Requests Immediate Approval for Installation of Increased Capacity Fuel Racks.Prompt Installation Will Provide Capability of Full Core Unload
ML19210E397
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 11/29/1979
From: Berry G
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
JPN-79-74, NUDOCS 7912040500
Download: ML19210E397 (3)


Text

,

POWER AUTHORITY OF THE STATE OF NEW YORK 10 CoLUMaus CIRCLE NEW YORK. N. Y.10019 (2125 397 6200 TRUSTEES GEORGET. BERRY JOHN S.OYSON opsR ATING OFFICER JOHN W. SOSTON v CE CNAIRMAN y Em PE R A TION S RICHARD M. ,LYNN JOSEPH R. SC IEDER ROBERT 3. MILLONZI [g'g g"g g' *

,REoERicx R. CLaR A November 29, 1979 '*"

!;"co','"cA^%,.....,

JPN-79-74 **0'='=""^~*^'

TELE ) DIED T0: Tsou,4,SgFRE,Y

& GENERAL COWNSEL Mr. Darrell G. Eisenhut, Acting Director Division of Operating Reactors U.S. Nuclear Regulatory Commission Office of liuclear Reactor Regulation Washington, D.C. 20555

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Urgent Request for Spent Fuel Rack Installation Approval

Dear Mr. Eisenhut:

This is in reference to a telephone conversation on November 5, 1979 between your Mr. T. Ippolito and our Messrs. P. Early and J. Helland regarding the Authority's submittal to the Nuclear Regulatory Comission requesting approval to install increaseo capacity fuel racks in the FitzPatrick spent fuel pool.

In this telephone conversation, Mr. Ippolito indicatea that Nuclear Regulatory Commission approval to install the increased capacity fuel racks would not be forthcoming since the work in the NRC to complete certain reports regarding the racks had been assigned low priority. Mr. Ippolito further stated that it is not necessary that these racks be installed in tne FitzPatrick spent fuel pool before the next refueling outage since it is not necessary to remove the entire core from the vessel for work on the Tcrus or LPRM's. We received this message from Mr. Ippolito after having received repeated assurances from your Mr. P. Polk during the past six months that NRC approval was imminent.

The purpose of this letter is to confinn our need for your imediate approval of this request and to request your assistance in securing this approval. The basis

  • for this need is both safety related and economic, and these are discussed separately below.

I. Safety Considerations

1. Prompt installation of the racks as scheduled will provide, .

as early as possible, the capability of a full core unload at the JAFNPP. This capability does not exist at the ,

present time.

7912040 4 1475 092 500 o

Mr. Darrell G. Eisenhut JPN-79-74 NRC Page 2

2. Extensive work has been planned for the outage to conduct inservice inspection of various stainless steel piping con-figurations (Core Spray piping, CRD hydraulic return nozzle and piping, Core Spray safe ends, recire. safe ends, recire.

piping (risers), recire. by-pass lines) which on other plants have experienced stress corrosion and thermal cycle cracking.

In particular, the recirculation pira safe ends cannot be repaired or replaced without removing the entire core from the reactor vessel. This is to ensure safe coolant coverage of the fuel during the performance of this work.

If this inspection should indicate that repairs or replace-ments are necessary to the reactor coolant pressure boundary, the core may have to be off loaded. In addition, the radio-logical doses associated with the work will be reduced by having the core removed from the reactor vessel,thus complying with ALARA requirements.

II. Economic Considerations The inability to off lead the entire core during the forthcoming refueling outage can cost the Authority and the people of New York State considerable expense resulting from increased outage time.

In addition to the piping work described under Item 2 of " Safety Considerations",

a considerable amount of work is planned for the Torus during the coming outage as a result of the Mark I Containment Program, which will require that the Torus be drain-ed. Since the FitzPatrick Technical Specifications do not permit work, which has the potential for draining the vessel, when no emergency core cooling systems are available, the piping work could not be done while the Torus is drained and the fuel is in the vessel. This means that, with the core in the vessel, any required piping work would have to be done in series with the Torus work thereby extending the duration of the outage by an amount dependent upon the piping work required to be done. This outage extension could range from several days to several weeks, resulting in loss to the Authority in the millions of dollars.

The Nuclear Regulatory Commission has had the Authority's submittal requesting approval to install the increased capacity fuel racks since November,1978. We believe that this should be adequate for the Nuclear Regulatory Commission to respond, especially since the FitzPatrick racks are of a design :hich has been accepted by the Commission -

for several other utilities.

We believe that the work scheduled for this outage should not be deferred for another refueling outage, nor should the people of the State of New York be penalized with the loss of economical electrical generation for a prolonged period because the Commission will not act on the Authority's request.

1475 094

h g .4 Mr. Darrell G. Eisenhut JPN-79-74 NRC Page 3 In view of the impact of denying this submittal on plant availability and on plant safety, we reiterate that we request your prompt approval.

Very truly yours, t

j : g/r . ' A ,(

George T.' Berry' President and Chief Operatir,g Officer 1475 094

.