Requests That Encl List of Incomplete Licensing Activities Be Marked to Indicate Obsolete Action Items & Priority of Remaining Items.Requests That Updated List Be Submitted within 30 Days
ML19249D473
Person / Time
Site: Hatch  
Issue date: 08/20/1979
From: Ippolito T
Office of Nuclear Reactor Regulation
To: Whitmer C
GEORGIA POWER CO.
References
NUDOCS 7909240711
Download: ML19249D473 (3)


Text

- - - _ _ - __

gn _

o UNITED STATES f

g y p s-,

i g NUCLEAR REGULATORY COMMISSION

., y

,g WASHINGTON,0. C. 20555 August 20, 1979

+

Docket Nos. 50-321/366 Mr. Charles F. Whitmer Vice President - Engineering Georgia-Power Company P. O. Box 4545 Atlanta, Georgia 30302

Dear Mr. Whitmer:

We are in the process of reviewing our projected work load with the intent of updating the licensing backlog.

In order to more efficiently utilize our limited resources, we are attempting to identify those action items which have become obsolete; i.e., either the need for the action has passed, or circumstances now exist which do not warrant the expenditure of resources necessary to accomplish the action.

The attachment to this letter provides a listing from our records of licensing activities which were initiated by you and have not been completed. We would appreciate your assistance in identifying those items which are no longer required and can be deleted. We would consider a formal request to withdraw any application that is.ietermined to be obsolete.

The priority we assign these activities is determined primarily by public safety considerations. However, so that we may give proper consideration to your reeds, it would be helpful if you assign a priority to the remainder of the items according to their importance to you. Also, if the attachment does not contain certain licensing actions you have requested, please identify these by reference or provide copies of your original request.

We would appreciate having the list marked up and returned within 30 days of your receipt of this letter. You may contact your D0R project manager if you have any questions or need further discussion.

Your assistance in this regard is appreciated.

Sincerely, G/

/

W 0 W h % l. (A >

ThomasA/fppolito, Chief Ocerating Reactors Branch G3 Division of Operating Reactors W

Er. clos r e:

.icensc? Recuestad Action Itens for F.cilities:

Hatch 1 and 2 f:r:losure:

Sea cage 2 3 9 09 40 71, p

Mr. Charles F. Whitmer 2-Georgia Power Company cc:

G. F. Trowbridge, Esquire Shaw, Pittman, Potts and Trowbridge 1800 M Street, N. W.

Washington, D. C.

20036 Ruble A. Thomas Vice President P. O. Box 2625 Southern Services, Inc.

Birmingham, Alabama 35202 Mr. Harry Majors Southern Services, Inc.

300 Office Park Birmingham, Alabama 35202 Mr. William Widner Georgia Power Company Power Generation Department P. O. Box 4545 Atlanta, Georgia 30302 Mr. L. T. Gucwa Georgia Power Company Engineering Departm.ent P. O. Box 4545 Atlanta, Georgia 30302 Appling County Public Library

'arker Street Baxley, Georgia 31413-th. R. F. Rogers U. S. Nuclear Regulatory Commission P. O. Box 710 Baxley, Georgia 31513 S\\%

99%

~

LICENSEE INITIATED AMENDMENT REQUESTS HATCH NUCLEAR PLANTS UNIT 1 AND 2 Date of Unit Title Application 1

APRM Rod Block and Scram Curves 5/8/75 1/2 Core Maximum Fraction of Limiting 10/18/78 and Power Density 6/5/79 1

End-of-Cycle RPT 3/22/79

~

1/2 Spent Fuel Pcol Capacity 7/9/79 1/2 Annual Environmental Report 7/12/79 2

Administrative Changes 7/19/79 2

Drywell-Suppression Chamber Vacuum Breakers 7/27/79 1

Overhead Crane Specs 9/15/79

.