Discusses Plans to Install Communication Links Between NRC & Nuclear Facilities for Emergency Use.Direct Lines from Each Facility to NRC Headquarters & Regional Ofc Will Communicate Operational & Environ Info
ML19241B997
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/22/1979
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
References
NUDOCS 7907260110
Download: ML19241B997 (2)


Text

'

ha em 8Ecv UNITED STATES

'O, NUC LE A R REGULATORY COMMISSION f),t (

k REGION lil 5

E 799 ROOSEVELT RO AD 0,s, p

GLE N E LLYN, ILLINOIS 60137 MAY 2 21979 Docket No. 50-266 Docket No. 50-301 Wisconsin Electric Power Company ATTN:

"r-Sol Burstein Lxecutive Vice President Power Plants 231 West Michigan Milwaukee, WI 53201 Gentlemen:

As a result of the recent accident at the Three Mile Island Nuclear Station (TMI), the NRC has been reviewing the arrangements for imme-diate notifications for licensees and communications available during emergencies.

The initial notification from TM1 was delayed due to several difficulties.

When concern was raised about evacuation, the telephone lines into the area around TMI became saturated and alternate telephone arrangements had to be found.

American Telephone and Telegraph Company, the local telephone com-panies and the White House were extremely helpful in reestablishing and expanding the telephone communications system between the site, NRC Headquarters and the Regional Office in King of Prussia, Pennsylvania during the acute phase of incident recovery. However, communications were limited while these lines were being worked on.

This experience clearly demonstrates the need to preestablish a limited number of direct and dedicated telephone lines at all sites where there is the possibility of a nuclear incident to facilitate the initial notification and to assure continuing communication.

In that regard, the NRC has already taken steps to assure that there will be an individual available at any time to receive a call from any nuclear facility.

As a further step to facilitate an immediate notification and to assure continued and uninterrupted communications with the licensees, the NRC is arranging to install special telephones at all operating nuclear power plants and selected fuel facilities.

There will be two direct and dedicated lines to each site.

One line will be for operations and will be configured in such a manner that when the telephone is lifted from the cradle it will automatically ring in the NRC Operations Center, Bethesda, Maryland and the appro-priate Regional Office.

For nuclear power plant sites, there will be extension in, at least, each unit's control room, the shift supervisor's office and any alte nate emergency operations center.

Fuel facility locations would se at the Plant Manager's Office, primary alarm station, and the designated relocation station.

q quJ

,en

- sui 79072601\\O

MAY 2 21979 Wisconsin Electric Power Coupany The second direct and dedicated line would be for health physics needs during an emergency. This would be a dial-up line, not auto-matic ringing, which would also tie together the site, NRC Head-quarters and the Regional Office.

For most facilities, extensions would be needed in the main health physics office, emergency operations center and any alternate emergency operations centers.

We are now preparing a proposed amendment to NRC regulations which would cover this request.

Besides any discussion on the need for and placement of these telephone lines, it is anticipated that the Statement of Consideration would touch on the question of who will pay the continuing charges for these telephone lines. The NRC be-lieves, however, that in the best interest of the public, installation should not be delayed pending settlement of the question of financial responsibility. Therefore, NRC will pay for the installation and service ch,rges at least until a final rule can be promulgated.

In the meantime, we anticipate that each licensee will cooperate with the NRC a.d the local telephone companies in allowirg these lines to be installed, as soon as feasible.

If you have any questions concerning these telephcee lines, please call Mr. A. B. Davis of this office ((312)858-2660).

Sincerely, f/$, a b? '/'

James G. Keppler /

Director cc:

Mr. G. A. Reed, Manager Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TIC Sandra A. Bast, Lak_ shore Citizens for Safe Energy yrn o n

(