Forwards IE Insp Repts 50-295/79-04 & 50-304/79-05 on 790321-23 & 26-30.No Noncompliance Noted
ML19225A154
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 05/15/1979
From: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
Shared Package
ML19225A155 List:
References
NUDOCS 7907180492
Download: ML19225A154 (2)


See also: IR 05000295/1979004

Text

7

s

TICl -

-

.

d

UNITED ST AT ES

j

4,

O

.t

NUCLE AR REGULATORY COMMISSION

-

f

,$

h

REGloN 11!

.

799 RoOSEVE LT ROAD

- [T], y[J

  • 'w

.

4

G LE N E LL YN, ILLINols 60137

  • ...*

MAY I 51979

Docket No. 50-295

Docket No. 50-304

Commonwealth Edison Company

ATIN:

Mr. Byron Lee, Jr.,

Vice President

P. O. Box 767

Chicago, IL

60690

Centlenen:

This refers to the inspection conducted by Messrs. M. C. Schumacher

and N. E. DuBry of this office on March 21-23 and 26-30, 1979, of

activities at Zion Nuclear Power Station, authorized by NRC Operating

Licenses No. DPR-39 and No. DPR-48, and to the discussion of our

findings with Mr. Wandke and others of your staff at the conclusion

of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

No items of noncompliance with NRC requirements were identified

during the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Fegulations, a copy of this letter

and the enclosed inspection report will be placed in the NRC's

Public Document Room, except as follows.

If this report contains

information that you or your contractors believe to be proprietary,

you must apply in writing to this office, within twenty days of your

receipt of this letter, to w thhold such information from public

i

disclosure.

The application must include a full statement of the

reasons for which the infomation is considered proprietary, and

-

should be prepared so that proprietary information identified in the

application is contained in an enclosure to the application.

!\\b

347

178

2007180 M R 9

.

,

.

.

Commonwealth Edison

-2-

MAY

5 1979

,

Company

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

I

%

A. B. Davis, Chief

Fuel Facility and

tbterials Safety Branch

Enclosure:

IE Inspection

Rpts No. 50-295/79-04 and

No. 50-304/79-05

cc w/ encl:

N. Wandke, Plant

Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Mr. Dean Hansell, Office

of Assistant Attorney

General

,

-,

_