Forwards IE Insp Rept 50-333/79-07 on 790529-0601 & Notice of Violation
ML19210E479
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/24/1979
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Leonard J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML19210E464 List:
References
NUDOCS 7912050088
Download: ML19210E479 (2)


See also: IR 05000333/1979007

Text

.

.

,

, , ,

UNITED STATES

{o

NUCLEAR REGULATORY COMMisslON

[

o

REGION I

$

$

631 PARK AVENUE

KING OF PRUSSI A. PENNSYLVANIA 19406

y*.

/

AUG g 4197$

Docket No. 50-333

Power Authority of the State of New York

James A. FitzPatrick Nuclear Power Plant

ATTN: Mr. J. D. Leonard

Resident Manager

P. O. Box 41

Lycoming, New York 13093

Gentlemen:

Subject:

Inspection 50-333/79-07

.

This refers to the inspection conducted by Mr. R. Zimerman of this office on

May 29 - June 1, 1979 and to the discussions of our findings held by Mr. Zimmerman

with yourself and other members of your staff at the conclusion of the inspection,

and to a subsequent telephone discussion between Mr. Zimmerman and Mr. J. Flaherty

on June 4, 1979.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Our inspector also verified the steps you have taken to correct the item of

noncompliance brought to your attention in a letter dated May 4, 1979. We have

no further questions regarding your action at this time.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full compliance with NRC requirements, as set forth in the

Notice of Violation, enclosed herewith as Appendix A.

This item of noncom-

pliance has been categorized into the levels as described in our correspondence

to you dated 'hcember 31, 1974. This notice is sent to you pursuant to the

provisions of Section 2.201 of the NRC's " Rules of Practice", Part 2, Title 10,

Code of Federal Regulations. Section 2.201 requires you to submit to this

office, within twenty (20) days of your receipt of this notice, a written

statement or explanation in reply including:

(1) corrective steps which have

been taken by you and the results achieved; (2) corrective steps which will be

taken to avoid further items of noncompliance; and (3) the date when full com-

pliance will be achieved.

1591

246

(}

7 91 g g 59

.

.

Power Authority of the

AUG 2 419N

State of New York

2

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room.

If this report contains any

information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure.

Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b)(4) of Section 2.790.

The information sought to be withheld shall be inccrporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in this

regard within the specified period . the report will be placed in the Public

Document Room.

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

_

a

n . Brunner, Chief

R ctor Operations and Nuclear

upport Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection

Report Number 50-333/79-07

cc w/encls:

George T. Berry, Executive Director

P. W. Lyon, Manager - Nuclear Operations

A. Klausmann, Director, Quality Assurance

M. C. Cosgrove, Quality Assurance Supervisor

J. F. Davis, Chairman, Safety Review Committee

V. J. Cassan, Assistant General Counsel

G. M. Wilverding, Licensing Supervisor

1561