Forwards IE Insp Repts 50-416/78-07 & 50-417/78-07 on 780419-20.No Noncompliance Noted
ML19249E475
Person / Time
Site: Grand Gulf  
Issue date: 04/28/1978
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Stampley N
MISSISSIPPI POWER & LIGHT CO.
Shared Package
ML19249E476 List:
References
NUDOCS 7910010552
Download: ML19249E475 (2)


See also: IR 05000416/1978007

Text

a ntch

UNITEo STATES

[

,

/

m

o

NUCLEAR REGULATORY COMMISSION

1.' 't

",^ #

(

E " ) ,~, 7

g

REGloN il

g

3 ,--

?'

c

230 PE ACHTRE E STRE E T. N W. SUI TE 1217

jC.

  • h~

f

ATL ANTA, GE oRGI A 30303

/[//

os....*/

APR 2 81978

In Reply Refer To:

RII:CRM

50-416/78-7

50-417/78-7

Mississippi Power and Light Company

Attn:

Mr. Norris L. Stampley

Vice President of Production

P. O. Box 1640

Jackson, Mississippi

39205

Gentlemen:

This refers to the inspection conducted by Mr. C. R. McFarland of this

I

office on April 19-20, 1978, of activities authorized by NRC Construction

Permit Nos. CPPR-118 and CPPR-119 for the Grand Gulf Nuclear Station,

Unit 1 and 2 facilities, and to the discussion of our findings held with

Mr. T. R. Reaves, Jr. at the conclusion of the inspection.

(

Arcas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter

and the enclosed inspection report will be placed in the NRC's Public

Document Room.

If this report contains any information that you (or

your contractor) believe to be proprietary, it is necessary that you

make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is

claimed that the informtion is proprietary, and should be prepared

so that proprietary informatic1 identified in the application is

contained in a separate part of the document.

If we do not hear

from you in this regard within the specified period, the report

will be placed in the Public Document Room.

i

\\<

W.

s

7910010 g g

1032 ~;0

P

.

Mississippi Power and Light

-2-

4

, Company

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

[

.- c e

,

C. E. Murphy, Chief

Reactor Construction and Engineering

Support Branch

Enclosure:

RII Inspection Reps rt Nos.

}

50-416/78-7

50-417/78-7

l

cc w/ encl:

Mr. W. L. Nail

Plant Superintendent

P. O. Box 756

l

Port Gibson, Mississippi 39150

(

1032

.'!