Forwards IE Insp Repts 50-329/79-13 & 50-330/79-13 on 790402-30 & Notice of Violation
ML19248D328
Person / Time
Site: Midland
Issue date: 05/30/1979
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Howell S
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML19248D329 List:
References
NUDOCS 7908150614
Download: ML19248D328 (2)


See also: IR 05000329/1979013

Text

'

.

,

6m 8809

UNIT E D STATES

f$

,

NUCLEAR REGULATORY COMMISSION

,

f, Q(

j

nEcios m

799 ROOSEVELT aO AD

f

.

  1. .*

,[

GL EN E LLY N. A LLINO'S 60937

%,

p

.....

RAY 3 01979

Docket No. 50-329

Docket No. 50-330

Consumers Power Company

ATTN:

Mr. Stephen H. Howell

Vice President

1945 West Parnall Road

Jackson, MI 49701

Gentlemen:

This refers to the inspection conducted by Mr. R. J. Cook during the

period of April 2-30, 1979, of activities at the Midland Nuclear

Power Plant Construction Site authorized by NRC Construction Permit

No. CPPR-81 and CPPR-82 and to the discussion of our findings with

Messrs. T. C. Cooke, J. L. Corley and others af your staff at periodic

intervals during the inspection period.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section

2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of

Federal Regulations.

Section 2.201 requires you to submit to this

office within thirty days of your receipt of this notice a written

statement or explanation in reply, including for each item of non-

compliance: (1) corrective action taken and the results achieved:

(2) corrective action to be taken to avoid further noncompliance;

and (3) the date when full compliance will be achieved.

790815cGP(

usato

.

.

2-

MAY 3 0 B79

Consumers Power

.

-

Company

In accordance with Section 2.790 vf the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federai Regulations, a copy of this

letter, the enclosures, and your response to this letter will be

placed in the NRC's Public Document Room, except as follows.

If the

enclosures contain information that you or your contractors believe

to be propriatary, you must apply in writing to this of fice, within

twenty days of your receipt of this letter, to withhold such information

from public disclosure.

The application must include a full statement

of the reasons for which the information is considered proprietary,

and should be prepared so that proprietary information identified in

the application is contained in an enclosure to the application.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

.hSwE

Gaston Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice of

Violation

2.

IE Inspection Reports

.

No. 50-329/79-13 and

No. 50-330/79-13

cc w/encls:

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Ronald Callen, Michigan Public

Service Commission

Dr. Wayne E. North

Myron M. Cherry, Chicago

dD;:311