Forwards IE Info Notice 79-18, Skylab Reentry. No Action Required
ML19225B564
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 07/06/1979
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Daltroff S
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
References
NUDOCS 7907250521
Download: ML19225B564 (1)


Text

-T k pn neauq y

k UNITED STATES y 7, f. <

g NUCLEAR REGULATORY COMMISSION 3.e ?

'. E REGION I 0, A#

8 631 PARK AVENUE

%

  • NI# [

KING OF PRUSSIA. PEP.NSYLVANIA 19406 a

Docket Nos. 50-277 J1!1 e 73 50-278 Philadelphia Electric Company ATTN:

Mr. S. L. Daltroff Vice President Electric Production 2301 Market Street Philadelphia, Pennsylvania 19101 Gentlemen:

This Information Notice is provided as an early notification of a possibly significant matter.

It is expected that recipients will review the information for possible applicability to their facilities.

No specific action or response is requested at this time.

If you have questions regarding this matter, please contact the Director of the appropriate NRC Regional Office.

Sincerely,

/

ff-

~

Boyce

. Grier

~

Director

Enclosures:

1 IE Information Notice No. 79-18 2.

List of IE Information Notices Issued in 1979 cc w/encls:

W. T. Ullrich, Station Superintendent Troy B. Conner, Jr., Esquire Eugene J. Bradley, Esquire Raymond L. Hovis, Esquire Warren Rich, Esquire

- k h.

79072 5DSP/

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 IE Information Notice No. 79-18 Date:

July 6, 1979 Page 1 of 1 SKYLAB REENTRY Description of Circumstances,:

The most recent dates for reentry of Skylab are July 10 to la, 1979, with July 12, as the most probable date.

Recognizing that a hit on a nuclear power plant would be highly unlikely by Skylab debris, the NRC believes it would be prudent for licensees to review their contingency plans in case such an event should actually Ncur.

The NRC is in communication with the Department of Energy (DOE), and will receive notification from them as soon as the reentry corridor can be established.

This notification may occur within 1 to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> before reentry actually occurs.

If it is determined that there are any licensed nuclear power plants in the reentry corridor, the plants will receive notification from their respective Regional Office via the dedicated phone line.

This Information Notice is provided as an early notification of a possibly significant matter.

It is expected that recipients will review the informa-tion for possible applicability to their facilities.

No specific action or response is requested at this time.

If further NRC evaluations so indicate, an IE Circular or Bulletin will be issued to recommend or request specific licnesee actions.

If you have questions regarding the matter, please contact the Director of the appropriate NRC Regional Office.

No written response to this information notice is required.

7 907120397 sco

@ 20D

ENCLOSURE 2 IE Information Notice No. 79-18 Date:

July 6, 1979 Page 1 of 2 LISTING OF IE INFORMATION NOTICES ISSUED IN 1979 Information Subject Date Issued to Notice No.

Issued 79-01 Bergen-Paterson Hydraulic 2/2/79 All power reactor Shock and Sway Arrestor facilities with an Operating License (01.) or Construction Permit (CP) 79-02 Attempt'. Extortion -

2/2/79 All Fuel Facilities Low Enricted Uranium 79-03 Limitorque Valve Geared 2/9/79 All power reactor Limit Switch Lebricant facilities with an OL or CP 79-04 Degradation of 2/16/79 All power reactor Engineered facilities with an Safety Features OL or CP 79-05 Use of Improper Materials 3/21/79 All power reactor in Safety-Related Components facilities with an OL or CP 79-06 Stress Analysis of 3/23/79 All power reactor Safety-Related Piping facilities with an OL or CP 79-07 Rupture of Radwaste Tanks 3/26/79 All power reactor facilities with an OL or CP 79-08 Interconnection of 3/28/79 All power reactor Contaminated Systems with facilities with an Service Air Systems Used OL and Pu Processing As the Source of Breathing fuel facilities Air 79-09 Spill of Radioactivity 3/30/79 All power reactor Contaminated Resin facilities with an OL 79-10 Nonconforming Pipe 4/16/79 All power reactor Support Struts facilities with a CP 452 3 Of

IE ?nformation Notice No. 79-18 Date.

July t, 1979 Page 2 of 2 LISTING 0F IE INFO.' GTION NOTICES ISSUED IN 1979 Information Subject Date Issued to Notice No.

Issued 79-11 Lower Reactor Vessel Head 5/7/79 All power reactor Insulation Eupport Problem facilities with an OL or CP 79-12 Attempted Damage to New 5/11/79 All Fuel Facilities, Fuel Assemblies Research Reactors, and Power Reactors with an OL or CP 79-13 Indication of Low Water 5/29/79 All power reactor Level in the Oyster facilities with an Creek Reactor OL or CP 79-14 Safety Classification of 6/11/79 All applicants for, Electrical Cable Support and holders of a Systems power reactor CP 79-15 Deficient Procedures 6/7/79 All power reactor facilities with an OL or CP 79-16 Nuclear Incider.t at 6/22/79 All research and Three Mile Island test reactors with an OL 79-17 Source Holder Assembly 6/20/79 All power reactor Damage from Misfit Between facilities with an Assembly and Reactor Upper OL or CP Grid Plate 452 3esk