ML19210E695

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-454/79-14 & 50-455/79-14 on 790911-28. Noncompliance Noted:Inadequate Procedures & Failure to Follow Procedures Re Qualification of Personnel & Inadequate Document Control
ML19210E695
Person / Time
Site: Byron  Constellation icon.png
Issue date: 10/23/1979
From: Maxwell G, Suermann J, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19210E691 List:
References
50-454-79-14, 50-455-79-14, NUDOCS 7912050554
Download: ML19210E695 (23)


See also: IR 05000454/1979014

Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-454/79-14; 50-455/79-14

s

Docket No. 50-454; 50-455

License No. CPPR-130; CPPR-131

Licensee-

Commonwealth Edison Company

Post Office Box 767

Chicago, IL 60690

Facility Name:

Byron Nuclear Generating Station, Units 1 and 2

Inspection At:

Byron Site, Lyron, IL, and CECO Corporate Office

Inspection Conducted: September 11-28, 1979

/' f /'Y.'~~

'

ft/f'//77'

Inspectors:

J. E. Konklin

-<

^ '

&

ll

J. Y

s(f

j

j

s

G. F. Maxwel

/c'// 9 / 7 7

,

',

L /.~

NW

J. F. Suermann, (September 18-28 only)

/o /.2 J/29

Accompanying Personnel:

C. C. Williams (September 28 Exit Meeting only)

D. W. Hayes (September 28 Exit Meeting only)

J. H. Neisler (September 28 Exit Meeting only)

( ?c'] % /cb <. -

Approved By:

C. C. Williams, Chief

/ C/ 2 3/ 7 e

Projects Section 2

/

/

/

Inspection Summary

Inspection on September 11-28, 1979 (Report No. 50-454/79-14; 50-455/79-14)

Areas Inspected. Content and implementation of the licensee's Quality

Assurance Program in the following areas:

1.

Site quality assurance, including auditing, trending, and surveillance

activities, and the control of noncomformances.

2.

Corporate quality assurance, including auditing, trending, and interfaces.

3.

Design and design changes, including design document control, and incor-

poration of engineering changes. 1502

302

7 912 050 $$ y

.

'

4.

Procurement, including procedures, purchasing activities, and auditing

of materials suppliers.

5.

Control of purchased materials, including procedures, receipt inspec-

tion, otorage and maintenance, and surveillance of site contractors.

The inspection involved a total of 172 inspector-hours onsite or at the

CECO Corporate Office by three NRC inspectors.

s

Results: Of the five areas inspected, two items of noncompliance were

identified in two areas (infraction - inadequate procedures and failure to

follow procedures with regard to qualification of personnel, three examples

- Section I, Paragraph 1.b. and Section III, Paragraph 2; deficiency -

inadequate document control, two examples - Section I, Paragraph 2 and

Section II, Paragraph 4.b.).

1502

303

-2-

'

DETAILS

Persons Contacted

Byron Site

Principal Licensee Employees

,

  • G. Sorensen, Project Superintendent

+*J. McIntire, Site QA Supervisor

  • R. Tuetkin, Lead Mechanical Engineer
  • J.

Mihovilovich, Lead Structural Engineer

  • G.

Smith, Lead Electrical Engineer

J. Porter, QA Mechanical Coordinator

  • S.

Forsha, QA Structural Coordinator

AR. Aken, QA Electrical Coordinator

  • R. Klingler, QA Mechanical Engineer

K. Key, Site Purchasing Coordinator

  • J. Klink, QA Engineer

M. Stanish, QA Engineer

L. Combs, QA Engineer

Huriter Corporation

kM. Somsag, QA/QC Supervisor

H. Lindquist, Material Control Supervisor

M. Zeisk, Lead Auditor

A. Simon, QA Administrator

R. Irish, QA Training Coordinator

Blount Brothers Construction

  • R. A. Donica, QA/QC Supervisor

T. Calsyn, Receipt Inspector

Hatfield Electric

  • G. Van Lyssel, Construction Manager
  • W. Gratza, QA danager

R. K. Donica, QC Inspector

CECO Corporate Office

1502

f.04

Licensee

+ W. Shewski, QA Manager

+*G.

Marcus, QA Director

J. Rohde, SNED QC Supervisor

-3-

J. Westermeir, ShTD Project Engineer

'

R. Janacek, Licensing Administrator

J. Iglehart, Office Supervisor, Purchasing

M. Zolfo, Ascociate Purchasing Agent

J. Harper, Assistant Purchasing Agent

J. Brynildsen, ShTD Engineer

Sargent & Lundy

,

.J.

Lavalle, Project Manager

R. Rakowski, Mechanical Engineer

USNRC-RIII (Exit Meeting Only )

+ C. Williams, Chief, Projects Section 2

+ D. Hayes, Chief, Engineering Support Section 1

+ J. Neisler, La Salle Project Inspector

The inspectors also contacted other licensee and contractor personnel,

including craftsmen, QA/QC, technical and engineering staff members.

  • Denotes those attending the interim exit meeting at the Byron Site on

September 20, 1979.

+ Denotes those attending the final exit meeting at the RIII offices on

September 28, 1979.

Functional or Program Areas Inspected

Functional or program areas inspected are discussed in Sections I, II, and

III of this report.

1502

305

-4-

Section I

Prepared by J. E. Konklin

Reviewed by C. C. Williams, Chief

Projects Section 2

,

is

Procurement and Control of Equipment and Materials

The RIII inspector reviewed documentation and inspected activities

relating to the procurement and control of safety-related equipment

and materials by CECO and by three major site contractors, including

procedures, requisitions, purchase orders, receipt ir.spection reports,

vendor documentation packages, surveillance activities and reports,

audit reports, and storage and maintenance activities. The three

site contractors selected for the review included Hunter Corporation

(Hunter), the site contru9 tor responsible for safety-related piping

and mechanical component installation; Blount Brothers Corporation

(Blount), the site contractor responsible for safety-related structural

concrete work; and Hatfield Electric Corporation (Hatfield), the

site contractor responsible for safety-related electrical construction

activities.

a.

Review of Related Procedures

The inspector reviewed the following CECO general procedures

related to purchasing activities:

(1) Ceneral Procedure No. 702, effective September 6, 1969,

" Purchase Orders."

(2) General Procedure No. 703, effective November 28, 1977,

" Changes in Purchase Requisitions and Purchase Orders."

(3) General Procedure No. 701, effective September 15, 1977,

" Purchase Requisitions."

(4) General Procedure No. 704, effective July 28, 1969,

" Shipment Release".

In addition, the inspector reviewed the following CECO Quality

Assurance Procedures (QP's) related to purchasing activities:

(1) QP No. 4-1, Revision 6, dated October 28, 1977, " Request

for Bid, Proposal Evaluation and Recommendation."

1502

306

-5-

.

(2) QP No. 4-2, Revision 6, dated January 12, 1979, " Evaluation

of Contractor's Quality Assurance Program."

The inspector reviewed the following site contractor procedures

related to the purchasing, receipt and control of procured

materials:

(1) Hunter Procedure SIP 3.602, Revision 2, dated April 28,

'

1978,

-

" Material Receiving and Inspection."

(2) Hunter Procedure SIP 3.102, Revision 1, dated February 9,

1978,

" Material and Services Procurement."

(3) Hunter Procedure SIP 3.801, Revision 2, dated July 31,

1979,

" Storage of Mechanical Components and Materials."

(4) Blount QA/QC Work Procedure No. 2, Issue 8, Revision 7,

dated September 13, 1977, " Procurement Control."

(5) Blount QA/QC Work Procedure No. 10, Issue 4, Revision 3,

dated October 18, 1976, " Receiving, Storage, and Handling."

(6) Hatfield Site Procedure No. 5, Revision 1, dated July 7,

1977, " Class I Material and Equipment Receiving and

Inspection."

(7) Hatfield Site Procedure No. 6, Revision 1, dated July 28,

1977, " Reporting Damaged and Nonconforming Material and

Equipment."

(8) Hatfield Site Pro.edure No. 14, Revision 2, dated October 2,

1978, " Handling and Storage of Safety Related Material and

Equipment."

b.

On-Site Review of Procurement Documentation

The inspector randomly selected, from the Site Purchasing

files, five purchase orders for safety-related equipment and

materials utilized or installed by Hunter Corporation, three

purchase orders for safety-related equipment and materials

utilized or installed by Blount, and tbree pure. nase orders for

safety-related equipment and materials utilized or installed by

Hatfield. The inspector reviewed the purchase orders and the

associated Material Services Requisitions (MSL's) for comnlete-

ness, consistency, appropriate requirements, and appropriate

signoffs per procedures. The inspector also verified that the

1502

307

-6-

selected vendors vere listed on the CECO Approved Bidders Liss

for the specific equipment or material procured.

The inspector noted one discrepancy in reviewing the selected

purchase o ders and MSR's - the CECO QA signoff was missing on

one purchase order; however, CECO QA had approved the associated

MSR which had identical requirements. The inspector then

checked approximately 20 additional purchase orders to verify

,

QA signoff and concluded that the lack of a signoff on the one

.

purchase order was an isolated occurrence and was not indicative

of a problem.

The inspector then reviewed the Material Receiving Reports

(MRR's) and the vendor documentation packages associated with

the selected purchase orders, and verified the warehouse storage

locations and maintenance conditions for the equipment purchased

and delivered under two of the purchase orders. The MRR's were

reviewed for completeness and appropriate signoffs, and the

vendor documentation packages were reviewed for tonformance

with the purchase order requirements.

During review of the MRR's, the inspector noted that the Receipt

Inspection Checklists for equipment and materials purchased by

the CECO General Office were completed and signed as " Inspected

By" CECO Station Construction field engineers and construction

supervisors, aone of whom had been qualified or certified in

accordance with ANSI N45.2.6, " Qualifications of Inspection,

Examination, and Testing Personnel for the Construction Phase

of Nuclear Power flants." CECO is committed to comply with t'e

requirements of Regulatory Guide 1.58/ ANSI N45.2.6 in CECO

Topical Report CE-1-A and in the CECO Quality Assurance Manual,

Quality Requirement QR No. 2.0, Revision 10, dated April 2,

1979. The inspector notified the licensee that this failure to

,

qualify / certify personnel performing inspection activities to

the requirements of ANSI N45.2.6 is an item of noncompliance

with Criterion V of 10 CFR 50, Appendix B (50-454/79-14-01;

50-455/79-14-01). Two additional examples of failure to comply

with Criterion V with regard to qualification of inspection

personnel are discussed in Paragraph 2 of Section III of this

report, and are included under the above item of noncompliance.

2.

Review of CECO Site Engineering Surveillance

The inspector reviewed the curveillance of site cor. tractors by CECO

Station Construction personnel, including the surveillance schedules

and the surveillance check sheets from January 31, 1977 to September 3,

1979 in the mechanical area, from February 1, 1977 to September 10,

1979 in the structural area, and from January 31, 1977 to September 10,

1979 in the electrical area. The inspector found approximately 35

1502

08

-7-

check sheets which were

.t signed off by CECO QA as required by

Sections 3.3 and 4.2 of CECO Quality Procedure QP No. 18-2, Revision

5, dated October 28, 1977, " Surveillance of Contractor Quality

Assurance / Control Activities."

Approximately ten of the abcve discrepancies appeared to be isolat M

occurrences in a series of closely-spaced repetetive surveillances;

however, the inspector found fourteen check sheets in a row involving

'

calibration of instruments used by Hunter Corporation and covering a

-

period of approximately one year, and eleven check sheets involving

concrete and grout pour preparation by Blount, which were not signed

off by CECO QA and which were not isolated occurrences. The inspector

notified the licensee that this failure to properly review and

approve surveillance documentation in accordance with QP No. 18-2 is

an item of noncompliance with Criterion VI of 10 CFR 50, Appendix E

(50-454/79-14-02; 50-455/79-14-02).

One additional example of

failure to comply with Criterion VI with regard to documentation

control is discussed in Paragraph 4.b. of Section II of this report,

and is included under the above item of noncompliance.

3.

Storage of Safety Related Materials

The inspector inspected the warehouse storage of safety-related

materials by Hunter and Hatfield, the storage of structural steel by

Blount, the cable storage yard, the piping and conduit storage

areas, and field storage of the Unit 2 reactor vessel.

No items of noncompliance or deviations were identified.

4.

Review ofCECo Corporate Office Procurement Activities

a.

Audits Related to Purchasing

The inspector reviewed the CECO audit schedules for 1977 through

1979. The inspector then selected and &riewed specific aulits

related to procurement for the Byron Pro 3ect, including andits

of Byron Site Purchasing, QA audits of the CECO Purchasing

Department, and QA audits of materials suppliers including the

NSSS equipment supplier, Westinghouu . The following audi.s

were reviewed:

(1) QA audit of Site Purchasing, Audit Report No. 1, date d

April 25, 1977.

(2) QA audit of Site Purchasing, Audit Report No. 2, dat ed

September 21, 1977.

1502 .509

-8-

(3) QA audit of the CECO Purchasing Department, Audit Report

dated October 5, 1978.

(4) QA audit of the CECO Purchasing Department, Audit Report

dated September 20, 1979.

(5) Audit Report No. 6-79-208, dated August 28, 1979, covering

an audit of Southwest Fabricating and Welding Company on

,

August 23-24,

979.

.

(6) Audit Report No. 6-79-189, dated May 8, 1979, covering an

audit of Ramco Industries Inc. on April 30, 1979.

(7) Audit Report No. 6-79-191, dated June 4, 1979, covering an

audit of Teledyne Brown Engineering on May 31, to . Tune 1,

1970 -

(8) Audit Report No. 6-79-200, dated July 18, 1979, covering

an audit of Pittsburgh Testing Laboratory on July 12-13,

1979.

(9) Audit Report No. 6-79-185, dated May 9, 1979, covering an

audit of Systems Control Corporation on April 24-25, 1979.

(10) Audit Report dated February 15, 1979, covering an audit of

Westinghouse, Monroeville, on February 6-7, 1979.

(11) Audit Report dated February 10, 1978, covering an audit of

Westinghouse, Pensacola, on January 31-February 2, 1978.

(12) Audit Report dated February 16, 1979, covering an audit of

Westinghouse, Cheswick, on February 8-9, 1979.

(13) Audit Report dated February 16, 1979, cevering an audit of

Westinghouse, Tampa, on February 5-6, 1979.

No adverse issues were identified.

b.

Review of General Office Purchase Orders

The inspector selected two purchase orders from the General

Office Purchasing files for review, with emphasis on the

inclusion of specified technical requirements in the procure-

ment documents, conformance with the approved bidders list, and

receipt of the required technical information in the vendor

documentation submittals. The following purchase orders and

associated documents were reviewed:

1502

510

-9-

.

(1) Purchase Order No. 186239, dated June 27, 1975, with ITT

.

Grinnel Corporation, for procurement of safety-related

hangers, snubber and supports to S&L Specification F/L-2771

as revised March 14, 1974, with change order of August 20,

1976 to add procurement of mechanical seismic restraints

and attachments.

(2) S&L Specification F/L-2771, as noted above. The inspector

'

did not review the specification in detail, but verified

.

that the correct specification was included in the purchase

order and that the QA requirements fo' vendor documentetion

had been included.

(3) Station Nuclear Engineering Department (SNED) letter cf

June 17, 1975 to CECO Purchasing, requesting the inclusion

of Specification F/L-2886 for mechanical seismic restraints.

(4) Price requests dated April 5, 1974 to five bidders for the

original purchase to F/L-2771; and September 18, 1975 to

three bidders for the mechanical seismic restraints to

F/L-2886.

(5) Letter of April 4, 1978, from CECO to ITT Grinnel Corporation,

which accepts the Grinnel QA Program.

(6) The SNED vendor submittal file for Purcnase Order 186239.

The inspector verified that the required procedures,

analyses, and test results were submitted by the vendor

and reviewed by S&L.

(7) Purchase Order No. 222430, dated March 10, 1978, with

Chicago Bridge & Iron Company for pipe whip restraints to

Specification F/L-2909 dated September 21, 1977.

(8) Specification F/L-2909, as noted below. The inspector

verified that the specification included appropriate

acceptance criteria, that the QA requirements for vendor

documentation were detailed, and that an inspection point

program was incorporated.

(9) Nuclear Price Request NUPR No. 15218, dated September 27,

1977, and SNED to Purchasing letter dated January 23,

1978, which evaluated the proposals received and noted

that the QA manuals had been accepted for specific bidders.

(10) Letter of July 24, 1978 from CECO to Chicago Bridge & Iron

Company, which accepts the CBI Quality Assurance Program.

1502

311

- 10 -

t

(11) The ShTD vendor submittal file for Purchase Order 222430.

-

The inspector verified that the required procedures,

analyses, and test results were submitted by the vendor

and reviewed.

No items of noncompliance or deviations were identified during

the above review.

s

.

1502 312

- 11 -

.

.

Section II

-

Prepared by G. F. Maxwell

Reviewed by D. W. Hayes, Chief

Engineering Support Section 1

s

1~

Audits Conducted by CECO Site QA - Units 1 and 2

a.

The inspector reviewed the site audit schedule for 1977, 1978

and 1979 to determine if audits are being scheduled as required

by CECO " Byron Quality Instruction No. 11" (current revision),

CECO Topical Report CE-1-A (section 18) and therefore ANSI

N45.2.12Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2.12" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process..

b.

The inspector randomly selected the below listed Ceco Site QA

audits to observe if audits are being conducted as scheduled,

if audits are being documented, if CECO QA is conducting follow-

up inspectisn (as required) to determine that satisfactory

corrective action has been taken and if aedit personnel were

qualified - as required per CECO Topical Report CE-1-A, Section

18.

(1) Audits of Hatfield Electric Company (HECo) (the site

electrical contractor), CECO audit reports numbered;

6-77-72, 6-78-140, audit #6, 6-78-105, 6-78-162 and

6-78-123.

(2) Audits of Peabody Testing Services and Pittsburgh Testing

Laboratory (PTL) (the site testing groups responsible for

concrete testing and nondestructive examination of welds /

piping), CECO Unit reports numbered; 7-22-77, 6-79-192 and

6-79-172.

(3) Audits of Hunter Corporation (HC) (a site contractor),

CECO audit reports numhered; 6-78-121, 6-78-145 and

6-78-160.

(4) Audits of Blount Brothers Corporation (BBC) (a si'.e con-

tractor responsible for concrete activities), CECO audit

reports numbered; 6-78-101, 6-78-111, 6-78-133 and 6-78-156.

(5) Audit of CECO Station Construction, CECO audit reports

numbered; 6-78-154 and 6-77-56.

No items of noncompliance were identified.

1502 313

- 12 -

2.

Nonconforming Conditions Identified by CECO or Site Contractor

-

Personnel - Units I and 2

The inspector observed that CECO site QA has established and is

a.

maintaining a Nonconformance Repert (NCR) station log to monitor

resolution per CECO Topical Report CE-1-A, Section 16.0, page

16-2 and therefore ANSI N45.2, Section 17.

'

b.

The inspector observed that resolution and appreval of corrective

.

actions by Engineering, relative to Nonconformance Reports

(NCR's), is ht ng completed in a timely manner - a requirement

of CECO Topical Report CE-1-A, Section 16.

This observation

was confirmed by a review of 45 NCR's initiated by B.B.C.,

four

NCR's initiated by P.T.L. and 16 NCR's initiated by H.C.

c.

The inspector observed that; Engineering is issuing monthly

reports indicating the status of all NCR's submitted for reso-

lution, the Site QA Supervisor is performing follow-up and

final approval to assure satisfactory correction of nonconforming

conditions, and the site QA Supervisor is conducting ar extensive

overview of site NCR's - a requirement of CECO Topical Report

CE-1-A, Section 16.

These observations were confirmed as a

result of interviews with site personnel, a review of the above

mentioned NCR's, Monthly QA Performance Measurement Reports

(CECO) and the NCR logs maintained by CECO.

No items of noncompliance were identified.

3.

Audits Conducted by Site Contractors - Units 1 and 2

a.

The inspector reviewed Hunter Corporation audit schedules (for

1977 and 1978) and Hunter audit reports numbered 2-06, 2-02 and

058-2 to observe; if audits are being conducted as scheduled,

if audits are being documented, if Hunter QA personnel are

conducting follow-up inspection (as required) to determine that

satisfactory corrective action has been taken and if audit

personnel were qualified. The audit scaedules, reports, follow-

up, audit personnel records and corrective actions were compared

with the requirements of Ceco Topical Report CE-1-A (section

18) and therefore ANSI N45.2.12.

b.

The inspector reviewed Blount Brothers Corporation (BBC) audit

schedules (for 1977 and 1979) and BBC audit reports numbered

Q4-323 and Q4-240. The audit schedules, reports, follow-up,

audit personnel and corrective actions were compared with the

requirements of CECO Topical Report CE-1-A (section 18) and

therefore ANSI N45.2.12.

1502Property "ANSI code" (as page type) with input value "ANSI N45.2.12.</br></br>1502" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process.

314

- 13 -

c.

The inspector reviewed Hatfield audit reports numbered H06-77-03,

H06-78-1 and audit report dated February 23, 1978 to observe;

if audits are being documented, if Hatfield QA personnel are

conducting follow-up inspection (as required) to determine that

satisfactory corrective action has been taken and if audit

personnel cere qualified. The reports, follow-up, audit per-

sonnel and corrective actions were compared with the requirement

of CECO Topical Report CE-1-A (section 18) and therefore ANSI

,

N45.2.12.

As a result, on September 13, 1979, the inspector

.

observed that Hatfield had not retained a copy of the site

audit schedules for the years prior to 1979. However, prior to

the NRC site exit (on September 20, 1979) these audit schedules

were re-constructed by the Hatfield Site QA Manager.

The

inspector compared the re-constructed schedules with CECO site

QA audit and surveillance schedules (for dates pricr to 1979);

the inspector has no further questions about this matter at

this time.

No items of noncompliance were identified.

4.

Design and Design Changes - Units 1 and 2

The inspector randomly selected eleven Field Change Requests (FCRs)

from the CECO Station Construction Department's (SCD) Field Change

Request Log. The purpose of selecting the FCRs was to determine:

if FCRs are receiving the proper approval prior to work being com-

pleted (as applicable); if adequate interface exists between SCD,

Station Nuclear Engineering Department (SNED) and the Architect

Engineer (Sargent & Lundy); if the applicable site cor. tractors are

maintaining or referencing the FCRs (as applicable) on the affected

design document (s); and if the SCD Field Change Request Log indicates

(accurately) the status of FCRs. The applicable requirements which

were used as a reference included CECO Topical Report CE-1-A Section

3.2 and 6.0; ANSI N45.2.11, Sections 2.2.15 and 5.1; CECO Quality

Procedure 3-2 (current revision); CECO Byron Site Instructions

numbered BQI-9 (revision 1) and BQI-10 (revision 4); Blount QA/QC

work procedure No. 1 (Issue 10, Revision 9); Hatfield Procedure

No. 4 (Issue 1, Revision 2); and SNED Procedures numbered Q.8 and

Q.9.

As a result of the reviews of the SCD Field Change Request

Log; interviews with CECO, SCD, SNED, S&L and contractor personnel;

and comparisons made with nine of the eleven FCRs at the applicable

contractors work locations:

The inspector observed that the site Hatfield QC inspection

a.

group did not have a copy of FCRs numbered 277 aor 281. Also,

the applicable drawings retained by this group did not have a

copy of these FCRs either attached or referenced on them

(reference Hatfield Procedure number 4, Revision 2, Issue 1,

paragraph 5.18.7).

During a subsequent inquiry, the inspector

1502 il5

- 14 -

was informed by CECO QA that all FCRs held by Hatfield (that

are numbered 1 through 400) cre under re-evaluation by Hatfield

Engineering in reference co a NRC item of noncompliance identi-

fied in IE inspection repcrt 50-454/79-01 and 50-455/79-01.

The inspector confirmed this with the assigned NRC RIII electrical

inspector who had identified the noncompliance (454/79-01-C.,

455/79-01-02).

The aformentioned concern will be followed-up

as part of the RIII inspection to assure satisfactory resolution

,

of noncompliance item numbered 454/79-01-02 and 455/79-01-02;

.

this matter is unresc1ved (454/79-14-03;

455/79-14-03).

b.

Relative to three other FCRs, (numbered 605, 775 and 780), the

inspector observed:

(1) FCR 605 was initiated on November 16, 1978 to allow Hunter

to increase the sleeve length on some oiping system wall

sleeves for Unit 2 Reactor building.

on September 20,

1979, the inspector and CECO QA personnel noted that

neither Hunter, CECO, SCD, or CECO QA had a/the approved

copy of the FCR. On September 26, 1979, the inspector

noted that the S&L Project Manager for Byron has a letter

d aeu December 20, 1978, wherein he claimed that he was

forwarding the approved FCR 605 to the Byron Station Con-

struction Drpartment. On September 24, 1979, saile inter-

viewing tiu CECO SCD representative responsible for the

mechanic,1 piping system's erection, the inspector observed

that S&I approved an Engineering Change Notice (ECN)

numbered 957 on December 20, 1978.

S&L wrote ECN 957 in

response to FCR 605 thereby " superceding" or causing the

FCR condition to be upgraded by a more " senior" design

document.

The CECO SCD representative assured the inspector

that no affected construction activities had been conducted

prior to the site's receipt of the approved " senior"

document. The inspector observed that Hunter and SCD did

s

have a copy of ECN 957; however, neither the SCD Field

Change Request log or any other CECO site logs accurately

shoved the " approved" status of FCR 605.

(2) The inspector and CECO QA personnel observed that SCD

Field Change Request log did nat accurately show the

telephone approval for FCR 775 or 780.

A review of these

two FCRs, with attachments, indicated that tney had received

' telephone approval on May 4,1979 and May 10, 1979 respec-

tive_1y; however, the SCD Field Change Request log did not

show1h3L telephone approval had been received.

The CECO Q.i % nual, Quality Procedure 3-2, Revision 6,

paragraph 4.5 jequires that SCD be responsible for the

logging and coordination of FCRs.

The inspector informed

1502

516

- 15 -

CECO SCD and CECO QA that there is no apparent jeopardy to

the public's safety, due to the inaccurate statusing of

FCRs (605, 775 and 780); however, that this is a condition

of noncompliance (a deficiency).

This conditior is another

example of the deficiency described in Section I, Paragraph

2 of the details section of this report.

The ir apector discussed this matter with the CECO Construc-

s

tion QA Manager who stated that the administrative condition (s)

-

which has caused the inaccuracies in the tracking of FCRs

will he resolved within two months.

He stated that the

FCR log will be checked item by item to determine and

reflect the current status and as required will obtain the

appropriate documents and signatures which correspond to

the status.

lie further stated that, to keep the log current,

each site will be required to review the log monthly to

determine which additional documents and signatures are

needed to update the log for previous months activities

and document their requests for additional information.

Except as noted, no items of noncompliance were identified.

5.

Audits Conducted by CECO Corporate Office - Units 1 and 2

The inspector reviewed the CECO Corporate audit schedules for

a.

Byron related activities covering 1977, 1978 and 1979.

The

schedules were reviewed to determine if corporate audits are

being scheduled as required by CECO Topical Report CE-1-A

(section 18) and therefore ANSI N45.2.12.

b.

The inspector randomly selected CECO corporate audit reports

of:

Byron Site activities (audit reports dated September,

1979, May, 1979 and March, 1278) and S&L Design Activities

(audit reports dated March,1977 and November, 1977). The

inspector reviewed these audit reports and related correspon-

dence to observe; if audits are being documented, if CECO QA is

conducting follow-up inspection (as required) to determine that

satisfactory corrective action has been taken and if audit

personnel were qualified as required per CECO Topical Report

CE-1-A section 18 and therefore ANSI N45.2.12.

No items of noncompliance were identified.

1502 .517

- 16 -

.

Section III

Prepared by J. F. Suermann

Reviewed by D. W. Ilayes, Chief

Engineering Support Section I

s

1.

Design and Design Change Control

The IE inspector reviewed Commonwealth Edison Company (CECO) QA

a.

Procedure Q.P. No. 3-2 " Design Change Control," and Station

Nuclear Engineering Department (SNED) Procedures Q.8 " Field

Change Requests," dated February 16, 1979 (Revision 3), Q.9

" Design Change Notices," dated December 1, 1977 (basic issue)

and Q.14 " Distribution Lists for Design Documents," dated

January 17, 1977 (basic issue).

The procedures reviewed as

well as discussions with SNED personnel indicated that CECO

appears to have a system that basically complies with ANSI

N45.2Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. for controlling design changes.

Items covered by the

procedures included, but were not limited to, conditions

requiring design changes; distribution, review, approval,

release and revision requirements; and provisions for assuring

that design changes are compared with SAR commitments.

The IE

inspector also reviewed Sargent & Lundy (S&L) Procedure GQ 3.13

" Engineering Change Notice," dated September 20, 1978 (Revision

5) and discussed implementation of the procedure with S&L

personnel.

S&L personnel appeared knowledgeable in the pro-

cedural requirements and responded to the inspector's satis-

faction on questions regarding the application of the procedure.

S&L appeared to have adequate control over design changes and

their translation into possible SAR commitments.

b.

A random selection of documents was made to inspect compliance

on the part of S&L and CECO (SNED) with their respective proce-

dures.

Other than one or two isolated instances of a missed

block on a form, the following documents appeared to indicate

the respective engineering organizations were following their

procedures:

(1) S&L Engineering Change Notice No. 1266, cover letter dated

August 2, 1979.

(2) Field Change Request No. 605, cover letter dated December 20,

1978.

1502

.618

- 17 -

.

(3) Field Change Request No. 77a, cover letter dated Septemoer 20,

1979.

(4) Engineering Change Notice No. 1172, cover letter dated

May 21,

1979.

(5) ECN Index and Status Report, Page 69, dated September 15,

,

1979.

.

2.

QA/QC Personnel Qualification / Certification

The IE inspector reviewed Hunter Corporation Site Implementation

a.

Procedure (SIP) 1.702 "QA Personnel Qualification and Training,"

Revision 1 dated Parch 5, 1979 for compliance with ANSI N45.2.6-1973,

which the licensee has committed to in its QA program. Additionally,

the personnel records of 23 QA/QC personnel were reviewed for

compliance with SIP 1.702 and ANSI N45.2.6.

Discussions with

the QA Supervisor, QA Administrative Supervisor, and QA Training

Coordinator were held to resolve questions on the procedures

and records.

Specific comments relating to the adequacy of the

site implementing procedure and the records relating to it are

as follows.

(1) The use of a proficiency test as a basis for certification

is fairly common throughout the records but the SIP does

not give definitive guidance as to whom the test is adminis-

tered (with the conclusion being inferred that it is at

the discretion of the QA Supervisor), whether the test is

a practical, oral or written test, or what passing grades

are required (i.e. quantitative criteria) for qualification.

(2) ANSI N45.2.6 requires that prior experience be in QA

inspection or testing or both.

The llunter SIP is 5ritten

such that prior experience in construction, instal;ation

or other equivalent fields is used as a basis for certifi-

cation in lieu of QA related experience. This is true of

both Level 4 and Level 5 requirements in the Hunter SIP.

(3) ANSI N45.2.6 requires that prior experience, education and

training all be considered as relevant factors in the

awarding of certifications.

In at least fourteen of the

23 records reviewed, the personnel had the minimal educational

requirements, but there was a lack of prior QA experience,

and a predominant number of certifications were based upon

site-conducted training and demonstrated proficiency (i.e.

no formal proficiency test was required).

1502

319

- 18 -

.

(4)

In at least three cases, the prior experience of the

-

personnel certified was not related to the position for

which he was certified as required by ANSI N45.2.6 but it

did meet the more liberally written SIP.

(5)

In one case of a Level 3 Lead Auditor, the qualification

certificate does not indicate the period of certification

as required by both the SIP and ANSI N45.2.6, nor does it

,

indicate the basis used for certification.

.

(6) Paragraph 5 of ANSI N45.2.6-1973 requires that certain

records be kept in the personnel folders. The Hunter SIP

lacks definitive guidance as to what records are required

ir. the qualification folders to substantiate the basis of

certification.

The specific cases of a lack of prior related experience are

considered to be the result of the liberally worded, and sub-

sequently inadequate, SIP.

The liberal interpretation of SIP

1.702, specifically in ita rewording of experience factors and

its arbitrary use of proficiency testing to offset specific

prior QA requirements, does not meet the intent of ANSI N45.2.6.

b.

The IE inspector reviewed Blount Brothers Corporatior,QA/QC

Work Procedure Number 33, " Personnel Qualification and Certifi-

cation Procedure," Issue 2, Revision 1, dated February 9, 1979.

In addition, the inspector discussed the implementation of the

procedure with the QA/QC Supervisor and reviewed the personnel

qualification folders of nine Blount QA/QC personnel.

Based

upon the above, specific comments relating to the adequacy of

the site implementing procedure and the records relating to it

are as follows.

(1) The QA/QC Supervisor informed the IE inspectr

that follow-

on training is conducted on an "as needed" basis. The

only training formally required by the procedure is the

initial training or indoctrination given at the time an

employee is hired and there are no procedural requirements

that formally require continued training to maintain

proficiency in technical areas or to keep personnel abreast

of changes in QA policy or procedures.

(2) Background education and prior experience are minimal in

meeting the requirements of ANSI N45.2.6-1973.

In one

case, the personnel record clearly showed an individual

lacked the minimum education and was apparently accepted

for a position based on extensive field experience without

documenting the exception taken to the procedural require-

ments. This was an isolated instance and not considered

i502

(20

- 19 -

.

to be injuricus to the puv '.c health and safety, but the

IE inspector did questian ;ne thoroughness with which

people were examined to establish their certification.

(3) The QA/QC Supervisor stated that on occasion a proficiency

test ma',' be used as the basis for certification, and

several records substantiated this. There are no procedural

requirements addressing this practice, either quantitatively

s

or qualitatively.

.

(4) Contrary to ANSI N45.2.6, which requires specific QA

related experience at certain levels and a balanced con-

sideration of prior related experience, education and

training, several people were awarded certification based

on the results of site conducted training and served minimal

apprenticeship periods as trainees before being awarded

Level 1 capabilities. One individual who had eight weeks

of site training and marginal prior experience before

being certified as a receipt inspector was interviewed by

the IE inspector.

Based on the interview the inspector

questioned the individual's knowledge of what should have

been basic requirements associated with his position.

The

individual was quite nervous and seemed to respond more

positively to the questions re phrased by the QA Supervisor

which indicated the individual may have been more knowledgeable

and simply did not respond well to this particular interview.

(5)

Blount Procedure 33 is vague on the quantitative criteria

used to measure acceptable physical requirements, whereas

ANSI N45.2.6 requires that specific criteria be met with

regard to visual acuity.

The practice of ascribing little weight to prior related

experience when certifying individuals, the lack of the

procedure to address quantitative criteria, failure to

reflect the use of proficiency testing and controlling its

use in the procedure, and failure to address continued

post-indoctrination training as a matter of record are

considered inadequate implementation of ANSI N45.2.6.

c.

The IE inspector reviewed Hatfield Electric Company Procedure

  1. 17A " Qualification and Certification of Inspection Personnel,"

Revision 0, Issue 2, dated September 14, 1978 and related

personnel records of six Hatfield personnel. Additionally, the

IE Inspector sought clarification from the Hatfield QA Supervisor

on several questions raised during the inspection. Documentary

review and discussion with QA personnel resulted in the conclusion

that the procedures are inadequate for the following reasons.

1502 .i21

- 20 -

.

(1) The QA supervisor informed the inspector that Hatfield

personnel are qualified to Procedure 17A and not to ANSI

N45.2.6Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2.6" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., yet the QA supervisor's Certificate of Qualifi-

cation states his own Level 3 capability was awarded per

ANSI N45.2.6.

Since Procedure 17A does not invoke ANSI

N45.2.6Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2.6" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. (either in whole or partially with exceptions so

stated) this is a conflict and the procedural basis of

certification is unclear.

,

.

(2) Procedure 17A does not specify what the period of certifi-

cation is for qualified persennel nor does it specify what

re-evaluations are required or when they are required.

(3) Procedure 17A does not specify what the basis of certifi-

cation is for awarding personnel certification.

It is not

clear if proficiency testing is a criterion used in evalu-

ating initial hire personnel or if test scores are solely

those of required training once the person embarks on the

Hatfield training cycle.

(4) Procedure 17A does not specify any quantitative criteria

for eye examination (i.e. what visual acuity criteria are

the acceptable minima for an inspector) nor does it specify

the frequency of examination and the disposition of exami-

nation results.

(5) Procedure 17A does not specify what records are required

as part of the person's qualification file.

(6) Paragraph 5.5 of Procedure 17A is so liberally written

that virtually any prior experience in general construction

may be considered adequate in meeting the experience

factors used as guidelines in ANSI N45.2.6.

The require-

ments of paragraph 5.5 do not comply with the minimum

requirements of ANSI N45.2.6-1973 from either a qualitative

or quantitative viewpoint.

d.

Paragraph 2c. above dealt with the procedural adequacy of

Hatfield Procedure 17A in complying with the intent and imple-

mentation of ANSI N45.2.6.

A review of the six Hatfield per-

sonnel files revealed the following discrepancies in following

the procedure, notwithstanding the procedure's inadequacy.

(1) Paragraph 5.5.5 of Procedure 17A requires that detailed

explanations be documented on the qualification certifi-

cate when equivalent experience is used to qualify an

individual.

In at least four of the six files, the

explanation was not documented to justify how the prior

experience related to the level assigned.

1502 ?22

- 21 -

.

(2) The experience and educational background stated on the QA

Supervisor's certificate of qualification did not comply

with the requirements of ANSI N45.2.6 at the time of

certification (May 31, 1977) and the level of capability

assigned was per ANSI N45.2.6.

(3) 6ne QC inspector was hired on August 13, 1979 and as of

the date of this inspection the certificate of qualifi-

,

cation reflected only the man's name, job title, and date

-

of hire. The inspector was informed verbally that the

individual was in a trainee status but the certificate did

not reflect this. The certificate did not indicate the

man's level of capability, nor was it signed, nor did it

list any criteria used for qualification. There were no

other documents in the file and a copy of the man's

employment application was finally obtained from the

Hatfield project manager; the experience shown on the

application was neither construction nor QC related.

(4) A second QC inspector's certificate of qualification was

signed and dated October 16, 1978 by the QA Supervisor,

but the qualification test awarding him a trainee level

was dated October 23, 1978.

This is contrary to Paragraph

5.5.5 of Procedure 17A. The experience shown on the

certificate was neither in inspection nor construction as

required by Paragraph 5.5.1 of Procedure 17A.

(5) A third QC Inspector hired on February 26, 1979 was certi-

fied to a Level I position but the certificate of qualifi-

cation was neither signed nor dated as of this inspection.

Moreover, the experience shown on the certificate did not

appear to meet the requirements of Paragraph 5.5.2 of

Procedure 17A. The/ individual had no prior QA/QC or

nuclear plant experience prior to joining Hatfield in

February 1979.

The examples of inadequate implementing procedures (paragraphs

e.

2.a.-c.) and failure to follow procedures (paragraph 2.d.) do

not meet the intent of ANSI N45.2.6, and as such constitute

noncompliance with 10 CFR 50, Appendix B, Criterion V.

These

two additional examples of failure to comply with Criterion V

are included inder the noncompliance discussed in Section I,

Paragraph 1.b.

.

Unresolved Items

Unresolved items are matters about which more information is required in

order to determine whether they are acceptable items, items of noncompli-

ance, or deviations.

An unresolved item disclosed during the inspection

is identified in Section II, Paragraph 4.a.

1502

e23

- 22 -

.

Exit Interview

An interim exit meeting was held at the Byron Site at the completion of

the On-Site portion of the inspection on September 20, 1979, The final

exit meeting was held at the Region III offices on September 28, 1979.

Attendees at both meetings are denoted in the Persons Contacted paragraph.

The inspectors sumuarized the scope and findings of the inspection. The

licensee acknowledged the findings.

,

.

1502

324

- 23 -