ML19211D235

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-440/79-10 & 50-441/79-10 on 791016-18. Noncompliance Noted:Inadequate Procedures & Failure to Follow Procedures for Qualification of Insp & Testing Personnel
ML19211D235
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 11/19/1979
From: Maxwell G, Suermann J, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19211D227 List:
References
50-440-79-10, 50-441-79-01, 50-441-79-1, NUDOCS 8001170140
Download: ML19211D235 (19)


See also: IR 05000440/1979010

Text

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report Nos. 50-440/79-10; 50-441/79-10

Docket Nos. 50-440; 50-41

License Nos. CPPR-148; CPPR-149

Licensee: The Cleveland Electric Illuminating

Company

P. O. Box 5000

Cleveland, OH 44101

Facility Name: Perry Nuclear Power Plant, Units 1 and 2

Inspection At:

Perry Site, Perry, OH

Inspection Conducted: October 16-18, 1979

[r[" A ->c W. 4 L

Inspectors: J.E]Konklin

//-/ f-- 7 f

M

NOV$/9ISlf

1

%L

K. R. Naidu

4 V ??, /1 ?7

l-

s'k

J. F. Suermann

M.# /9,/ 7/

Accompanying Personnel: C. C. Williams (October 17-18, 1979)

.

C. E. Jones (October 17-18, 1979)

C' <L . _,len cu/cv

Approved By: C. C.c Williams , / Chief

//-/ 9- 7f

Projects Section No. 2

Inspection Summary

Inspection on October 16-18, 1979 (Report No. 50-440/79-10 and 50-441/79-10)

Areas Inspected: Licensee actions relative to previously identified items

of noncompliance and unresolved items; licensee's compliance with ASME

1762 049

soo1170 /VO

,

Code certification requirements; licensee's maintenance program for NSSS

equipment;

status of tagging of electrical equipment; procedures, work

activities and quality records related to placement of safety-related

concrete, implementation of the requirement of T/I No.2512/4. This

inspection involved a total of 88 onsite inspector-hours by four NRC

inspectors.

Results: Of the five areas inspected, three items of noncompliance were

identified in three of the areas (infraction - inadequate procedures and

failure to follow procedures for qualification of inspection and testing

personnel, two examples,Section IV; infraction - inadequate identification

of nonconforming equipment,Section II; infraction - lack of prompt correc-

tive action to assure that ASME Code requirements are met,Section I.)

-2-

1762 050

'

DETAILS

Persons Contacted

Principal Licensee Employees

  • M. Edelman, Manager, Nuclear QA Depar'. ment
  • G. Groscup, Manager, Nuclear Engineering Department
  • D. Fitzpatrick, Site Construction Manager
  • W. Kacer, CQS General Supervising Engineer
  • A. Kaplan, General Supervising Engineer, Construction
  • B. Barkley, General Supervising Engineer, Design
  • P . Ma rt it. , General Supervising Engineer, PQS
  • D. Cooper, CQSS Supervisc

Other Personnel

  • P. Gibson, CQS QC Supervisor (KEI)
  • R. Vondrasek, CQS QE Supervisor (GAI)
  • T. Arney, QA Program Manager (GAI)

R. Crofton, CQS Lead Piping Quality Engineer (GAI)

J. Connelly, CQS Lead Civil Quality Engineer (GAI)

J. Mehaffey, CQS Lead Mechanical Quality Engineer (GAI)

W. Wre, CQS Civil Quality Engineer (GAI)

S. Tulk, CQS Electrical Quality Engineer (GAI)

G. Parker, CQS Mechanical Quality Engineer (GAI)

M. Combs, CQS Engineering Aide (GAI)

K. Pech, Assistant Project Manager (GAI)

T. Hesmond, QC Manager (National Engineering)

T. Gage, QC Inspector (National Engineering)

R. Thornton, QC Supervisor (National Mobile)

D. Burnbaum, Project Engineer, Hoboken Office (UST)

P. Wang. Laboratory Chief (UST)

L. Medley, QC Inspector (UST)

The inspectors also contacted and interviewed other licensee and contractor

personnel.

  • Denotes those attending the exit interview on October IS, 1979.

Licensee Action on Previous Inspection Findings

(Closed) Open Item (440/78-12-03; 441/78-11-03): Failure to distribute

procedure on Field Questions. The inspector reviewed CEI Memorandum

dated October 3, 1979 which was transmitted to the site contractors and

which contained twenty-one project procedures (including the procedure on

Field Questions). This item is considered closed.

-3-

1762

051

(Closed) Open Item (440/78-03-07; 441/78-02-07): Possible trend in relax-

ation of civil code requirements. The inspector reviewed the construction

Quality Assurance Nonconformance Trend Analysis transmitted by CEI Memorandum

dated March 22, 1978.

The licensee took corrective action between

March and July 1978 to correct deficiencies noted in the trend analysis.

Corrective action included, but was not limited to: specific evaluation

of the relaxed ceJe requirement; formation of an Ad Hoc Committee to

review the use of Field Variance Authcrizations and Nonconformances;

training classes; and revised policy guidance on the use of FVA's, NR's

and ECN's.

This item is considered closed.

(Closed) Unresolved Item (440/76-06-01; 441/76-06-01) The review of

Gilbert Associates Incorporated (GAI) Specifications SP-17 and SP-96,

Newport News Industrial Corporation (NNIC) Procedures 465-NC-v101, 946-N-W001

and 948-N-W001 and NNIC QA Manual by the NRC inspector was incomplete.

The procedures and specifications were reviewed. The test requirement

was verified for the 5/64" diameter E-70TG type electrode.

This type

electrode was used on the 1-2A/B weld and is identified with a unique

number, 77N1547. Records indicate that Lincoln Electric Company manufac-

tured and supplied this electrode; Certified Material Test Report (SMTR)

dated July 21, 1977 certified that the electrode complies with requirements

of paragraph NB-2400 of the ASME Code Section III (1974) with the summer

and winter addenda.

Charpy V-notch impact test results exceeded the 20

ft.-lbs. at -20 F requirement specified in paragraph 5:09.2.7.a.(3)(b)

of Specification SP-17.

(Closed) Unresolved Item (440/78-09-02; 441/78-08-02) Additional information

was provided on the following items:

1.

The PBI QA Manual was revised and revision 1 dated January 18, 1979

specified the use of a model DA-200 contour probe for MT examination.

The yoke method was not used.

2.

An eye examination was administered to the level III inspector; his

visual acuity was acceptable and is documented in a record dated

August 1978.

3.

A letter from Lincoln Electric Company dated July 3, 1979 to CEI

quotes Table 8 on pages 18-19 of the AWS 5.1-69 as not requiring any

mechanical tests on 3/32" and 1/8" electrode.

(Closed) Noncompliance (440/78-12-04) The internal cleanliness of the

Unit 1 Reactor Pressure Vessel was contrary to the requirements of GE

Procedure 22A2537. NICC generated Nonconformance Report (NCR) 38-6,

collected samples of the foreign material and subjected it to visual

spectrographic analyses. The analyses indicated that the material was

typical manufacturing debris.

CEI QA personnel determined that there

-4-

1762 052

were no documents to indicate that the RPV was cleaned after the feed-

water nozzle modifications were made in the shop. The Unit 1 RPV was

scheduled to be scrubbed utilizing GE Procedure 22A2537, titled " Final

Cleaning Procedure", with approved solvents under GE supervision. However,

due to modifications on the recirculation inlet nozzles this operation

will be done after completion of work. To prevent recuaence, CEI personnel

performed first line inspections on Unit 2 up to its' shipment. The

licensee informed the insp etor that the cleanliness of Unit 2 RPV was

acceptable on arrival at site.

(Closed) Unresolved Item (440/78-12-05) The Unit 1 RPV alignment was

offset an average .048' in the x plane which exceeded the maximum permissible

value .025'.

The offset was attributed to adverse accumulation of tolerances

during machining of the vessel support flange.

GE safety / reliability

review dispositioned the Field Deviation Disposition Request #KL1-0012 to

"use as is".

The alignment on Unit 2 RPV was initially performed on

December 18, 1978 and subsequently verified on April 21, 1979; the check

indicates that the middle target shifted from .023NE in the first quadrant

to .013NW in the fourth quadrant measured at the target at the Shroud

Support Ring. CEI is continuing to follow up on this matter. The inspector

has no further questions at this time.

(Closed) Unresolved Item (440/78-12-05) Inadequate information on GE's

three Product Quality Certificates (PQC) #N975, N993 and HH768 dated

December 16, 1976, April 4, 1977 and June 9, 1978.

CEI QA personnel

determined that the above PQCs were not final records and obtained the

following clarifications:

1.

PQC N975-MPL-B13-D003, P0 #205-H8953.

This PQC is for Unit 2 0-

rings only.

2.

PQC #N993-MPLB13-D003, GEP0 #205-AE208. This PQC is for RPV Unit 1.

3.

PQC #HH768-MPL #B13-D002; GE P0 #205-AH431. This PQC is to cover

the completed RPV Unit I with the intervals installed and its 0-ring

seals.

(Closed) Noncompliance (440/78-12-07) Failure to follow procedures relative

to " Hold Point" sign offs and approve procedures prior to use.

CEI

conducted an independent investigation and confirmed that the contractor

and construction quality control personnel failed to adhere to the program

requirements even though they observed the referenced hold points.

CEI

in a letter dated August 28, 1979 to all CQC and CQE personnel requested

adherence to programmatic requirements relative to " Hold" and " Witness"

points. Relative to approval of procedures, NNIC initiated Engineering

Change Notice (ECN) 1190-38-31 to revise the review and approval require-

ments for Manufacturing Installation Instructions (MII). NN1C requires

MII's to be submitted to the site organization for review, recording and

approval at least four weeks prior to commencement of work unless otherwise

noted. An item of noncompliance (441/79-07-02) was identified related to

the signoffs on MIIs.

1762 053

5-

(Closed) Noncompliance (440/78-12-08) Visual inspection of eight welds

were unacceptable; inspection records documented these welds as acceptable.

NCR 96-191 was generated by NNIC to identify the eight nonconforming

welds. An Action Request (AR) was written by Quality Engineering requesting

NNIC to identify quality program concerns raised in NCR 96-191. A three-fold

corrective action was recommended: (a) evaluate the adequacy of the

visual inspection in NNICO Instruction 948-N-N002, (b) reinspect similar

welds (c) retrain NNICO inspectors in visual inspection and examine their

proficiency by reviewing their inspections.

CEI rejected NNIC's initial

reply on the basis that the reinspection was restricted to the Bioshield

walls and requested NNIC to broaden the range of inspection.

NNIC

Document #701-2708 dated May 1, 1979, indicates that reinspection of

welds in Units 1 and 2 bioshield was performed and several unacceptable

welds were identified and repaired. NNTC conducted a two hour training

session on September 20, 1978 on visual inspection of welds and discussed

NRC findings. Additionally, National Inspection And Consultants (NIC)

conducted a training session for NNIC inspection personnel on visual

inspection requirements and awarded a certificate dated January 19, 1979.

The NNIC statistical interpretation of the unacceptable welds identified

during the reinspection concluded that the visual inspections were acceptable.

The findings are documented in NCRs 17-88, 17-89 and 96-269.

To date NCR

96-269 is c1csed and the repair, reinspection and acceptance of welds

completed are documented in NCR 96-269. CEI QA through their audit and

inspection program subsequently identified several additional problems

related to inadequate inspections which resulted in CEI issuing a Stop

Work Order No. 79-06 dated September 6, 1979.

(Closed) Noncompliance (440/78-15-02; 441/78-14-02) Failure to assure

that ourchased materials (embedments and structural steel) conformed to

the specification requirements.

1.

Nelson Stud attachments to the stainless steel Spent Fuel Liner

Plates were reinspected and the unacceptable welds were repaired

reinspected and accepted. Weld history record for Welds 53-32-1,

-2,

-3, dated April 13, 1979 reflects the work performed.

2.

The stitch welds on Unit 2 wier wall were reinspected. NNIC document

701-2624 dated February 27, 1979 indicates that a sample size of 216

welds were reinspected out of which nine welds did not meet the

requirements; the welds were accepted based on paragraph 8.15.1.6 of

AWS D1.1276 code which permits an underrun of the nominal fillet

size by 1/16" without correction provided that the undersize dces

not exceed 10% of the length of the weld.

(Closed) Noncompliance (440/78-15-03; 441/78-14-03) Inadequate control of

welding process.

1.

Training sessions were conducted on May 1 and 2, 1979 by NNIC to

emphasize the preheat requirements and is so documented; a list of

-6-

1762

054

attendees who were present is attached to the record. Discussions

with the NNIC QA manager indicate that several training sessions

were conducted subsequently.

2.

NNIC developed a procedure, 701-F-W003, which was approved by CEI on

April 20, 1979, titled " Monitoring Welding Parameters other than

NDE".

This procedure adequately addresse.s the parameters to be

monitored during welding to verify that welding procedures are being

followed. The inspector reviewed surveillanca reports and determined

that the welding parameters were being adequately monitored to

determine compliance with the respective welding procedures.

(Closed) Noncompliance (440/78-15-04; 441/78-14-04) Deficiency in pressure

test documentation. NNIC document No. 701-2683 dated April 10, 1979

indicates that all the pressure test records from November 23, 1977

through May 11, M78 were reviewed with the inspectors who performed the

tests.

It was determined that the inspectors were qualified to SNT-TC-1A

Level II and that only the documentation was discrepant in some areas.

The Level II inspectors were given proper instructions. The leak test

procedure, H65-N-T005, was revised on March 14, 1979 and the revised

format of the Leak Test Report appears to eliminate discrepant entries.

(Closed) Unresolved Item (440/79-09-01; 441/79-09-01) - All MCCs which

have been installed for Units 1 and 2 have not been identified as " conditionally

released". This item is closed as an unresolved item and is being upgraded

to an item of noncompliance in this inspection report; details Section

II.

This condition was upgraded to an item of noncompliance, because it

appears to be a condition requiring more attention than has been paid to

it by CEI since June 27, 1979.

-7-

1762

055

.

Section 1

Prepared by:

J. E. Konklin

Reviewed by: C. C. Williams, Chief

Projects Section No. 2

1.

Review of Licensee Actions on Previous Inspection findings

The RIII inspectors reviewed *.he licensee's actions relative to the

resolution of specific inspection findings which were identified in

previras RIII inspection reports and which were still in an open

tratus prior to this inspection.

The items reviewed, and the licensee

actions relative to the resolution of the items are discussed in the

foregoing section of this report.

2.

Review of Licensee's Compliance with ASMI Code Requirements

The RIII inspector reviewed the licensee's implementation of the

ASME Code certification system requirements on the Perry Project.

The review indicated that safety-related components and systems at

Perry are being designed, fabricated and installed under various

editions and addenda of the ASME Code and that specific questions

exist as to whether appropriate and timely actions have been taken

by the licensee to assure full compliance with all ASME Code require-

ments.

Work on safety-related components er systems which require ASME Code

certification has been performed by three major Perry site contractors,

Newport News Industrial Corporation (NNIC), Pullman Power Products

(Pullman) and Johnson Controls, although the licensee has recently

removed the work oa the NSSS systems from NNIC and has contracted

with General Electric for this work.

Five basic contract specifications, SP-38, SP-39, SP-44, SP-47 and

SP-90, are involved in the ASME Code work at Perry.

The applicable

installation code for the work which has been done by NNIC under

Specifications SP-38 and SP-39, and which has recently been awarded

to General Electric, is the 1977 Edition, Winter 1977 Addenda. For

the work being done by Pullman under Specifications SP-44 and SP-47,

the applicable installation code is the 1974 Edition, Winter 1975

Addenda and for the work being done by Johnson Controls under Specifi-

cation SP-90, the applicable installation code is the 1977 Edition,

Winter 1977 Addenda.

With regard to certification of the site contractors, the inspector

verified that NNIC, Pullman and Johnson Controls possess current

"NA" and "NPT" authcrizations and that the General Electric I & SE

Group, which will assume the work under Specifications SP-38 and

SP-39, will be required to have the appropriate code authorizations

prior to start of work.

1762

056

-8-

.

The rules of the Summer 1976 and earlier editions and addenda require

that installations shall be affixed with an "NA" Code stamp, but do

not require the affixing of an "N" stamp. The rules of the Winter

1976 and later editions and addenda require that an "N"

Certificate

holder having overall responsibility for the system shall affix an

"N" Code stamp to the completed system.

"Overall responsibility"

includes materials, design, fabrication, examination, testing,

inspection and certification for manufacture and installation of the

entire system.

During discussions with the licensee and review of licensee documents

relating to code certification, the inspector determined that the

licensee has been aware of the need for further actions with regard

to the code certification requirements and has taken the initial

steps to obtain an Owner's Certificate of Authorization for the

Perry Project. However, the inspector also noted that Code interpre-

tation III-1-78-186, issued on June 1, 1978, states that the Owner's

Certificate of Authorization does not authorize the owner to act as

the "N" Certificate holder. The document reviewed by the inspector

included the following:

a.

The Inspection Service Contract, dated September 19, 1977,

between CEI and Hartford Insurance Company, for inspection

services (as the Authorized Inspection Agency) and a Quality

Assurance Program audit.

b.

A letter from CEI to the ASME, dated November 30, 1978, documenting

CEI's agreement to file the required N-3 Data Report Form with

the Jurisdictional Authority (the State of Ohio).

c.

A letter from ASME to the State of Ohio, dated January 8, 1979,

notifying the Jurisdictional Authority that an application has

been received from CEI for an Owner's Certificate of Authorization.

d.

Report of an evaluation performed by Gilbert Associates for the

licensee, dated February 13, 1979, and titled, " Requirements

for 'N'

stamping ASME Section III Piping for the Perry Nuclear

Power Plant."

The discussions with the licensee and review of the above documents,

elicited the following significant concerns regarding the licensee's

compliance with ASME Code certification requirements:

a.

The installation codes currently in effect for Specifications

SP-38, SP-39 and SP-90 require final overall responsibility

signoff by an "N" certificate holder.

At present, there is no

"N" Certificate holder on the Perry Project. Although no

significant instrumentation installation work has been done by

Johnson Controls under Specification SP-90, the work covered by

Specifications SP-38 and SP-39 is approximately 20% complete.

-9-

i762 057

Technically, the "N" stamp authorization is not required until

final system acceptance; however, the documentation and trace-

ability requirements to assure full code compliance make an

early "N" authorization essential.

b.

Substantial amounts of hardware under Specifications SP-38,

SP-39, SP-44, SP-47 and SP-90 will be installed to code editions

which are earlier than the code editions and addenda in effect

for the design and fabrication of the components. There are

special cases where this may be acceptable under the code, such

as when a total system is designed and procured under one order

at one time to one editiot of the code; however, most of the

design and procurement under the above specifications was not

done on a systems basis.

c.

Although the licensee has been aware since late 1977 of the

potential need for an "N" Certificate authorization for the

Perry Project, CEI has taken no significant actions since the

February 1979 study noted above either to obtain the

"N" Cartificate

authorization or to obtain an exemption with regard to the need

for such a certificate. During this inspection the licensee

stated that a decision has not yet been reached as to whether

CEI will apply for the "N" Certificate authorization, whether

another onsite organization will be requested to obtain the

authorization, or whether a request for exemption from the "N"

certification requirements will be made.

The inspector informed the licensee during the onsite exit meeting

on October 18, 1979, that the failure of CEI to take timely action

to obtain, or to have another onsite organization obtain, an "N"

Certificate authorization for the Perry ASME Code work, or to take

steps to seek relief from the requirement, was a potential item of

noncompliance with Criterion XVI of 10 CFR 50, Appendix B.

Following

evaluation at the Region III office, the inspector notified the

licensee by telephone, on October 31, 1979, that this lack of timely

corrective action will be cited as an item of noncompliance with

Criterion XVI (50-440/79-10-01; 50-441/79-10-01).

During the above mentioned telephone conversation, the licensee

stated that CEI is preparing a letter to NRC which will:

State that the installation work by GE on Specifications SP-38

a.

and SP-39 will be done under an earlier edition of the ASME

Code than that presently specified for the work; an edition

which does not require final acceptance by an "N" Certificate

holder, and

b.

Request an exemption from the "N" Certificate requirements for

the portions of the work under Specification SP-90 which now

require such an authorization.

- 10 -

1762

058

.

3.

Corrective Action on Unit 1 Zero Degree Pipe Whip Restraint,

Reported Per 10 CFR 50.55(e)

The inspector reviewed the corrective actions taken by the licensee

with regard to welding deficiencies found in the Unit 1 zero degree

pipe whip restraint structure. The deficiencies were initially

reported to Region III as a potential 10 CFR 50.55(e) item on June 27,

1979. The final report on the subject was transmitted by the licensee

to Region III on July 23, 1979.

The reported deficiencies were discovered during receipt inspection

and sampling UT of the structure at the Perry Site. The restraint

was fabricated by Ranor Incorporated of Westminster, Massachusetts.

Based on the results of the sampling UT on site, the structure was

shipped to Greenville Metals Manufacturing in Greenville, Tennessee,

a Newport News Facility, for re-UT and repair. At the Greenville

facility, approximately 99% of the welds were re-UT'd, and all

identified defects were repaired. The structure underwent final

inspection at the Greenville facility on July 17, 1979 and was

accepted. The restraint was received onsite on July 19, 1979 and

passed receipt inspection.

To prevent the same type of problem on the Unit II pipe whip restraint,

that structure was removed from Ranor, Incorporated and taken to the

Greenville facility. The licensee stated that all welding done on

the Unit II restraint will be 100% visually inspected and all welds

requiring UT will be re-UT'd at Greenville.

Based on the above, the inspector concluded that appropriate corrective

actions have been taken by the licensee relative to the zero degree

pipe whip restraints. The above 10 CFR 50.55(e) reportable deficiency

is considered to be resolved.

4.

Interviews With Site Construction Craftsmen

During this inspection, implementation of temporary instruction

number 2512/4 (Interviews With Craftsmen at Construction Sites) was

initiated by the two accompanying Region III personnel. The purpose

of this effort is to solicit any substantive concerns and opinions

with respect to construction quality and/or deficiencies in safety

related work. Five (5) craftsmen were interviewed under controlled

circumstances. These craftsmen were involved in containment suppression

pool, piping, and cable tray hanger fabrication activities.

In

general, the craftsmen were collectively impressed with the quality

efforts involved in their site fabrication activities.

Subsequent

NRC inspections shall include increased emphasis on the identified

area of construction activity. Approximately 25 more craftsmen will

be interviewed during subsequent NRC inspections.

- 11 -

1762

059

.

Section II

Prepared by: G. F. Maxwell

Reviewed by: D. W. Hayes, Chief

Engineering Support Section No. I

1.

Interim Maintenance of NSSS Equipment - Units 1 and 2

The inspector observed that, since the cancellation of the

a.

Newport News contract relative to installation and inspection

of NSSS equipment identified in Contract Specifications SP-38

and SP-39, the following events have occurred:

(1) CEI Engineering department has been assigned interim

responsibilitity for the storage and maintenance of the

NSSS equipment located at PNPP Units 1 and 2.

(2) Newport News has been directed, since the issuance of the

"Stop Work" order by CEI (dated September 6, 1979), to

accumulate all applicable quality related documentation

and turn it over to CEI.

(3) CEI Engineering Department has assigned three staff members

the responsibilities of assuring that, during the interim

period prior to re-assigning to a contractor the responsi-

bilities of NSSS equipment, site NSSS equipment is properly

handled and stored.

(4) To assist in carrying out the physical inspections, which

are required during routine maintenance inspections, CEI

has assigned a QC inspector to overview the activities of

the interim maintenance group.

(5) Open noncomformance reports which were generated by Newport

News prior to their receipt of the "Stop Work" order dated

September 6, 1979, are being converted by CEI into "new"

nonconformance reports. The "new" reports will re-direct

those responsible for corrective action (s) to be taken

relative to resolving the unsatisfactory conditions identified

in the open nonconformance reports.

b.

The inspector observed that the assigned CEI Engineering department

personnel and CEI QC inspector (s) have been utilizing draft

- 12 -

t76.

060

.

copies of the CEI procedures which were written for use during

the interim maintenance period. However, the inspector noted

that the procedures were finalized and approved on October 16, 1979

to become effective on October 23, 1979.

The final versions of

the procedures were compared with the draft copies of the

procedures currently being used; no significant differences

were observed.

The inspector has no further questions about

these two procedures (numbered 2-1301 and 3-1302), at this

time.

The inspector interviewed the CEI Engineering personnel who

c.

have been assigned responsibilities for the interim maintenance.

These personnel were found to be cognizant of their responsi-

bilities and duties, as they relate to the maintenance program

and the implementation of the CEI procedure titled, " Field

Storage Maintenance of Equipment" (3-130-2).

As a result of

the interviews;

the inspector observed that the individual

responsible for the " visual" inspection of NSSS equipment

storage did not have certifications showing that he was certi-

fied to the inspection levels as prescribed in ASNI N45.2.6

Section 2.2. Prior to the completion of the inspection, the

RIII inspector was given a copy of the aforementioned individuals

certification, indicating that the individual was qualified as

a " Mechanical (limited) Level II" inspector. The inspector has

no further questions about this matter, at this time.

d.

The inspector selected two pieces of NSSS Associated equipment

to determine if their storage conditions were satisfactory.

Both were found to be protected and covered, with space heaters

energized (RCIC pump motor IE-51-C001 and Fuel Pool Circulation

pump motors 0641-C003 A and B).

The inspector observed that

the assigned CEI QC inspector has not, in either case, conducted

the independent physical inspections as required by CEI. QA

personnel had already identified this unsatisfactory condition

in a nonconformance report numbered CQC NR #1415. Further, the

inspector was informed that this condition is limited to approxi-

mately twelve pieces of safety-related mechanical equipment and

that the inspection points, which were missed, will be inspected

during the upcoming scheduled monthly inspections. The inspector

has no further questions about this matter at this time.

2.

Inspection Status of Safety-Related Materials - Units 1 and 2

a.

The inspector observed that on June 27, 1979 a nonconformance

report was generated by CEI to identify that almost all of the

electrical equipment and motor operated valves, which were

still under control of the receiving warehouse, had " inadequate

documentation". The inadequate documentation was related to

-' -

i762 06)

the environmental testing of Class IE equipment, as required by

purchase specifications to assure compliance with IEEEE 323

and/or IEEE344. The inspector was informed by the CEI representative

responsible for the receipt inspection and control of CEI/ Gilbert

purchased materials that:

(1) Ninety-nine percent of the affected Class 1E equipment and

motor operated valves, which are still being controlled by

CEI warehouse personnel - not released to site contractor

personnel for installation, have been clearly identified

as nonconforming.

(2) The CEI representative does not know the identification

status of the affected motor operated valves and Class 1E

equipment which had been released to site contractor

personnel prior to June 27, 1979.

b.

On October 17 and 18, 1979, the inspector, accompanied by CEI

QA personnel, toured the Pullman Power Products (PPP) piping

installation work areas in the Auxiliary and Intermediate

buildings. The inspector selected five safety-related motor-operated

valves which had been released to PPP prior to June 27, 1979.

One of the valves was in the process of being installed, one

was not being installed and had not yet been installed and the

other three had been installed. None of the valves had any

identification showing that they were nonconforming or had been

" conditionally released.

The inspector and the accompanying

CEI QA representative requested that the selected valve numbers

be cross-checked by Gilbert Site Engineering to determine if

these valves were also nonconforming due to " inadequate documentation".

The provided " Perry Valve Bill of Material Status Report"

indicated that each of the selected valves were listed as being

among those motor-operated valves not having adequate documentation

to assure compliance with the afore IEEE Standard (s). The

inspector informed the licensee that this failure to clearly

identify and track nonconforming materials is contrary to 10 CFR 50, Appendix B, Criterion XIV; PNPP PSAR, Chapter 17,

Section 17.1.14.1; CEI Corporate Nuclear Quality Assurance

Program, Section 1400, paragraph 1.1, and CEI PNPP Construction

Quality Section Procedure 1502 (dated May 1, 1978), paragraphs

5.2.2 and 5.2.3 (440/79-10-02; 441/79-10-02).

762 062

- 14 -

.

Section III

Prepared by: K. R. Naidu

Reviewed by: D. W. Hayes, Chief

Engineering Support Section 1

Observation of Work Activities - Welding of Unit 1 Reactor Building Columns

The inspector observed welding activities associated with the installation

of the columns in the Unit 1 Reactor Building and determined the following:

A.

All the 17 columns have been installed in place. Pittsburgh

Bridge and Iron (PBI) subcontracted the installation work to

Kelley Steel Company (KSC) who perform work under the PBI QA

Manual. Procedure Exhibit AQ titled, " Procedure for Installation

of 17 Botton Tier Columns", was used to install the columns.

Prior to welding the botton stub (which is embedded in concrete)

to the column, an ultrasonic test was performed on the base

metals utilizing NDE Procedure #U.T.NIC-059, Revision 4.

A.

Welding on two columns identified as 4 and 6 was in progress.

C.

Weld Procedure Specification prequalified to the AWS D1.1-72

code for joint BU5a was being utilized.

D.

E7018 type electrode was being used.

E.

Records indicate that weldors performing the weld were qualified.

F.

The root pass and subsequent layers of the weld were subjected

to Magnetic Particle (MT) examination by the prod method utilizing

MT-NIC-052 Revision 2, dated May 9, 1979. Records indicate

that the Level II NDE inspector was qualified to perform MT.

G.

On column 10, an MT after the root pass revealed an indication.

PBI-105, dated September 13, 1979, was generated to identify

this unacceptable condition.

The indication was explored to a

depth of 5/16".

The inspector reviewed NCR PB1-118, dated October 3, 1979 which was

generated to identify a 2" x 8" area of porosity in the welds

attaching the bent plate to the upper flange located on the east

side of beam 305B4. The beam is located at elevation 679'-6" in the

control room complex. This unacceptable indication was apparently

overlooked during fabrication. Corrective action recommended was as

follows:

- 15 -

~1762OS3

A.

Grind out areas of excessive porosity to sound base metal.

B.

Repair weld ground areas in accordance with Weld Repair Procedure

15.6 (PBI QA Manual).

C.

Grind repaired areas to base metal.

D.

Visually inspect repaired areas.

CEI approved the corrective action and included MT examination of

each layer of weld.

The inspector has no further questions on this matter.

- 16 -

1762

064

Section IV

Prepared by: J. F. Suermann

Reviewed by: D. W. Hayes, Chief

Engineering Support Section 1

1.

Containment Structural Concrete - Procedures

As part of observing a containment pour, the inspector reviewed the

training and qualification procedures of U. S. Testing Company prior

to reviewing the records of four QC inspectors who performed inspections

on the pour. The inspector had no comments on U. S. Testing Company

Procedure QCP-6, " Training of Inspection and Test Personnel", Revision

1, dated May 3, 1978. Review of Procedure UST-TQ-1, Revision 9,

" Training and Qualification of Inspection, Test and Audit Personnel",

dated March 23, 1979 revealed that the procedure specified experience

factors for use as a basis of qualification that were less stringent

than the minimum capabilities stated in ANSI N45.2.6-1973.

Although

the requirements of Paragraph 3.1.2 of Procedure UST-TQ-1 are recognized

in that other relevant factors may be considered in qualifying

inspection and test personnel, the paragraph is not sufficient

authority for exercising less stringent criteria than that contained

in Regulatory Guide 1.58 and ANSI N45.2.6, to which the licensee is

committed. Discussions with U.S. Testing Company personnel and a

records review (see paragraph 3 below) indicated that Paragraph

3.1.2 was apparently being used as a " loophole" to hire personnel

with little or no prior experience, relying on site conducted indoc-

trination as a basis for certification. The liberal interpretation

on the part of the procedure requiring certain prior experience

levels does not meet the intent of ANSI N45.2.6 and as such is in

noncompliance with 10 CFR 50, Appendix B, Criterion V (50-440/79-10-03;

50-441/79-10-03).

2.

Containment Structural Concrete - Observation of Work

The inspector was notified that a pour was in progress in Containment

1. National Engineering and Contracting Company, a site concrete

contractor, was placing pour No. RB1-WO3-645; the pour was a drywell

wall of approximately 600 CY of 5000 psi concrete placed from elevation

630'-9" to elevation 646'

At the time the inspector arrived, the

grout construction joint layer had already been placed and approxi-

mately two feet of concrete had been placed. The Pre placement

Checkout Record was reviewed and it appeared the required checkoffs

were made and the final QC clearance was obtained prior to the pour.

- 17 -

1762 06l5

'

The Concrete Pour Card and Placing Record were in order and indicated

that the six man vibration crew was briefed on proper technique

prior to the pour. The Inspection Report for Concrete Placement,

dated October 16, 1979, indicated that the required hold points for

concrete pre placement, reinforcing steel placement and concrete

placement were met.

It further indicated that the six vibrators

used on the pour were checked for calibration as required. All six

vibrators met or exceeded the minimum 8000 cpm calibration requirements.

The inspector observed the placing and vibrating crews in progress.

Placement operations appeared under control; concrete was confined

to a maximum free fall distance of five feet; concrete was not moved

excessively in a lateral direction; the placing sequence appeared to

prevent the formation of cold joints; vibrator crews appeared to be

achieving the proper consolidation and were following procedures

regarding mode and time of vibrator insertion.

QC personnel carefully

followed both the placing and vibrating operations.

U. S. Testing

Company QC inspectors performed the required slump, temperature, air

entrainment and unit weight tests per procedures.

Concrete compression cylinders were made according to ASTM requirements

and the sampling frequency was followed according to procedures.

Field curing boxes were used to retain the cylinders for a maximum

of twenty-four hours. The inspector noted that one of the three

curing boxes indicated the temperature range exceeded the maximum

permissible 60-80 F limits during the initial curing cycle. The

licensee correctly identified this as a nonconforming situation and

took prompt corrective action to remedy the problem and also prevent

its recurrence. The inspector noted water was added at the truck

discharge point prior to emptying the drum contents. Procedures

permitted this practice and the amount of water added was controlled.

Water sight gauges on the trucks were operative and checked by the

QC inspector. QC inspectors were aware of the requirement to mix

added water with 30 revolutions of the drum.

No items of noncompliance were identified in this area.

3.

Containment Structural Concrete - Quality Records

a.

Concrete data and related equipment -

The IE inspector reviewed the calibration records for the

testing apparatus used on pour RBI-WO3-645, and found the

following equipment had current calibration stickers:

air

meter #14, slump cones #7 and 14, unit weight bucket #8, field

scale #24, and thermometer #124. Calibration records for

trucks 66, and 83 and 84 indicated all water sight gauges were

operating within tolerance and the trucks unitormity test

- 18 -

.

1762

066

.

results met ASTM C-94-73A requirements.

NRMCA certifications

for the main and back-up batch plants were current.

The main

batch plant automatic console gauges, admixture meters, and

scales were currently calibrated. The concrete and placement

Identification Sheet for the pour indicated that the specifi-

cation requirements were met with regard to slump, air entrainment,

temperature and unit weight.

Compression test specimen cylinders

were made as required by the specification.

b.

Personnel qualification records -

The records of the four U.S. Testing Company personnel assigned

to pour RBI-WO3-645 were checked against the requirements of

procedure UST-TQ1 and against ANSI N45.2.6.

Three of the four

record files inspected revealed the following:

(1) The documented experience and education factors did not

meet the procedural and/or ANSI requirements committed to

with regard to type or duration.

(2) Site conducted proficiency testing appeared to be the main

basis for certifying individuals and was the only relevant

factor in the personnel backgrounds.

(3) Supportive requirements such as eye / physical exams, pertinent

training and indoctrination were being administered after

the date of qualification of the individual.

(4) The Document of Qualification did not specify the period

of qualification. These practices are contrary to Regulatory

Guide 1.58 and ANSI N45.2.6 and as such are in noncompliance

with 10 CFR 50 (Appendix B), Criterion V.

This is a

second example of the previously cited item of noncompliance

(50-440/79-10-03; 50-441/79-10-03).

Exit Interview

The inspectors met with site representatives (denoted under Persons

Contacted) at the conclusion of the inspection on October 18, 1979. The

inspectors summarized the scope and findings of the inspection.

The

licensee acknowledged the findings reported herein.

- 19 -

i762

067