Forwards IE Insp Repts 50-461/79-11 & 50-462/79-01 on 791030-1102 & Notice of Violation
ML19211D290
Person / Time
Site: Clinton  Constellation icon.png
Issue date: 11/27/1979
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Gerstner W
ILLINOIS POWER CO.
Shared Package
ML19211D291 List:
References
NUDOCS 8001170445
Download: ML19211D290 (2)


See also: IR 05000461/1979011

Text

b

e

y[ga arag

.

o

UNITED STATES

'g

NUCLEAR REGULATORY COMMISSION

y

3,

g

e

REGION 111

'

.. [

799 ROOSEVELT ROAD

,

o,,

% .'.N .J[

GLEN ELLYN,ILLINols 60137

...

NOV 2 71979

Docket No. 50-461

Docket No. 50-462

Illinois Power Company

ATTN:

Mr. W. C. Gerstner

Executive Vice President

500 South 27th Street

Decatur, IL 62525

Gentlemen:

This refers to the inspection conducted by Messrs. J. F. Suermann and

G. F. Maxwell of this office on October 30-November 2, 1979, of activities

at the Clinton Power Station, Units 1 and 2, authorized by NRC Construction

Permits No. CPPR-137 and No. CPPR-138 and to the discussion of our findings

with Messrs. Mch.,d, Geier, Koch and others of your staff at the conclusion

of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and inter-

views with personnel.

During this inspection, certain of your activities appeared to be in noncom-

pliance with NRC requirements, as described in the enclosed Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201 of the

NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office within thirty days of your

receipt of this notice a written statement or explanation in reply, including

for each item of noncompliance: (1) corrective action taken and the results

achieved; (2) corrective action to be taken to avoid further noncompliance;

and (3) the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter, the enclosures,

and your response to this letter will be placed in the NRC's Public Document

Room, except as follows.

If the enclosures contain information that you or

your contractors believe to be proprietary, you inust apply in writing to this

176'3 045

8001.17o 4 45

.

2

IO79

'

Illinois Power Company

2-

office, within twenty days of your receipt of this letter, to withhold such

information from public disclosure. The application must include a full state-

ment of the reasons for which the information is considered proprietary, and

should be prepared so that proprietary information identified in the application

is contained in an enclosure to the app h cation.

We will gladly discuss any questions "ou have concerning this inspection.

Sincerely,

[78dwa

-

Gaston Fiorelli, Chief

,

/

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Reports

No. 50-461/79-11 and

No. 50-462/79-01

cc w/encls:

Central Files

Reproduction Unit NRC 20b

PDR