Forwards IE Insp Repts 50-010/79-09,50-237/79-16 & 50-249/79-14 on 790601-30.No Noncompliance Noted
ML19249C851
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 07/19/1979
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
Shared Package
ML19249C852 List:
References
NUDOCS 7909190202
Download: ML19249C851 (2)


See also: IR 05000010/1979009

Text

kR RIC

  1. '
  • o

UNITED STATES

[lC

-

!" 3 g [ g

NUCLEAR REGULATORY COMMISSION

g .'

/, e

REGION til

A

o,

799 Roo?FVELT ROAD

'%#

GLEN ELLYN,ILLINolS 60137

o

  • ...+

JUL 191979

Docket No. 50-10

Docket No. 50-237

Docket No. 50-249

Commonwealth Edison Company

ATTN:

Mr. Byron Lee, Jr.

Vice President

Post Office Box 767

Chicago, IL 60690

Gentlemen:

This refers to the inspection conducted by Messrs. J. L. Barker and

L. D. McGregor of this office on June 1-30, 1979, of activities at

Dresden Tuclear Power Station, Units 1, 2 and 3, authorized by NRC

Operating Licenses No. DPR-2, No. DPR-19 and No. DPR-25 and to the

discussion of our findings with Mr. B. B. Stephenson and others of your

staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of a

selective examination of procedures and representative records, observa-

tions, and interviews with personnel.

No items of noncompliance with NRC requirements were identified during

the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room, except as follows.

If this report contains information that you or

your contractors believe to be proprietary, you must apply in writing to

this office, within twenty days of your receipt of this letter, to withhold

such information from public disclosure. The application must include a

full statement of the reasons for which the information is cortidered

proprietary, and should be prepared so that proprietary informacion

identified in the application is contained in an enclosure to the application.

.

e

y

b

' ' "

3J

7 9 G 919 016)

.

.

Commonwealth Edison Company

-2-

'JUL 191979

.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

[et

a

R. F. Heishman, Chief

Reactor Operations and

Nuclear Support Branch

Enclosure:

IF Inspection

Reports No. 50-10/79-09,

No. 50-237/79-16 and No.

50-249/79-14

cc w/ encl:

Mr. B. B. Stephenson,

Station Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Anthony Roisman, Esq.,

Attorney

Mr. Dean Hansell, Office of

Assistant Attorney General

.

O

y

t; b 3