APPENDIX A NOTICE OF VIOLATION Metropolitan Edison Company Docket No. 50-320 Based on the results of an NRC inspection conducted on December 4-8 and 12-14, 1978, it apoears that one of your activities was not conducted in full compliance with conditions of your NRC Facility License No. DPR-73 as indicated below.
This item is a Deficiency.
Technical Specification 4.6.1.1 states, in part:
" Primary CONTAIN-MENT INTEGRITY shall be demonstrated:
a.
At least once per 31 days by verifying that:
1.
All penetrations *... are closed by valves...".
- Except valves... which are located inside containment and are locked, sealed or otherwise secured in the closed position.
These penetrations shall be serified closed during eacn COLD SHUTDOWN except that verification of ths:e per.etrations being closed need not be performed more often than once per 92 days.
Contrary to the above, containment penetration isolation valves inside containment were not verified closed during two COLD SHUT-DOWN periods on November 10-20 and 23-30,1978.
These valves had not been verified closed since August 26, 1978, during a previous COLD SHUTDOWN period.
. -p
-r m