Notice of Violation from Insp on 790402-30
ML19225A525
Person / Time
Site: Dresden  
Issue date: 05/10/1979
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19225A522 List:
References
50-010-79-08, 50-10-79-8, 50-237-79-12, 50-249-79-10, NUDOCS 7907190497
Download: ML19225A525 (1)


Text

.

Appendix A NOTICE OF VIOLATION Commonwealth Edison Docket No. 50-237 Company Based on the inspection conducted on April 2-30, 1979, it appears that certain of your activities were in noncompliance with NRC requirements, as noted below.

This item is an infraction.

Unit 2 Technical Specifications, Section 3.7.A.1 requires the maximum volume in the torus to be 115,655 cubic feet.

Contrary to the above, during a quarterly flow test and sub-sequent troubleshooting of the HPCI System on January 3, 1979, the technical specification required maximum volume in the torus was exceeded.