Forwards Sargent & Lundy Final Rept Re Deficiency in Ventilation Stack Reported in LO Delgeorge 790606 Ltr. Restoration of Design Basis Capacity Indicated in Encl Rept Was Initiated in Aug 1979 & Will Be Completed by May 1980
Date released: 09/20/2019 Download: ML19249E793


Investigation of Field Condition of Ventilation Stack Base Ring Girder, Util Informed Sargent & Lundy in Sept 1978 of Crack in Base Ring Girder During Erection of Ventilation Steel Stack.Permanent Repair Scheme Proposed
ML19249E794
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 08/24/1979
From:
SARGENT & LUNDY, INC.
To:
References
Download: ML19249E794 (20)
Forwards Sargent & Lundy Final Rept Re Deficiency in Ventilation Stack Reported in LO Delgeorge 790606 Ltr. Restoration of Design Basis Capacity Indicated in Encl Rept Was Initiated in Aug 1979 & Will Be Completed by May 1980
ML19249E792
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 09/21/1979
From: Delgeorge L
COMMONWEALTH EDISON CO.
To: KEPPLER J G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML19249E792 (1)