Text
-
9 I
d pa arco UNITED ST ATES
/
'o NUCLEAR REGULATORY COMMISSION I'
. f' %
REGION 11
$.g 'h/ [$
101 M ARIE T T A si N v. suf TE 3100 o,.g AT L ANT A. GE ORGI A 30303
'N,
[
M6 l979 In Reply Refer To:
RII:JPO 50-348 Alabama Power Company Attn:
F.
L.
Clayton Senior Vice President Post Office Box 2641 Birmingham, Alabama Gentlemen:
This Information Notice is provided as an early notification of a possibly significant matter.
It is expected that recipients will review the infor-mation for possible applicability to their facilities.
No specific action this time.
If you have questions regarding or r sponse is requested at this matter, please contact the Director of the appropriate h7C Regional Office.
t
- 4\\ n y-
__3 s
James P. O'Reilly A
Director
Enclosure:
IE Information Notice No. 79-18 d4[
}b9
)
i 7 908010 C'2 4
JUL 6 1979 Alabama Power Company,
cc w/e.cl:
A. R. Barton Exec 4tive Vice President Pi Office Box 2641 E ':ingham, Alabama 35291 J. T. Youn g Vice President-Production Post Office Box 2641 Birmingham, Alabama 35291 C. Biddinger, Jr.
Manager-Corporate Quality Assurance Post Office Box 2641 Birmingham, Alabama 35291 H. O. Thrash Manager-Nuclear Generation Post Office Box 2641 Bi rmingham, Alabama 35291 H. G. Hairston, III Plant Manager Drawer 470 Ashford, Alabama 36312 R. E. Hollands, Jr.
QA Supervisor Post Office Box U Ashford, Alabama 36312 447 170
r s
UNITED STATES NUCLEAR PEGULATCRY COMMISSICN OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.
20555 July 6, 1979 IE Information Notice No. 79-18 SKYLAB REENTRY Description of Circumstances:
The most recent dates for reentry of Skylab are July 10 to 14, 1979, with July 12, as the most probable date.
Recognizing that a hit on a nuclear power plant would be highly unlikely by Skylab debris, the NRC believes it would be prudent for licensees to review their contingency plans in case such an event should actually occur.
The NRC is in communication with the Department of Energy (DOE), and will receive notification from them as soon as the reentry corridor can be established. This notification may occur within 1 to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> before reentry actually occurs.
If it is determined that there are any licensed nuclear power plants in the reentry corridor, the plants will receive notification from their respective Regional Office via the dedicated phone line.
This Information Notice is provided as an early notification of a possibly significant matter.
It is expected that recipients will review the in f o rma-tion for possible applicability to their facilities. No specific action or response is requested at this t ime.
If further NRC evaluations so indicate, an IE Circular or Bulletin will be issued to recommend or request specific licnesee actions.
If you have questions regarding the matter, please the Director of the appropriate NRC Regional Office.
contact No written response to this information notice is required.
7 7907)20387
IE Inf o rmat ion Not ice No. 79-18 Enclosure July 6, 1979 Page 1 of 2 LISTING OF IE INFORMATION NOTICES ISSUED IN 1979 Information Subj ec t Date Issued To Notice No.
Issued 79-01 Bergen-Paterson Hydraulic 2/2/79 All power reactor Shock and Sway Arrestor facilities with an OL or a CP 79-02 At t empted Extortion -
2/2/79 All Fuel Facilities Low Enriched Uranium 79-03 Limitorque Valve Geared 2/9/79 All power reactor Limit Switch Lubricant facilities with an OL or a CP 79-04 Degradation of 2/16/79 All power reactor Engineered facilities with an Safety Features OL or a CP 79-05 Use of Improper Materials 3/21/79 All power reactor in Safety-Related Companents facilities with an OL or CP 79-06 Stress Analysis of 3/23/79 All Holders of Safety-Related Piping Reactor OL or CP 79-07 Rupture of Radwaste Tanks 3/26/79 All power reactor facilities with an OL or CP 79-08 Interconnection of 3/28/79 All power reactor Contaminated Systems with facilities with an Service Air Systems Used OL and Pu Processing As the Source of Breathing fuel facilities Air 79-09 Spill of Radioactively 3/30/79 All power reactor Contaminated Resin facilities with an OL 79-10 Nonconforming Pipe 4/16/79 All power reactor Support Struts facilities with a CP 79-11 Lower Reactor Veseel Head 5/7/79 All holders of Reactor Insulation Support Problem OLs and cps
)[2
IE Inf ormation Notice No. 79-18 Enclosure July 6, 1979 Page 2 of 2 LISTING OF IE INFORMATION NOTICES ISSUED IN 1979 Information Subject Date Issued To Notice No.
Issued 79-12 Attempted Damage to New 5/11/79 All Fuel Facilities Fuel Assemblies Research Reactors, and Power Reactors with an OL er CP 79-13 Indication of Low Water 5/29/79 All Holders of Reactor Level in the Oyster Creek OLs and cps Reactor 79-14 NRC Position of Electrical 6/11/79 All Power Reactor Cable Support Systems Facilities with a CP 79-15 Deficient Procedures 6/7/79 All Holders of Reactor OLs and cps 79-16 Nuclear Incident at Three 6/22/79 All Research Reactors Mile Island and Test Reactors with OLs 79-17 Source Holder Assembly Damage 6/20/79 All Holders of Reac*.or Damage From Misfit Between OLs and cps Assecbly and Reactor Upper Grid Plate 44/
3i/3
-