ML19246C308

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-327/79-29 & 50-328/79-16 on 790508-11.No Noncompliance Noted.Major Areas Inspected:Areas of Previous noncompliance,10CFR50.55(e) Items,Response to IE Bulletin 79-02 & Containment Penetrations
ML19246C308
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 05/24/1979
From: Herdt A, Mcfarland C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19246C302 List:
References
50-327-79-29, NUDOCS 7907240129
Download: ML19246C308 (2)


See also: IR 05000327/1979029

Text

.

  1. p e nic

o

'o

UNITED STATES

!'

,,,,gg(',g

NUCLEAR REGULATORY COMMISSION

,

c

REGION 11

~A,8

101 MARIETT A sT., N.W., SUITE 3100

o

.

g

ATLANTA, GEORGIA 30303

.....

Report Nos. 50-327/79-29 and 50-328/79-16

Licensee: Tennessee Valley Authority

500A Chestnut Street Tower II

Chattanooga, Tennessee 37401

Facilty Name:

Sequoyah Nuclear Plant, Units 1 and 2

Eocket Nos. 50-327 and 50-328

License Nos.

CPPR-72 and CPPR-73

Inspection at S

oa Site near Daisy, Tennessee

Inspecto .

kt.

Io V 7/

'C.

R.

gFarl ud

Date Signed

Approved by:

[/

J )V[7f

'

A. R. Herdt, Section Chief, RCES Branch

Dat'e Signed

.

SUMMARY

Inspection on May 8-11, 1979

Areas Inspected

This routine unannounced inspection involved 26 inspector hours on site in the

areas of noncompliance, 10CFR 50.55(e) items, inspector follow-up items, IEB 79-02, and containment penetrations.

Results

Of the five ercas inspected, no apparent items of noncomplianc3 or deviations

were identified.

_b

,

00?2 40\\p

.

.

DETAILS

1.

Persons Contacted

Licensee Employees

  • G. G. Stack, Project Manager, Sequoyah Nuclear Porject (SNP)
  • J. E. Wilkins, Construction Engineer
  • D. W. Mack, Assistant Construction Engineer
  • R. W. Farrell, Supervisor, Quality Engineering Records Unit
  • R. W. Olson, Assistant Construction Engineer
  • E. C. Pendergrass, Engineer, QC Records Unit (QCRU)
  • J. M. Munns, Supervisor, Construction QA Unit (CQAU)

R. B. Bruce, QA Engineer, CQAU

L. W. Jones, Supervisor, Mechanical Inspection

J. A. Thompson, Mechanical Engineer

R. M. Callegari, Mechanical Engineer

S. N. Scott, Mechanical Aide

  • M. A. McBurnett, Nuclear Engineer, Regula'mry Staf f

K. G. Gallaway, Welding Inspector

J. M. Boone, Mechanical Inspector

  • W. E. Andrews , Power Production, QA Sta.'

'e rvisor

  • G. W. Killian, Office of Power, QA Coordtaatot

'

Other licensee employees contacted included several construction

craftsmen and engineering office personnel.

  • Attended exit interview

2.

Exit interview

The inspection scope and findings were summarized on May 11,1979 with

those persons indicated in Paragraph I above.

3.

Licensee Action on Previcus Iqspection Findings

(Open) Item of Noncomplaince, Infraction 50-328/79-04-01, Failure to

Follow procedure for Handling and Protection of Stainless Steel Piping.

The inspector reviewed the TVA April 5, 1979 response to Region II and

the corrective action stepc taken by TVA to correct the problem and to

avoid further noncompliance. The inspector reviewed QC inspection

records of the reactor building, but there has been no documented

inspection of the areas of concern as stated in the Notice of Violation.

TVA will conduct two special inspections of the areas of concern in the

Notice of Violation.

Special inspections will be initiated routinely for

future noncompliances.

3bb

-

..

.

-2-

4.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Licensee Identified Items (Units 1 and 2)

TVA has reported a number of items to Region II as reportable items in

complianca with 10CFR 50.55(e) and the inspector revewied the items below

and the supporting documentation, and discussed the items with responsible

staff during the inspection.

6.

(Closed) Item 50-327/79-12-03 Omitted Lateral Restraints on the

Chemical Volume Control System (CVCS) Piping. The inspector

reviewed TVA January 12, 1979 response to Region II NCR CEB78-2, the

engineering change notice (ECN) Number 20.63 and representative

drawings. The inspector observed the completed work in Unit I

related to Chemical Volume Control Hangers (CVCH) 551, 557, 676,

627, 628 and 629 as representative work.

Work related to Unit 2 was

not inspected.

b.

(Closed) Item 50-327/79-12-04, Heating, Ventilation and Air-

Conditioning (HVAC) Penetration in Containment Design. The

inspector reviewed the TVA responses to Region II dated January 12,

1979 and February 23, 1979, NCR CE3 78-03, the documentation

relative to the penetration loads in the design specification, ECN

2196 and representative to relived overstressed condiitions. The

inspector observed the completed work on Unit I related to IIVAC

supports 319, 320, 321, 323, and 324 ( 3 vacuum breakers) as

representative work. Work related to Unit 2 was not inspected.

c.

(Closed) Item 50-327/79-12-08 and 50-328/79-07-08 Piping Embedded in

Structural Concrete.

The inspector reviewed the TVA responses to

Region II dated February 8,1979 and March 21, 1979, NCR CEB 79-01.

The inspector reviewed TVA documentation of the subject and an

analysis of each of the defic .ncies noted in NCR CEB 79-01 and the

results indicate that the integrity of the structures and the piping

systems were not degraded by these violations. Therefore, had the

deficiency gone uncorrected, the safety of operation of the plant

would not have been adversely affected. The inspector also reviewed

documentation of the revision to the general civil design criteria

for the S quoyah Nuclear Plant (SNP), SQN-DC-V-1.1 RG, that requires

"a revir

of the conduits and pipes to be embedded in concrete to

.aat the requirements of section 703 of ACI 318-63 are met

ensure

d.

(0 pen) Items 50-327/79-29-01 and 50-328/79-16-01, Vibration in RHR

Piping.

Region II has received two interim reports in the subject

NCR CEB 79-04, dated March 9, 1979 and May 8, 1979. The next report

is expected to be submitted June 8, 1979.

Pipe vibration problems

f

)bO

1

"%)

~-

.

.

-3-

have been encountered on Unit 1 RHR piping during certain modes of

operation. Supports have been added. Retests have been conducted.

Further corrective action is being investigated.

This item was not

inspected.

(0 pen) Item 50-327/79-29-02 and 50-328/79-16-02, Fire Load not

e.

considered iu the Fire Hazard Analysis.

Region II has received the

TVA final report on the subject, NCR MEB 79-16, dated May 4, 1979.

A vapor barrier mode of Pittcote 300 material is used with a 4 foot,

4 inch high belt of foam glass insulation around the inside of the

steel conta:.nment vessel at elevation 679.

The Pitteote 300 material

is combustitle and constitutes a fire load that has not been consi-

dered in the SNP Fire Hazard Analysis.

Pittcote 300 was reonved

from all specification where required to meet the requirements, but

this particular specification was over looked. This item was not

inspected,

f.

(0 pen) Item 50-327/79-29-03 and 50-328/79-16-03, Installation of

Improper Coils in AFW and EGTS Control Circuits.

Region II has

received the TVA final report on the subject, NCR 7P, dated May 1,

1979. During preoperational testing and routine maintenance, four

instances were found where improper coils ware installed in control

circuits for the Auxiliary Feedwater (AFW) and emergency Gas Treatment

(EGTS) Systems.

In the four instances cited above, direct current

(dc) circuits and ac coils were installed in de circuits. When the

affected circuits with improper coils were energized, the coils

failed and disabled those control circuits a concerted effort is

being made to identify other possible similiar deficiencies as part

of the preoperational program.

This item was not inspected.

g.

(Open) Item 50-327/79-29-04 and 50-328/79-16-04, "- tainment Piping

Support Design Basis. On May 11, 1979 TVA infor

'gion II of a

l ative to the subjt

.LR CEB 79-19.

potentially reportable item re

TVA has found that the design basis accident (DBA) movement of the

steel containment was not properly accounted for in the design of

piping supports inside containment. A written report is to be

submitted to Region II by June 10, 1979.

This item was not

inspected.

h.

(Closed) Item 50-327/79-05-01, Signal Cable Used Without Proper

Environmental Qualification Data.

This item is the same as

50-327/79-12-02 (TVA NCR EEB 78-4) which was closed in report

50-327/79-20. The original cable has been pulled and fully

qualified czble has been installed.

i.

(0 pen) Item 50-328/79-16-05, Error in Design of Small Line Supports.

Region II has received the TVA final repor'. ot. .Ls subject, NCR

SWP-79-S-1, dated March 7, 1979.

Movement of tne steel containment

7Bl

36,a

. . .

O

-4-

vessel (SCV) was not accounted for in the design of supports for

several small lines that penetrate the shield building and the SCV.

This NCR was reported as item 50-327/79-19-01 for Unit 1.

This item

was not inspected for Unit 2.

6.

Inspecter I'ollow-up Items (IFI)

(Closed) IFI 327/79-20-09 and 328/79-11-09, Tracking QA audit Pending

Items. The inspector reviewed the Construcd on QA Units "Pending List QA

Activities". The list has been developed for ou6 standing items that are

of concern to the CQAV inspector and require follow-up during subsequent

audits.

The 1 sit is routinely used for audits scheduled each quarter.

7.

Independent Inspection - Containment Penetrations (Units 1 and 2)

The inspector reviewed the following items for a general review of the

subject:

"Containemt Penetration Schedules Unit 1 and 2", TVA drawing

a.

47B333-2G8 lists and locates all penetrations.

b.

" Structural Steel Containment Vessel Pentration Scehdule TVA drawing

48N 406 provides general details of six types of penetrations.

Seventeen spares are listed.

.

" Penetrations" Chicago Bridge & Iron Company drawing numbers 30 and

c.

31.

d.

FSAR Sections 6.2 " Con

inment Systems", and 3.8 " Penetration

Analysis".

6.2.1.1. Erimary Containment System Design and 6.2.1.2

" Secondary Containment System Design".

" Nondestructive Examination NDE) Requirements" by the Division of

e.

Engineerine Design (ENDES) Lists by ce;mponent and penetration number

information relative to weld location, applicable, code, material,

joint type, preheat, applicable NDE procedure numbers (specifications

and acceptance standards), weld procedure numbers, remarks relative

to alternate weld procedures and bracket information.

f.

" General Construction Specification" numbered G-19M, contains process

specifications for welding, heat treatment, NDE, and allied field

fabrication operations related to welding (such as pending, brazing,

stud welding, fit up and visual and dimensional examination of weld

joints). A series of Construction Procedures, W-1 through W-7,

written to further define the work required by the process specifi-

cations W-3 " Weld Procedure Assignment and Welding Surveillance"

further defines weld processes 4: used for penetrations.

g.

Construction QA procedure (QAP) written relative to all plant proce-

dures.

Inspection Instructions (II) provide the details of inspecting

for each of the QAP's, the NDE processes, and the unusual requirements

- .;

.

.

W,

z

-5-

.

of the various components and the craft procedures.

The structural

inspection of containment penetrations are related to the fit-up of

the welds and the welding process.

h.

The following Construction QA Audits related to containment penetra-

tions were reviewed as typical of the audits to date:

SN-76-02 Welding Ac'.ivities Class ABC & D Piping

SN-M-76-10 Installation of Mechanical Containment Penetrations

SN-E-76-05 Installation of Electrical Penetrations

SN-M-77-09 Mechanical Penetrations

SN-78-01 Electrical Penetrations, Storage, and Insta11atien

SN-79-02 Electrical Penetrations Unit 2

No items of noncompliance were identified.

ennrreta

8.

IE Bulletin 79-02 Pipe Support Base Plate Desioner Usino

Expansion Anchor Bolts (Units 1 and 2)

~

,

The inspector reviewed the following Inspection Instructions that are

related to IE Bulletin 79-02:

II 66 Inspection of Supports

II 93 Testing of Expansion Anchors Set In Hardened Concrete

II 66 Incorprates the Inspection Instruction previuosly contained in II 1

Inspection of Bolted Connections, II 36 Orientation and Alignment, and II

38 Inspection of Site Fabricated Assemblies.

NCR CEB 79-5 " Tensile '<2chor Capacities Lower than assumed in design

allowables also related to IEB 79-02.

The final interim report, dated

March 14, 1979, on NCR CEB 79-5 has been received by Region II.

No items of noncompliance were identified.

') )

-

-c3

-

3"