ML19211A811
| ML19211A811 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 11/30/1979 |
| From: | Benedict R Office of Nuclear Reactor Regulation |
| To: | LOUISIANA POWER & LIGHT CO. |
| References | |
| NUDOCS 7912210107 | |
| Download: ML19211A811 (8) | |
Text
W f'eeting S ama ry
['ocket File
- 1. Purrin Nf'.C POR J. Ani.iht Local PDR S. Hanauer TIC R. Tedesco NRR Reading R. Bosnak LWR #2 File S. Pawlicki E. Case F. Schauer D. F. Ross K. Kniel D. B. Vassallo T. Novak S. A. Varga Z. Rosztoczy D. Skovholt W. Butler W. Ganmill V. Benaroya J. Stolz R. Satterfield R. Baer V. Moore
- 0. Parr M. Ernst L. Rubenstein F. Rosa C. Heltemes R. P. Denise W. Haass EP Branch Chief R. Houston G. Chipman L. Crocker J. Collins F. J. Williams W. Kreger R. J. Mattson G. Lear R. LeYoung B. Youngblood Project Manager -
R. Benedict L. Hulman Attorney, ELD -
H. McGurren NRC
Participants:
J. Lee IE(3)
S. Boyd ACRS(16)
R. C. Stewart, Regio: IV J. Rothfleisch T. Abell G. Patthews W. Lovelace H. Berkow L. Schaub 7 912210 1635 270 g
NOV o o gg P00R 01 BEL DOCKET NO. 50-382 APPLICANT: LOUISIANA POWER AND LIGHT COMPANY FACILITY:
WATERFORD STEAM ELECTRIC STATION, UNIT 3
SUBJECT:
SumARY OF WATERFORD UNIT 3 SITE VISIT BY CASELOAD FORECAST PANEL Members of the NRC staff visited the Waterford plant site on September 25, 1979 to view r nstruction progress to date and to discuss construction progress with the applicant. A complete set of slides shown by the applicant during this meeting are available in LWR-2 files. Participants in this meeting are listed in Enclosure 1.
The applicant briefly described the organization of the project, including engineering, procurement, quality assurance, and startup staffing. The applicant also reported data on bulk quantities installed. These data are summarized in.
The following were major points of discussion:
1.
Overall, construction is about 3.25; behind. Half of this lag is due to lack of craft manpower, as discussed below.
2.
Installation of large pipe is ahead of schedule but that of small pipe is behind. The piping contractor (Tompkins-Eeckwith) is short of pipefitters and welders -- this is, apparently, a nationwide problem. During this shortage the available manpower will concentrate on installation of small pipe.
3.
Availability and turnover rates of manpower for the instrument contractor (Mercury), and the electrical contractor (Fishback and Moore) are also significant problems. Turnover rates range up to 30-40 percent.
4.
Canadian electricians and welders are being hired and some work is going into overtime, adding incentive for workers to stay on the job. Lower turnover increases producti.vity. The Canadians are high-productivity workers.
5.
A new HVAC contractor has been hired and is producing 50% better.
6.
Cable-pulling has fallen behind. The applicant reiterated what he had told us previously: cable pulling goals are related to when the startup testing requires completed cabling. This is shown in Enclosure 3.
. OFFICEh............
, URN-E p 0->
NRC FORM 318 (9 76) NRCM 0240 DU.S. GOVERNMENT PRINTING OFFICE: 1979-289-369
NOV 2 1979
,7 7.
The preparation of startup procedures continues. They have identified about 1800 procedures required, totalling about 87,000 pages. They are trying to get procedures approved internally at least 90 days before testing begins in order to allow sor= slack time and time for hRC review.
Eleven systems out of a total of 127 have been released for test. Also, much of the instrumentation calibration is being done before installation.
Progress on procedures is tabulated in Enclosures 4 and 5.
8.
Other problems, not necessarily critical at this tire, were identified.
a.
Design and analysis of firo protection needs early feedback from fmC review. The staff noted that, due to THI-2 related activities, the staff's schedule for such review could not be established now.
b.
Stress analysis of the pressurizer relief valve piping is continuing.
This is a basic engineering problem; it is not related to TNI-2.
c.
The Lonorgan cain steam safety valves failed to nect the blowdown requirements. Lonergan is working to rodify the internals, but a parallel effort is underway to get competitive bids on other valves.
9.
With respect to THI-2 related activities, the applicant expects to be able to deternine the impact of THI-2 by the end of 1979.
10 Financially, LP!.L will be able to maintain construction at the present rate through the first few months of CY 1930. Under the law, their existing request for rate relief must be decided by the end of CY 1979.
During the exit interview the staff stated that it was willing to naintain for now the September 1981 fuel load date that we forecast at the last neeting.
However, there nust be successful recovery in construction progress to actually meet that date. Furthermore, it appears that there is no " fat" in the schedule for completion of their startup procedures and testing. The applicant agreed that, although a May 1981 completion date is still the project schedule, the Septenber 1931 date is now nore realistic.
OMM sbud by sy R. A. Benedict Light Water Reactors Branch No. 2 Division of Project Management
Enclosures:
As Stated ces w/ enclosures:
See next page 1635 272 DPM: LWR 72 DPM:
R
'~
ogg,c, p, SURNAMEk.
DATEk.
.l.
NltC FORM 318 (9-76) NRCM 0240 D U.S. GOVERNMENT PRINT;NG OFFICE: 1979 289 369
Mr. D. L. Aswel1 NOV a i p*
Vice President, Powr !i o.i
- i t on Louisiana Power & Li+1
.i c.
142 Delaronde Street f;ew Orleans, Louisiasia li' i 1 cc:
W. Malcolm Stew:
0, Monroe 8 Lenanr 1424 Whitney Buil<!in i f;ew Orleans, Leuisi.'.
N 130 Mr. E. Blake h)Iplg[
Shaw, Pi ttman, r.nei<
ini I, d ridge 1800 M Street, i.. U.
l f
UjjjjfIk f
Washington, D. L.
- 'F"'
hr. D. B. Lesto Production Lngine"r Louisiana Power E I i " ' ' " apa ny 142 Delaronde St a cet f;ew Orleans, Lou i. im-
,"'l/4 Lym an L. Jones,.fr., I ai.
Gillespie & Jones 910 Security Hcc m' u.':
Unilding 4900 Veterans f,t wr i al Ioulevard Metairie, Louisian.i liivT Luke fontana, Evi.
Gillespie & Jones 824 Esplanade twi.ne flew Orleans, Louie i on i t0116 Stephen M. Irvini. '<i.
One hierican Pl.io. ',c e ' e 1c01 Ca ton Route, Lou i r. i. r.'
ar'!$
f 1635 273
\\
faiv
- gg7c, ENCLOSURE 1 ATTENDANCE LIST MEETING WITH W,TERFORD SEPTEM3ER 25,1979 NRC - STAFF S. Boyd R. Benedict R. C. Stewart (IE, Region IV) 1:P fL_
D. L. Aswell D. B. Lester F. J. Drumnond T. K. Armington
- 0. P. Pipkins R. W. Prados S. A. Allenan C. A. Smiroldo EBASCO J. Crnich R. J. Milhiser R. K. Stampley R. McMasters M. Soniker B. Pettigrew J. Costello H. Mulligan F. Sernatinger s
1635 274
ENCLOSURE 2
.e -,,qy BULK QUANTITIES SCHEDULED SCTU3L DATEOF lin0u EXPcCIED
$/31//iH THROUGH 9
RECOVERY IIEB U15m EQRECASI 8/31/79 CONCRETE CY 201,000 200,246 195,822 NOT REcuiRED LARGE PIPE LF 103,322 81,092 82,433 SMALL PIPE LF 100,845 48,421 41,955 MARCH, 1980 LARGE HANGERS EA 6,487 4,414 4,123 APRIL, 1980 CABLE TRAY LF 43,522 41,129 40,082 PUNCH LISTING EXPOSED CONDUIT LF 363,870 187,658 178,188 DECEMBER, 1979 CABLE LF 4,000,000 1,097,420 882,306 JULY, 1980 TERMINATIONS EA 176,000 21,193 9,564 AUGUST, 1980
- PER PROJECT SCHEDULE ESTABLISHED 4/79
-a LJ1
a 2!l "l
!W@ '
- s5. m E!
'i 4
t= 0E 3$ug s
S s
v s
0 n
o o
o o
o o
o o
0 V
l 0
k 1 [/
N M
bl 19
/,
Y[b
. /
l
.r, i,
1 I!I, i
5 I
r hd i i m sr l
S k
h I[l l! - :
l c s.
h',
ol.h y6 e
7 i
c t
e T l,.,
,j / _
{
U a'
f.
ll l
Ijl i: l! l A
b "
iI f
!i P
l
{
i
/
I L
10]
sL
- ll;
!iii
!t E
ll s
. ' D l
.N~
II D~
/
~
/
. ~
/
Y
/_
l
/_
~
~
C j Ii
~
0I
~
p, v
[{/
E f'.
{i P
M p
O i
)
/
t W
/
V l
[,_
l E
A
/
(; j i R
f
,/
A M
A d
I N
l D
i J R
/
E fl L' !
C e
i nQ
/
/!
i l
O n
UD M"w j!
N J
AI 1{
T j!
lRR-o a
f E6 lI (
ll TD n
/ ;ff R
A n
f,t O
4
/, !
J F L
PO I /) /l s
- I C
l t
1I B
o
.l,
'l.
1 l
j (T
A Lll;e:
I,j>[i k
f
'I. l; "Y
L f
E A' f' o
l! I,y !
I
!,;!ll i: /
'I l
a
(
f
_u A
jli lj i
Il a !
I 8
l l
M iL4 I
!l o[
i e
i [
'l
{g C
e r
A B
}
n 3
TL S
1 OE P
c' S
O w
UU a_
L P L PI N
A n
E
.i S t
Q J
T
_ AU I
a_RR TE i
F
/_
M,
s U
M a P E e
N r
t_
T u
3 A
)3m Jr%y t
M x
.t i
gA M CO wmL c
d
~
J
/
0 ENCLOSURE 4---
Procedure Proce-Proce-Proce-Proce-Delin-Type dure dure dures dures quent Estimate Present in Approved 4/79 Estimate Process Procedures General change change change change Plant Staff :223 223 0
31 (8) 45 16 Operating 249 249 0
2 (1) 10 4
Maintenance 209 209 0
30 4
23 4
Technical S u p lio r t 239 239 0
36 (33) 68 38 Total Plant Staff 920 920 0
99 (38) 146 62 Total Startup Phase 1,755 1,726 (29) 286 (39) 331 99 45 (33) s 1635 277
b4
)f t
ENCLOSURE 5
'.T' l' r o c e d u r e Proce-l'soce-l' r o c e -
l'soce-11 1in Type il u r e il u s e dures il u s c r.
- 10. n 1 Estimate Present in Approved 4/79 Estimate Process Procedurts General change change change change Startup:
419 419 0
125 (14) 185 38 43 (23) 2 (10)
Prerequi-200 200 0
45 4
site Preservice 29 0
(29) 0 (1) 0 (1)
Preoper-97
'> i G
17 10 0
aL1,na1 Integrated 90 90 0
Tests Total Startup 835 806 (29) 187 (1) 185 37 45 (33) 1635 278