Forwards IE Insp Repts 50-454/79-12 & 50-455/79-12 on 790723-26 & Notice of Violation
ML19249E600
Person / Time
Site: Byron  Constellation icon.png
Issue date: 08/18/1979
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
Shared Package
ML19249E601 List:
References
NUDOCS 7910020034
Download: ML19249E600 (2)


See also: IR 05000454/1979012

Text

[ga arcg'o

!

f{

UNITED STATES

8

8'

/g

NUCLEAR REGULATORY COMMISSION

). ,

g .y

c

REGION 111

' ' -

,.

o,

[

799 ROOSEVELT ROAD

,

g

GLEN ELLYN,ILLINolS 60137

  • ...*

AUG 181979

Docket No. 50-454

Docket No. 50-455

Commonwealth Edison Company

ATTN:

Mr. Byron Lee, Jr.

Vice President

P. O. Box 767

Chicago, IL 60690

Gentlemen:

This rr:fers to the inspection conducted by Mr. E. W. K. Lee of this

office on July 23-26, 1979, of activities at Byron Station, Units 1

and 2, authorized by NRC Construction Permits No. CPPR-130 and No.

CPPR-131 and to the discussion of our findings with Mr. G. Sorensen and

others of your staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of a

selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, aa described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201 of

the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office within thirty days of

your receipt of this notice a written statement or explanation in reply,

including for each item of noncompliance: (1) corrective action taken and

the results achieved; (2) corrective action to be taken to avoid further

noncompliance; and (3) the date when full compliance will be acnieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter, the enclosures,

and your response to this letter will be placed in the NRC's Public

Document Room, except as follows.

If the enclosures contain information

that you or your contractors believe to be proprietary, you must apply in

writing to this office, within twenty days of your receipt of this letter,

to. withhold such information from public disclosure. The application

791002 08

,u &

ln

.

Commonwealth Edison Company

-2-

AUG18 g7g

must include a full statement of the reasons for which the information is

considered proprietary, and should be prepared so that proprietary

information identified in the application is contained in an enclosare to

the application.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

i

L

~

Gaston Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A,

Notice of Violation

2.

IE Inspection Reports

No. 50-454/79-12 and

No. 50-455/79-12

cc w/encls:

Gunner Sorensen, Site

Project Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Mr. Dean Hansell, Office of

Assistant Attorney General

.

g

h

'bdC

l4

,