1979 Docket No. 50-409 Dairyland Power Cooperative ATTN:
Mr. F. W. Linder General Manager 2615 East Avenue - South La Crosse, WI 54601 Gentlemen:
This refers to Reportable Occurrence No. 79-16, dated September 10, 1979 concerning the failure in administrative controls which permitted the low flow scram protection circuit to be bypassed during startup and low power operation between September 7,1979 and September 9,1979.
We understand based on commitments made during our investigation of this incident on September 11 and 12, 1979, that you will take the following actions:
1.
Before the next reactor startup:
Develop and implement startup checklists requiring operator a.
sign off on procedural steps and include a " hold point" re-quiring the Shift Supervisor's approval and sign off before initiation of control rod withdrawal.
b.
Revise Administrative Control Procedure, ACP 02.3, to:
(1) Require the Reactor Plant Log to be initialed by each operator indicating that he has reviewed the plant status; (2) Require that the status of safety circait bypass keys be recorded in the Reactor Plant Log by system name rather than key number.
2.
Before the next safety circuit surveillance test, review and revise as necessary the test procedures and checklists to require the re-turn to normal of any safety circuits bypassed during the test.
3.
Conduct operator training to reemphasize the safety significance of safety circuit bypass and the importance of double checking the status of safety equipment.
1-o 1074 126
.s e10 0 20 82 6+
'n e n sed p e v,-
r e :. s I b.. ', L-i.
s...t....
~. I t.;!1 Dairyland Power Cooperative SE? I I 15:79 If our understanding of your planncd action, as described above, is not in accordance with your actual plans and actions, please contact this office immediately.
Sincerely,
- u _% & ~ ba..
James G. Keppfer Director cc:
Mr. R. E. Shimshak, Plant Superintendent Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TI' Anthony Roisman, Esq.,
Attorney J. J. Shea, NRR 10/4 127