Forwards IE Insp Repts 50-498/79-15 & 50-499/79-15 During Sept & Notice of Violation
ML19210E155
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 10/19/1979
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Eric Turner
HOUSTON LIGHTING & POWER CO.
Shared Package
ML19210E156 List:
References
NUDOCS 7911300611
Download: ML19210E155 (2)


See also: IR 05000498/1979015

Text

-7Zc

.

.

UNITED STATES

[p progDo

NUCLEAR REGULATORY COMMISSION

" ,#

$3Y)

REGloN IV

% g\\g$

ij

ARLINGTON, TEXAS 76012

l

o

611 RY AN PLAZA DRIVE, SUITE 1000

o,

A

~

October 19, 1979

,,,

In Reply Refer to:

RIV

Docket No. 50-498/Rpt. 79-15

50-499/Rpt. 79-15

Houston Lighting and Power Company

Attn:

Mr. E. A. Turner, Vice President

Power Plant Construction and

Technical Services

Post Office Box 1700

Houston, Texas

77001

Gentlemen:

This refers to the inspection conducted by our Resident Inspector,

Mr. H. S. Phillips, during the period of September 1979 of activities

authorized by NRC Construction Permits No. CPPR-128 and 129 for the

South Texas Project, Units No. I and 2, and to the discussion of our

findings with Mr. L. D. Wilson and other members of your staff during

the inspection period.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection con-

sisted of selective examination of procedures and representative recorus,

interviews with personnel, and observations by the inspector.

During the inspection, it was found that certain activities under your

license appear to be in noncompliance with Appendix B to 10 CFR 50 of the

NRC Regulations, " Quality Assurance Criteria for Nuclear Power Plants."

fhe item of noncompliance and references to the pertinent requirements are

identified in the enclosed Notice of Violation.

Two new unresolved items are identified in paragraph 3 of the enclosed

report.

This notice is sent to you pursuant to the provisions of Section 2.201

of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.201 rcquires you to submit to this office, within

30 days of your receipt of this notice, a written statement or explanation

in reply including:

(1) corrective steps which have been taken by you,

and the results achieved; (2) corrective steps which will be taken to

avoid further noncompliance; and (3) the date when full compliance will

be achieved.

1437

550

79113006'//

-

.

Houston Lighting and Power Company

2

October 19, 1979

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If the report contains any information that you believe to be

proprietary, it is necessary that you submit a written application to

this office, within 20 days of the date of this letter, requesting that

such information be withheld from public disclosure. The application must

include a full statement of the reasons why it is claimed that the infor-

mation is proprietary. The application should be prepared so that any

proprietary information identifiti is contained in an enclosure to the

application, since the application without the enclosure will also be

placed in the Public Document Room. If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document Room.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Sincerely,

e

W. C. Seidle, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

IE Inspection Report No. 50-498/79-15