Forwards IE Insp Rept 50-483/79-04 on 790424-26 & Notice of Violation
ML19225B466
Person / Time
Site: Callaway Ameren icon.png
Issue date: 05/30/1979
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Bryan J
UNION ELECTRIC CO.
Shared Package
ML19225B467 List:
References
NUDOCS 7907250212
Download: ML19225B466 (2)


See also: IR 05000483/1979004

Text

.

YIC

UNITED STATES

p* Mco

,

f

[g

NUCLE AR R E GU L ATOH Y COMMISSION

,

'{(

$

REGION 111

[

g

-

l ' y

f

799 ROOSE VELT RO AD

5

0,

N

d

GLE N E LLY N. BLLINOIS 60t37

gv j>

.....

IAAY 3 01979

Docket 50-483

Union Electric Company

ATTN:

Mr. John K. Bryan

Vice President - Nuclear

Post Office Box 149

St. Louis, Missouri 63166

Gentlemen:

This refers to the inspection conducted by Messrs. E. R. Schweibinz

and W. A. Hansen of this office on April 24-26, 19i9, of activities

at the Callaway Unit 1 construction site authorized by NRC Construction

permit No. CPPR-139 and to the discussion of our firdings with

Mr. Weber and others of the Callaway staff at the conclusion of the

inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representctive records,

observations, and interviews with personnel.

Certain other activities, set forth in the enclosed Appendix A to

this letter, appear to be a deviation from commitments which you

have made in previous correspondence with the Commission.

Please

advise us in writing within thirty days of the corrective action you

have taken or plan to take, showing the estimated date of completion

with regard to this deviation.

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter,

the euclosures, and your respcase to this letter will be placed in

the NRC's Public Document Room, except as follows.

If the enclosures

contain information that you or your contractors believe to be

proprietary, you must apply in writing to this office, within twenty

790725os/A

3@J

ysz

a4

n-

~m=1

.

.

MAY 3 01979

Union Electric Company.

-2-

days of your receipt of this

tter, to withhold such information

from public discl sur2.

The application must include a full state-

ment of the reasons for which the information is considered Iroprie-

tary, and should be prepared so that proprietary information

identified in tue spplication is contained in an enclosure to the

application.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

N

G. Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Ecclosures:

1.

Appendix A, Notice of

Deviation

2.

IE Inspection Report

No. 50-483/79-04

cc w/ enc 1:

W. H. Weber, Manager

Nuclear Construction

Central Filec

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Regions I & IV

Ms. K. Drey

Hon. C. J. Frasc , Chairman

343

l(57_

m-e