Motion for Addl Hearing Dates & for 790629 Deadline to File Testimony Re Need for Power Issue.Financial Qualificaions, Alternate Site Issues & Other Matters Wil Be Discussed During Hearing.W/Certificate of Svc
ML19241A856
Person / Time
Site: 05000471
Issue date: 05/17/1979
From: Matthew Meyer
MASSACHUSETTS, COMMONWEALTH OF
To:
References
NUDOCS 7907090467
Download: ML19241A856 (4)


Text

- .

LOCAL PD2 UNITED STATES OF AMERICA NUCLEAR PIGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD e

4x 9 o$ 4

)

19'7

/

HD r_

Boston Edison Company, et al., 9 Re: )

Ygjb v

[g,[#p

( 2, /k Pilgrim Nuclear Generating )

Station, Unit No. 2, Docket No. ) #s @

g /

50-471 ) '

) 110 MOTION OF THE COMMONWEALTH OF MASSACHUSETTS FOR ADDITIONAL HEARING DATES AND FOR A JUNE 29, 1979 DEADLINE FOR FILING TESTIMONY ON THE "NEED FOR POWER" ISSUE The Commonwealth of Massachusetts hereby moves that the ,

Atomic Safety and Licensing Board (the Board) grant additional hearing dates and set a June 29, 1979 deadline for filing of testimony by all parties on the "need for power" issue. The Commonwealth of Massachusetts states as its reasons therefore as follows:

1. The Board ordered on May 9, 1979 that the "need for power" issue would be reopened at the hearing scheduled to ccmmence on May 24, 1979.
2. As of today, the Board aas only scheduled ,

a total of 5 1/2 hearing days between May 24, 1979 and June 1, 1979, to hear all remaining issues in this matter.

3. Besides the "need for power" issue, sub-stantial additional matters will have to be heard during the May 24, 1979 to June 1, 1979 hearings. Principal among these other 311 175 V67 -

7907090 ' "O

issues are the " financial qualifications" issue and the " alternate sites" issue; several additional matters may also be heard during these hearings.

4. The Commonwealth of Massachusetts has been informed that the Nuclear Regulatory Commission Staff will not be able to file its written testimony on the "need for power" issue by May 18, 1979, the last day which is at least 15 days before June 1, 1979.
5. The Commonwealth of Massachusetts will not be able to submit written testimony on the "need for power" issue by May 18, 1979, but rather would have to offer oral testimony at the May 24, 1979 to June 1, 1979 hearings if the "need for power" issue is to be heard at that time.
6. It is unlikely that there will be adequate time during the May 24, 1979 to June 1, 1979 hearings to resolve all outstanding issues.

WHE REFORE , the Commonwealth of Massachusetts moves that the Board schedule additional hearing days and set a deadline of June 29, 1979 for all parties to file testimony on the "need for power" issue.

COMMONWEALTH OF MASSACHUSETTS BY: FRANCIS X. BELLOTTI ATTORNEY GENERAL h Wqk Mjuk Mi 9ael B. Meyer

  • Assistant Attorney General Utilities Division Public Protection Bureau One Ashburton Place, 19th Floor Boston, Massachusetts 02103 (617) 727-9714 May 17, 1979 CERTIFICATE OF SERVTCE I, Michael B. Meyer, hereby certify that the attached Motion of the . Commonwealth of Massachusetts for Additional Hearing Dates and for a June 29, 1979 Deadline for Filing Testimony on the "Need for Power" Issue has been served on the following list by hand delivering or by mailing poctage prepaid, first class copies to the below parties at their usual business addresses:

Edward Luton, Esq.

Chairman Atomic Safety and Licensing Board U.S. :!uclear Regulatory Commission Washington, DC 20555 Dr. A. Dixon Callihan Union Carbid Corporation P.O. Box Y Oak Ridge, Tennessee 37830 Dr. Richard F. Cole Atomic Safety and Licensing Board U.S. Nn. lear Regulatory Commission Washin: con, DC 205555 Atomic Safety and Licensing Appeal Board U.S. Nuclear Regulatory Commission Washington, DC 20555 Office of the Secretary d)

Docketing and Service Section 4 \\

U.S. Nuclear Regulatory Commission g Washington, DC 20555 _

" +

.g N _ '

George H. Lewald, Esq. 9 O' d'# '

Ropes and Gray d /

225 Franklin Street Q Boston, Massachusetts 02110 @

^ w Dale G. Stoodley, Esq.

Ecston Edison Company 800 Boylston Street Boston, Massachusetts 02199 31i i76

Barry H. Smith, Esq. ~

Marcia E. Mulkey, Esq.

Office of the Executive Legal Director U.S. Nuclear Regulatory Commission Washington, DC 20555 Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, DC 20555 William S. Abbott, Esq.

50 Congress Street, Suite 925 Boston, Massachusetts 02109 Mr. Daniel F. Ford 1208 Massachusetts Avenue Cambridge, Massachusetts 02138 Henry Hermann, Esq.

151 Tremont Street Boston, Massachusetts 02111 Chief Librarian Plymouth Public Library North Street Plymouth, Massachusetts 02360 Mr. and Mrs. Alan R. Cleeton 22 Mackintosh Street Franklin, Massachusetts 02039 i

t. Act: 0 t. , . _

Michael B. Meyerl Assistant Attorney General May 17, 1979