ML19210E016

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-282/79-21 & 50-306/79-18 on 790709-13, 17-18,0801-03 & 09.Noncompliance Noted:Failure to Follow Design Change Procedures
ML19210E016
Person / Time
Site: Prairie Island  
Issue date: 10/04/1979
From: Daniels F, Jackiw I, Little W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML19210E001 List:
References
50-282-79-21, 50-306-79-18, NUDOCS 7911290164
Download: ML19210E016 (25)


See also: IR 05000282/1979021

Text

.

-

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

PIGION III

Report No. 50-282/79-21; 50-306/79-18

Docket No. 50-282; 50-306

License No. DPR-42; DPR-60

Leiensee: Northern States Power Company

414 Nicollet Mall

Minneapolis, MN 55401

Facility Name:

Prairie Island, Units 1 and 2

Inspection At: Red Wing, MN-

Inspection Conducted: July 9-13, 17-18, August 1-3 and 9, 1979

Inspectors:

W. S. Little

j"Is' 'f?w <?v

'. J ekiw

/6-8-77

.

.j

's

[

/

. Dan e s

/o-3-79

M. D. Riden

@[3f77

, ,, y

g

7

,

Approved By:

W. S. Litt'le, Chief

/8/[/@

Nuclear Support Section 2

//

'

Inspection Summary

Inspection on July 9-13, 17-18, August 1-3 and 9, 1979 (Report No.

50-282/79-21;50-306/78-1R

Areas Inspected:

Announced special inspection of the licensee's implementa-

tion of the Quality Assurance Program in the following areas: QA/QC

sdministration; qualification of personnel; design changes and modifications;

records control; receipt storage and handling; tests and experiments;

procurement control; document control; offsite and onsite review committees;

audits; test and measurement equie; ment; surveillance and calibration;

maintenance; housekeeping and cleanliness; and offsite support staff.

The inspection involved 171 inspector hours on site by four NRC inspectors.

Results: Of the sixteen areas inspected, no apparent items of noncomp-

linace or deviations were identified in thirteen areas, two apparent items

of noncompliance were identified in two areas (infraction - failure to

follow design change proceduresji- Paragraph 7; infraction - failure to

adhere to record control requirdments Paragraph 15) one apparent deviation

was identified in one area.

'

1434

308

7911290

lW

.

DETAILS

-

1.

Persons Contacted

G. H. Neils, General Superintendent, Nuclear Power Plant Operation

F. P. Tierney, Plant Manager

L. O. Mayer, Manager, Nuclear Support Services

E. L. Watzl, Plant Superintendent, Plant Engineering and Radiation

Protection

A. A. Hunstad, Staff Engineer

R. E. Warren, Office Supervisor

R. L. Lindsey, Superintendent Operations

D. A. Schuelke, Superintendent Radiation Protection

J. L. Hoffman, Superintendent Technical Engineering

K. J. Albrecht, Quality Assurance Engineer

R. V. Pederson, Quality Assurance Engineer

P. F. Suleski, Supervisory Engineer QA Nuclear

D. J. Silvers, Quality Assurance Engineer

T. E. McFadden, General Superintendent, Operational Quality Assurance

P. H. Kamman, Superintendent, Nuclear Quality Assurance

The inspectors also interviewed several other licensee employees

including shift supervisors and plant engineering and administrative

personnel.

On August 9, 1979, a management meeting was held in the Northern

States Power Company (NSP) corporate offices in Minneapolis, Minnesota.

The purpose of the meeting was to discuss the findings identified

during the Quality Assurance inspection conducted on July 9-13,

17-18 and August 1-3, 1979. Attendees included the following

reprensentatives.

NRC Region III

R. F. Heishman, Chief, Reactor Operations and Nuclear Support Branch

W. S. Little, Chief, Nuclear Support Section 1

R. F. Warnick, Chief, Reactor Projects Section 2

I. N. Jackiw, Reactor Inspector

C. D. Feierabend, Reactor Inspector

F. T. Daniels, Reactor Inspector

NSP

L. J. Wachter, Vice President, Power Production and System Operation

D. E. Gilberts, General Manager, Power Production

G. H. Neils, General Superintendent, Nuclear Power Plant Operation

T. E. McFadden, General Superintendent, Operational Quality Assurance

L. O. Mayer, Manager, Nuclear Support Services

P. H. Kamman, Superintendent, Nuclear Quality Assurance

1454

509

_2_

.

F. P. Tierney, Plant Manager, Prairie Island

.

G. T. Bart, Quality Assurance Engineer

E. L. Watzl, Plant Superintendent, Plant Engineering and Radiation

Protection, Prairie Island

K. J. Albrecht, Quality Assurance Engineer, Prairie Island

P. D. Charais, Quality Assurance Engineer, Prairie Island

R. L. Scheinost, Quality Assurance Engineer, Montir.ello

T. E. Harlan, Operations QA Specialist I

2.

QA/QC Administration

The QA/QC implementing procedures were reviewed to evaluate the

licensee's administrative program for assuring tuat the QA program

scope is defined, for controlling the preparation, review and approval

of QA/QC procedures; and for establishing responsibilities and

methods for reviewing and evaluating the QA/QC program. The Adminis-

trative Control Directives (ACD's) and Administrative Work Instructions

(AWI's) were reviewed against the commitments made in " Operational

Quality Assurance Plan", (0QAP) Rev. 3 which had been accepted by

NRC.

a.

Documentation Reviewed

1ACD1.1, Rev. 6, Administrative Control Directives

1ACD1.2, Rev. 5, Administrative Work Instructions

1ACD2.1, Rev. 1, Operational QA Program Boundary

1ACD2.4, Rev. 1, QA Program Administration

1ACD4.1, Rev. 5, Document Control

3ACD1.1, Rev. 7, Administrative Control Directions

3ACD1.2, Rev. 6, Administrative Work Instructicns

3ACDI.3, Rev. 6, Administrative Memorandums

3ACDI.4, Rev. 5, Plant Administrative Control

3ACD2.1, Rev. 2, Operational QA Program Boundary

3ACD2.4, Rev. 3, QA Program Administration

3ACD5.1, Rev. O, Document Control

SACD1.1, Rev. 3, Administrative Control Directives

SACD1.2, Rev. 2, Special Orders

SACD1.3, Rev. 3, Section Work Instructions

5ACD1.4, Rev. 4, Plant Operations Manual

SACD2.1, Rev. O, QA Program Boundary

5ACD2.2,

v. 5, Internel Audits

5ACD2.4,

av. O, Q-List Committee

5ACD3.1.

.ev. 4, Prairie Island Plant Organization

SACD2.2

lev. 5, Internal Audits

The above documents and their implementation as they relate to

the administration of the QA program were reviewed.

1434

310

-3-

.

b.

Findings

(1) Noncompliance

No items of noncompliance were identified

(2) Deviations

No deviations were identisied.

(3) Unresolved Items

Plant Q-List-1ACD2.1 lists those structures, systems and

components subject to Appendix B to 10 CFR 50, however a

Q-list extension that has been through all of the required

reviews and approvals has not been issued as required by

SACD2.1. The inspector stated that the official Q-list

extension would be reviewed during a subsequent QA inspection.

c.

Discussion

The OQAP approved by NRR states that the Plant Quality Engineer

reports to the Plant Superintendent, Engineering and Radiation

Protection. The inspector expressed concern that this organiza-

tional structure did not provide sufficient " independence from

cost and scheduling considerations when opposed to safety

considerations" as stated in paragraph 3.2 of ANSI N18.7.

No

problems were apparent in this area and the licensee indicated

that they were considering revising the OQAP such that the

Plant Quality Engineer would report to the Plant Manager.

The inspector expressed concern that the QA/QC responsibilities

were divided between so many plant and corporate organizations,

making it difficult to assure that all the proper systems and

activities are subject to the QA programs. Extra effort must

be put both on communi:ations and the interfaces between these

organizations to make certain all areas important to safety are

addressed. The inspector stressed the importance of the licensee

management communicating their interest and support of QA/QC to

the plant Quality Engineer.

It was brought to the inspectors attention that the licensee

was considering using peer QC inspectors in the plant. The

pros and cons of using peer inspectors were discussed. The

inspector stated that to make the " peer" approach work, serious

consideration must be given to making sure their QC training

was adequate; and to assigning the " peer" inspectors to the QC

engineer to supervise their activities for specific periods of

time. At the exit interview on August 9, 1979, the licensee

indicated that they were no longer considering the use of peer

inspectors.

1434

411

-4-

.

3.

Audit Program

The licensee's audit program was inspected to evaluate the licensee's

audit program and its compliance with the OQAP and Section 6 of the

Technical Specifications.

a.

Documentation Reviewed

1 ACD 2.2, Rev. 2, Audits

3 ACD 2.2, Rev. 3, Audits

5 ACD 2.2, Rev. 5, Internal Audits

2 ACD 7.1, Rev. 2, Safety Audit Committee

3 AWI 2.2, Rev.2, Audit Schedule and Log

3 AWI 2.26, Rev. 1, Lead Auditor Qualifications

Records to confirm implementation of the above ACD's and AWI's

were inspected at Prairie Island and in the corporate office in

Minneapolis.

b.

Findings

(1) Noncompliance

No items of noncompliance were identified.

(2) Deviations

No deviations were identified.

(3) Unresolved Items

Section 20.2 of the 0QAP commits to establishing measures

to assure periodic audits of each Directive issued within

the Operational Quality Assurance Program, and Section

20.3 of the OQAP states that required audits shall be

performed each year except that the time period may be

extended to not more than two years provided such exten-

sions are justified based on past experience.

(These

commitments are implemented in Directives 3 ACD 2.2 and 5

ACD 2.2) At the time of the inspection audits of the

following directives had not been conducted yearly, and

the audit period extension was not justified based on past

experience; 3 ACD 2.2, 5 ACD 2.2, 5 ACD 2.3, 5 ACD 2.5, 5

ACD 7.1, and 5 ACD 8.4.

c.

Discussion

The division of responsibilities for the audit program appears

to be a potential source of problems. The audit of the

Surveillance Program Directive, 3 ACD 9.1, appears to not have

j .4 3 k

b k 2.

-5-

.

been done because of a misunderstanding between the corporate

and plant QA staffs, however, the inspector did note that the

SAC had audited the plant surveillance progarm in the Spring of

1978 and 1979.

The inspector emphasized the importance of

communi.ation and interface control between the different

internal organizations performing audits to make certain that

all required audits are performed.

Currently the OQAP only required auditing of Directives within

the Operational Quality Assurance Program and does not require

the auditing of safety related activities as they are being

carried out. The inspector emphasized that to properly audit a

program (maintenance, surveillance, etc.), the audit should

include some actual observations of safety related activities

while they are in progress. The licensee stated that they were

considering revising the OQAP to include audit of activities.

The inspector expressed concern that extensive periods of time

were being taken to resolve audit findings.

As an example,

Audit AIII resulted in findings QAF-14 through 17.

Resolution

of these findings took as long as a year to accomplish relatively

simple corrective actions.

4.

Offsite Rceiew Committee

The inspector reviewed records and conducted interviews to evaluate

the performance of the Safety Audit Committee. The Administrative

Work Inst rucctions and records were compared with the requirements

of Section 6 of the Technical Specifications.

a.

Documents Reviewed

2 AWI 7.1.3, Rev. 2, Safety Audit Committee Charter

SAC Meeting Minutes dated 5/18/77, 8/24/77, 12/7/77, 3/8/78,

6/21/78, 9/20/78, 2/6/79

SAC Audit Schedule and Records for 1978 and 1979

b.

Findings

(1) Noncompliance

No items of noncompliances were identified.

(2) Deviations

No deviations were identified.

(3) Unresolved items

No unresolved items were identified.

-6-

5.

Personnel Qualification Program

The inspector reviewed the QA prcgram relating to qualification of

personnel for key positions at the plant.

It was found that the

corporate and plant Directives adequately identify the minimum

educational experience and qualification requirements for:

principal

operating staff, first level supervision, oncite technical engineering

staff, plant craftsmen, plant operators, NDT personnel, chemistry

technicians, QA staff and SAC members.

a.

Documents Reviewed

5 ACD 3.1, Rev. 4, Prairie Island Plant Organization

5 ACD 3.11, Rev. 2, Plant Training Program

3 ACD 3.3, Rev. 1, Nuclear Plant Maintenance

3 ACD 7.2, Rev. 1, Power Div. Welder Qualification

3 ACD 7.6, Rev. O, NDE Personnel Qualification

3 ACD 7.5, Rev. 1, Welding Inspection

b.

Findings

(1) Noncompliance

No items of noncompliance were identified.

(2) Deviations

No deviations were identified.

(3) Unresolved Items

No unresolved items were identified.

c.

Discussion

Even though the guides and standards do not require it, the

inspector stated that the minimum qualificatione for the Training

Supervisor should be specified in a plant directive.

6.

Offsite Support Staff

The inspector reviewed licensee Directives and interviewed corporate

personnel to determine whether safety related offsite support staff

functions are performed by qualified personnel in conformance with

licensee approved administrative procedures. The inspector emphasized

the importance of subjecting all such safety related support functions

to QA procedur-s.

9

L'

1454

414

-7-

a.

Documents Reviewed

1 ACD 3.3, Rev. 3, Design Change Control

1 ACD 5.1, Procurement Control

1 ACD 5.4, Rev. 1, Material Receipt Control

2 ACD 3.3, Program Control

b.

Findings

(1) Noncompliance

No items of noncompliance were identified.

(2) Deviations

No deviations were identified

(3) Unresolved Items

No unresolved items were identified.

7.

Design Changes and Modification Program

The inspector reviewed the Design Changes and Modification Program

to ascertain whether the licensee is implementing a Quality Assurance

Program that is in conformance with the Prairie Island Operational

Quality Assurance Plan, ANSI N18.7-1976 and 10 CFR 50 Appendix B.

The following items were considered during this review: determination

that procedures have been established for control of design and

modification change request; determination that procedures and

responsibilities for design control have been established; verification

that administrative controls for design document control have been

established; verification that responsibilities have been assigned

in writing to assure implementation of design change document control:

verification that administration control and responsibilities have

been established to assure that design changes and modification ~

will be incorporated into plant procedures, operator training programs

and updating plant drawings; verification that controls have been

developed that define channels of communication between design

organizations and the responsible individuals; verification that

administrative controls require that design documentation and records

which provide evidence that the design and review process was performed

be collected and transmitted to records storage; verification that

controls require that implementation of approved design changes be

in accordance with approved procedures; verification that controls

require that post modification acceptance testing be performed per

approved test procedures and the results evaluated; verification

!434

l5

-8-

that responsibility has been assigned for identifying post modifica-

tion testing requirements and acceptance criteria; and responsibility

and method for reporting design changes / modifications to the NRC in

accordance with 10 CFR 50.59.

The inspector also reviewed the licensee's temporary modifications,

such as electrical jnmpers and lifted electrical leads, to ascert.ain

that a program exists and requires proper reviews and approvals of

temporary modifications and that these activities are accomplished

using detailed approved procedures.

a.

Documentation Reviewed

The following documents were reviewed:

5 ACD 6.1 " Design Change Control"

5ACD 6.2 " Design Change Installation Procedures"

5 ACD 6.3 " Design Change Implementation"

5 ACD 6.4 " Design Change Preoperational/ Operational Testing"

3 AWI 4.1.1 " Safety Evaluation"

3 AWI 4.1.2 " Responsibilities of Project Coordinators"

3 AWI 4.1.3 " Fire Protection Prevention Review of Design Changes"

3 AWI 4.1.4 " Design Change Records"

3 AWI 5.3.1 " Drawing Control Responsibilities"

3 ACD 5.3 " Drawing Revision"

SWI-PERP-2 "Section Work Request Authorizing Instruction"

SWI-PERP-4 " Safety Evaluation"

SWI-PERP-5 " Responsibilities of Project Coordinator"

b.

Findings

(1) Noncompliance

10 CFR 50 Appendix B, Criterion V requires that activities

affecting quality shall be prescribed by documented instruc-

tions, procedures, or drawings, of a type appropriate to

the circumstances and shall be accomplished in accordance

with these instructions, procedures, or drawings.

Contrary to the above, the following examples of failures

to follow procedures were identified by the inspector and

constitute an item of noncompliance.

(a) 3ACD4.1 " Design Change Control" Revision 4, Sections

6.4.2 and 6.4.3 require that after the Preliminary

Design Change Package is completed an overall review

of that Package shall be performed. This review

shall ensure that all pieces of the Package are

properly prepared and that this shall be indicated by

a signature of the overall reviewer.

In addition,

}434

j}h

-9-

the Responsible Engineer's signature shall indicate

that all required forms in the Preliminary Design

Change Package are properly completed.

The inspector found that section's III B 1 and 2 of

Design Change Control Form (DCCF) 3-3016, for Design

Change 77L397 " Removal of Auto Start of Auxiliary

Feedwater Pump", were not completed but the form was

signed approving the Design Change.

(b) 3ACD4.1 section 6.3.8 requires that the Responsible

Engineer assure that all operating, maintenance,

surveillance or other procedures which may require

revisions or which should be generated as a :esult of

the Design Change are identified on fers 3-3017-7 and

indication be made when the procedures are revised or

generated by a date and initials. Also, form 3-3017-7

" Procedures" requires that a signature block be pro-

vided to indicate that each procedure has been prepared.

While reviewing documentation for Design Change

77L397, the inspector found that form 3-3017-7, had

been completed but no initials appeared on the form.

Further review by the inspector revealed that procedure

checklist C28-2 had been revised but not initialed as

required.

(c) 3AWI 5.3.4 requires that a Drawing Revision Request

be issued to change the drawings effected by a Design

Change.

The inspector found that for Design Change 77L397, a

design change notice had been issued to indicate that

eleven drawings are expected to be effected by the

proposed Design Change. Work on the Design Change

had been completed in September 1978. A review of

records indicates that a drawing revision request had

not been issued as required, and the eleven effected

drawings have not been revised.

The inspector also found that as a result of the

Design Change a "new drawing request" had been

initiated and on January 9, 1979, a check drawing had

been received at the plant.

Six months later the

check drawing has still not been reviewed nor issued.

(2) Deviations

No deviations were identified.

- 10 -

(3) Unresolved Items

The following unresolved item was identified in the area

of design caanges and modifications:

ANSI 18.7 and 3ACD 3.6 Revision 0 dated June 7, 1979

require that temporary modifications, such as electrical

jumpers and lifted electrical leads shall be controlled by

approved procedures which shall include a requirement for

independent verification has not been implemented by the

plant.

However, the inspector noted that 3ACD3.6 is being reviewed

by plant personnel and a 5ACD will be issued soon.

c.

Discussion

(1) No formal system has been established to provide and

document that Design Changes have been communicated to

plant operators.

Procedure 3AWI4.1.2 requires that the Design Project

Coordinator along with the Training Supervisor arrange and

organize the appropriate training. licweve r , if the Design

Change does not involve the Construction Department and a

Design Project Coordinator is not assigned, no formal

provisions exist to require that the Responsible Engineer

initiate the appropriate training.

(2) 3ACD4.1 Revision 5, Section 5.6(5) requires that the Plant

Superintendent Engineering and Radiation Protection approve

Design Changes prior to installation, with the exception

that installation may proceed providing that Design Change

approval is obtained prior to declaring the related system

operable.

The inspector noted that this is inconsistent with require-

ments provided in Sections 6.2 and 6.4.8 of the same

procedure. These sections require that Design Changes be

approved prior to installation.

(3) 3ACD4.1 Revision 5, Section 5.6(10) dated December 8,

1978, requires a time.'.y (3 month) close out of design

changes after installation.

The inspector's review of a number of design changes,

where installation was completed after the effective date

of the 3ACD, indicates that these design changes have been

closed out in the required 3 month period. However, the

khb

_

_

inspector noted that there are still a number of old

(prior to December 8, 1978) design changes that have not

been closed out.

8.

Maintenance Program

The inspector reviewed the licensee's Maintenance Program to ascertain

whether the QA Program relating to maintenance activities is being

conducted in accordance with the Operational Quality Assurance Plan,

10 CFR 50 Appendix B requirements and commitments in the QA Plan.

The following items were considered during this review; written

procedures have been established for initiating requests for routine

and emergency maintenance; criteria and responsibilities have been

designated for performing work inspection of maintenance activities;

provisions and responsibilities have been established for the identi-

fication of appropriate inspection hold points; methods and responsi-

bilities have been designated for performing testing following

maintenance work; methods and responsibilities for equipment control

have been clearly defined; and administrative controls for special

processes have been established.

.

The inspector also reviewed the licensee's Preventive Maintenance

Program and verified that a written program has been established

which includes responsibility for the program, a master schedule for

preventive maintenance and documentation and review of completion of

preventive maintenance activities.

a.

Documentation Reviewed

The following documents were reviewed:

3 ACD 3.3, " Nuclear Plant Maintenance"

3 ACD ?.6, " Equipment Control"

5 ACD 3.10, " Equipment Control"

'

SWI-0-5, " Operation Section Work Request and Work Request

Authorization"

SWI-M-1, " Maintenance Section Work Request and Work Request

Authorization"

SWI-M-7, " Control of the Electrical PM File"

SWI-E0-1, " Operations Section Work Request Authorization"

SWI-IC-1, "I&C Section WR/WRA"

3 ACD 7.1, " Welding Procedure Control"

3 ACD 7.3, " Welding Material Control"

3 ACD 7.4, " Nondestructive Examination Procedure"

5 ACD 9.4, " Welding Control"

5 ACD 8.3, " Welding Material Control"

3 ACD 7.5, " Welding Inspection"

3 ACD 3.5, " Training"

5 ACD 3.11, " Plant Training Program"

1434

319

.

- 12 -

.

b.

Findings

(1) None apliance

No apparent items of noncompliance were identified.

(2) Deviations

No deviations were identified.

(3) Unresolved Items

One unresolved item was identified:

The Northern States Power Company Operational Quality

Assurance Plan revision 3 dated June 20, 1978 states in

section 4.9 that training programs shall be established

for those personnel performing quality-affecting activities

such that they are knowledgeable in the quality assurance

directives and their requirements and proficient in imple-

menting these requirements.

Section 4.9 further states

that the scope, the objective, and the method of implementing

the training programs are documented.

Contrary to the commitment made in the Operational Quality

Assurance Plan the following discrepancies were identified

in the licensee's Quality Assurance Training Program:

(a) 5 ACD 3.11 does not clearly define the scope of the

QA training.

(b) No system exists for checking that individuals involved

in quality effecting activities have been trained on

all required QA material.

(c) No system exists to identify and train individuals

that had missed scheduled QA training sessions.

(d) A program for QA retraining of personnel has not been

established.

c.

Discussion

The following items were brought t

the attention of the licensee.

(1) No formal system to review corporate 3 ACD's and incorporate

th m into plant procedures in a timely manner.

For example, special processes procedure 3 ACD 7.1, 3 ACD

7.3, 3 ACD 7.4 and 3 ACD 7.5 all have effective dates of

MayorJuneofly79. The plant 5 ACD's that implement

'

434

320

- 13 -

these procedures have effective dates prior to May and

.

June 1979 and in one case the effective date of plant 5

ACD is February 1976.

The inspector noted that no documented evidence was available

to indicate that the corporate 3 ACD requirements had been

incorporated into the plant 5 ACD's.

(2)

In some cases Work Request Authorization forms are not

being completely filled out.

The inspector found that

some of the WRA's reviewed did not have the workman and

the workman's supervisor blocks filled in.

(3) Work requests ;re not always detailed enough to determine

cause of the malfunction or failure, or description of the

corrective action taken.

9.

Housekeeping / Cleanliness Program

The inspector reviewed the licensee's Housekeeping and Cleanliness

Program to verify that the licensee is implementing adequate housekeeping

and cleanliness controls to assure that the quality of safety related

systems is not degraded. Also, that the program meets the requirements

of the Operational QA Plan and ANSI N 45.2.3.

Items considered during the review were:

Control of housekeeping

during work activities; establishment of housekeeping zones; control

of combustible material and debris; establishment of cleanliness

classifications for plant systems; and establishment of requirements

for material accountability in critical clean areas. The inspector

observed that physical housekeeping and cleanliness of the plant

appears to be adequate and is meeting the requirements of the existing

plant procedures.

a.

Documents Reviewed

SWI-I&M-3, " Plant Helper Cleaning Assigments"

SWI-0&M-6, " Auxiliary Building Vacuum Cleaner Operation"

SWI-0&M-8, " Laundry Operations"

SWI-0&M-9, " Control of Combustible Material at Job Sites"

SWI-0-8, " Plant Cleaning Responsibilities"

b.

Finding

(1) Noncompliance

No apparent items of noncompliance were identified.

(2) Deviations

No deviations were identified.

1434

321

_ , , _

(3) Unresolved Items

-

The licensee has not addressed all the requirements provided

in ANSI N 45.2.3.

Fox example, zone designations and cleanliness requirements

for these zones have not been established as required in

ANSI N 45.2.3.

Current procedures are not specific in the

designation of zones. Also no formal procedures have been

established to inspect and evaluate housekeeping in the

plant as required by ANSI N 45.2.3.

10.

Test and Experiments Program

An inspection vas conducted to determine if the licensee had implemented

a QA Program relating to the control of test and experiments in

conformance with regulatory requirements, commitments and guides. A

formal method has been established to handle all requests or proposals

for conducting plant tests and experiments involving safety related

components, systems, structures or modes of operation different from

those described in the FSAR. A formal system, including assignment

of responsibility, has been established for reviewing and approving

test procedures and performing an evaluation pursuant to 10 CFR 50.59.

A review was conducted of the spent fuel pit expansion

pre-operational testing, safety injection system safeguards 'est and

a special natural circulation test.

a.

Documentation Reviewed

5 ACD 3.3, Operations Committee

3 ACD 3.9, Review & Approval of Plant, Schedules and Procedures

3 ACD 9.2, Surveillance Test Procedures

b.

Findings

(1) Noncompliance

No items of noncompliance were identified.

(2) Deviations

No items of deviation were identified.

(3) Unresolved Items

No unresolved items were identified.

1434

322

- 15 -

11.

Test and Measurement Equipment Program

The inspector verified by the review of established controls for

test and measurement equipment that criteria and responsibility for

an equipment inventory list has been prepared which identifies the

equipment, calibration frequency, procedures and applicable national

standards. Formal requirements exist for identifying the status of

calibration and assuring that equipment is calibrated on or before

the date required. Requirements have been established which prohibit

the use of test and measuring equipment which has not been inspected

and calibrated within the prescribed frequency with controls to

prevent inadvertent use of such equipment. A system has been estab-

lished for control and evaluation of new or out-of-calibration

equipment.

a.

Documentation Reviewed

5 ACD 1.5, Procedure Control

5 ACD 3.4, Records Management

5 ACD 3.14, Measuring and Test Equipment

5 ACD 7.1, Procurement

SWI-M-6, Torque Wrenches

SWI-I&C PM-6, Condensate Storage Tank Level Calibration

SWI-I&C PM-8, Boric Acid Storage Tank Temperature Controller

Calibration

SWI-I&C TI-1, Test Instrument Calibration

b.

Findings

(1) Noncompliance

No items of noncompliance were identified.

(2) Deviations

No items of deviation were identified.

(3) Unresolved Items

No unresolved items were identified.

12.

Surveillance Testing and Calibration Control Program

The inspector examined surveillance testing, calibration and inspection

required by Section 4 of the Technical Specifications, inservice

inspection of pumps and valves as described in 10 CFR 50.55a. (g),

and calibration of safety related instrumentation not specifically

controlled by Technical Specifications. A review was conducted of

master surveillance and calibration schedules for test frequency,

1434

323

- 16 -

group responsibility and status. Responsibility has been assigned

for approval, performance, acceptance criteria verification, and

maintaining an up-to-date schedule,

a.

Documentation Reviewed

5 ACD 1.5, Procedure Control

5 ACD 3.4, Records Management

5 ACD 3.3, Operations Committee

3 ACD 3.9, Review & Approval of Plans, Schedules and Procedures

3 ACD 9.1, Surveillance Test Programs

3 ACD 9.2, Surveillance Test Procedures

SWI-I&C-3, Initial Refueling Instrument Calibration Schedule

SWI-I&C.PM-5, Feedwater Header Flow DPI Calibration

SWI-I&C.SUR-1, I&C Surveillance Program General Description &

Guidelines

OPNS Section G, Surveillance

RPM Section H series, Plant Testing & Surveillance Files

b.

Findings

(1) Noncompliance

No items of noncompliance were identified.

(2) Deviations

No items of deviation were identified

(3) Unresolved Items

3 ACD 3.9 requires in part that surveillance test schedules

and inservice inspection examination schedules be approved

by the plant manager and reviewed by the plant operations

committee for general adequacy. Although this directive

was effective July 2, 1979, it was received at the station

on July 13, la79 and has not been incorporated in the

station 5 ACD series.

It appears that there is a lack of

responsibility assignment at the station level to handle

new ACD's or changes to the 3 ACD's that affect 5 ACD's.

13.

Receipt, Storage and Handling of Equipment and Materials Program

The inspector reviewed the program to verify the administrative

controls and implementation of the program were within the require-

ments as set forth in the Prairie Island Operational Quality Assurance

Plan, ANSI N 18.7-1976 and ANSI 45.2.2-1972.

l434

24

- 17 -

a.

Documentation Reviewed

(1) The following documents were reviewed to verify the establish-

ment of administrative controls for receipt of safety-related

items, disposition of items received onsite, storage of

items and handling of items.

1 ACD 5.3, Supplier Inspection

3 ACD 6.1, Uniform Nuclear Plant Procurement Process

5 ACD 8.1, Receiving Process

5 ACD 8.2, Inventory Control

5 ACD 8.3, Weld Material Control

5 ACD 8.4, Control of Non-Conforming Items

SWI-I&C-SP-1, Spare Parts Inventory Control

SWI-OS-Z, Inventory Control

(2) The following documentation was reviewed and actual physical

inspections were performed to verify the administrative

controls were properly implemented.

Puicnase Orders

M-87089

M-02041

M-94194

M-51305

M-59927

M-99574

M-97383

M-99623

b.

Findings

(1) Noncompliance

No items of noncompliance were identified in this area.

(2) Deviations

No deviations were identified.

(3) Unresolved Items

The following items do not conform with the Prairie

Island Operational Quality Assurance Plan and ANSI N

45.2.2.

(a) The requirement for administrative controls to conduct

periodic inspections of the storage areas as per ANSI

N 45.2.2-1972, paragraph 6.4.1 and the actual conducting

of such inspections are not implemented or performed.

1434

425

- 18 -

(b) The requirement for administrative controls for

handling of safety related material and for hoisting

equipment used in the handling of safety related

equipment as per ANSI N 45.2.2-1972, paragraph 7 are

not implemented or performed.

(c) The requirement for administrative controls for

maintenance and care of items in storage including

shelf life as per ANSI N 45.2.2-1972, paragraph 6.4.2

are not implemented or performed.

(d) 5 ACD 8.2 states that to return an unused item to

storage it shall be inspected by the Quality Engineer;

contrary to this the I&C Section Work Instruction

allows returning QA-1 items to storage without the

required QA inspection.

(e) Levels of Storage - No apparent attempt has been to

establish the 4 levels of storage as per 3 ACD 6.1

Rev. I and ANSI N45.2.2-1972.

c.

Discussion

Access control to storage areas and security of storage.

- On July 10, 1979 observed many personnel enter the

warehouse storage area without any appearent access

control.

- Eating and drinking in I&C storage area.

- 12 I&C specialists, 2 I&C coordinators and the I&C

engineer are allowed access to the I&C storage

area.

- The I&C storage area is actually part of the I&C

shop.

- Several boxes of I&C parts were sitting on floor in

I&C shop work area.

Use of correct procedure for rcceiving controls.

Plant was

using the receiving process as specified in 3 ACD 6.1, step 6.7

while the receiving process as deliniated in 5 ACD 8.1, step

6.1 has not been revised to reflect new process.

14.

Procurement Program

The inspector reviewed the program to verify the administrative

controls and implementation of the program were within the requirements

as set forth in the Priarie Island Operational Quality Assurance

Plan, ANSI N 18.7-1976 and ANSI N 45.2.13.

d

,i

"

)434

326

- 19 -

.

a.

Documentation Reviewed

(1) Reviewed 3 ACD 6.1, Rev. 2, May 2, 1979, to verify the

establishment of administrative controls for procurement

documents on safety related items and to provide measures

and assign responsibilities to provide an acceptable

method for qualifying a vendor, supplier, or cont.ractor.

(2) The following documentation was reviewed to verify the

administrative controls were properly implemented.

Purchase Orders

M-03734

M-05218

M-04426

M-05509

M-04896

b.

Findings

(1) Noncompliance

No items of noncompliance were identified

(2) Deviations

No deviations were identified

(3) Unresolved Items

No unresolved items were identified.

15.

Records

The inspector reviewed the program to verify the administrative

controls and implementation of the program were within the requirements

as setforth in ANSI N45.2.9-1974, Corporate Directive 1ACD 4.3,

Rev.0, PINGP Directive 5 ACD 3.4, Rev. 1, 10-19-77 and Criterion

XVII of Appendix B to 10 CFR 50.

a.

Documentation Reviewed

(1) The following documents were reviewed to verify the establish-

ment of proper administrative controls and implementing

instructions to maintain the records required by Technical

Specifications, to accomplish proper storage control of

records, to insure retention periods for records have been

established and to insure responsibilities for above

requiremeats have been assigned.

1434

427

- 20 -

1 ACD 4.3

SWI-OS-9

3 ACD 3.8

5 ACD 3.4

Operational Quality Assurance Plan

(2) The following records were checked to ensure they were

retrievable;

firmly attached in binder or placed in

folders or envelopes, or other su. table containers; stored

in a suitable file cabinet or selving in a container in a

predetermined location and stored in a proper storage

facility.

Unit I and 2 Reactor Operators Log

Operations Log

Audit Reports

Discrepancy Reports

I&C Calibration Records

I&C Surveillance Records

Procurement Records

Receipt Inspection Records

Reportable Occurrence Records

Review Committee Records

Radiation Exposure Records

Radioactive Release Records

b.

Findings

(1) Noncompliance

Criterion XVII of Appendix B to 10 CFR 50 requires that

" sufficient records shall hc maintained to furnish evidence

of activities af fect 'ng quality. The records shall include

at least the following:

Operating logs and the results of

reviews, inspections, tests, audits, monitoring of work

performance and materials analyses. The records shall

also include closely-related data such as qualifications

of personnel, procedures, and equipment.

Inspection and

test records shall, as a minimum identify the inspector or

data recorder, the type of observation, the results, the

acceptability, and the action taken in connection with any

deficiencies noted. Records shall be identifiable and

retrievable.

Consistent with applicable regulatory require-

ments, the applicant shall establish requirements concerning

record retention, such as duration, location, and assigned

responsibility."

Administrative Control Directive 3 ACD 3.8, Rev. O, November 28,

1977 requires thac " Required records shall be indexed.

This index shall indicate, as a minimum, record retention

times, where the records are to be stored, and the location

}khk

- 21 -

of the records within a specific file. A Records System

.

Index which identifies r.11 required record files and their

location shall also be provided."

Administrative Control Directove 5 ACD 3.4, Rev. 1, October 19,

1977 requires that "A general index shall be established

listing the required records and QA record index 1rcation".

Contrary to the above: no general index had been established

or maintained listing retention times which are required

by Technical Specificatio.is and other controlling documents.

(2) Deviations

,

.

No deviations were identified.

(3) Unresolved Items

Storage of Records - Although, some records are microfilmed

at this time, there are many more which are not maintained

in proper storage facilities. Records which are required

by the Technical Specifications are located in many places

and in some cases the manner in which they are stored is

quite lax. For example, there is a definite lack of

controlling access to required records and maintaining

fire prevention or environmental control except normal

administrative building methods.

A major problem with record storage is the lack of storage

facility. The licensee stated in a letter, dated March 8,

1978 to the Director, NRR that this was a possibly needed

facility. The inspector stated that a storage facility to

bring PINGP up to the minimum requirements of 3 ACD 3.8,

Rev. O, is needed. The cchedule for completion and imple-

mentation of a storage facility will be inspected during a

subsequent inspection.

16.

Document Control Program

The inspector reviewed the program to verify the administrative

controls and implementation of the program were within the requirements

as setforth in the Prairie Island Operational Quality Assurance

Plan.

a.

Documentation Reviewed

(1) The following documents were reviewed to verify the estab-

lishment of administrative controls for drawings, manuals,

and Technical Specifications control:

l434

329

22 _

,

3 ACD 5.1

5 ACD 4.2'

.

5 ACD 1.1

5 ACD 4.3

5 ACD 1.2

5 ACD 4.4

5 ACD 1.4

SWI-OS-5

5 ACD 4.1

SWI-OS-6

(2) The inspector reviewed ten working drawings at 3 different

locations to insure they were being maintained in accordance

with SWI-OS-5.

(3) The inspector verified the Operations Manual was located

in specified areas, procedure 5 ACD 4.1, Rev. 2 was in

each manual and pages were properly stamped.

(4) The inspector reviewed the controlled drawing file at the

four required locations to determine if they were being

maintained in accordance with 5 ACD 4.4, Rev. 4.

b.

Findings

(1) Noncompliance

No items of noncompliance were identified in this area.

(2) Deviations

No deviations were identified.

(3) Unresolved Items

(a) The methods of maintaining controlled drawings in the

I&C work area, electrical work area and the electrical

engineer work area did not conform with the Operational

Quality Assurance Plan and 5 ACD 4.4, Rev. 4 in that

the authorized users of the file were not designated

and the responsible person for the files in the case

of the I&C and electrical engineer files was not

aware of the requirements as set forth in the afore-

mentioned procedure.

(b) The procedure for drawing control, 5 ACD 4.4, Rev. 4,

was not revised nor had steps been taken to revise

the procedure when the control room controlled drawing

file was cancelled on June 21, 1979. This item was

brought to the attention of the responsbile supervisor

and a change was initiated.

)434

330

- 23 -

17.

Onsite Review Committees

.

The inspector reviewed onsite Review Committee minutes to ascertain

whether the onsite review funcitons were conducted in accordance

with Prairie Island Technical Specification.

a.

Documentation Reviewed

The inspector reviewed the following items reviewed by the

Operations Committee to verify that those who participate in

the review included persons who constituted a quorum and

possessed expertise in the areas reviewed.

IE Bulletin 78-05

Reportable Occurrence 78-14 and 79-12

Safety Evaluation #33

Quality Program Report #5

b.

Findings

(1) Noncompliance

No items of noncompliance were identified.

(2) Deviations

IE Bulletin 78-05 response states that the required

inspections would be completed by June 1, 1979, and on

February 22, 1979 the item was discussed during Onsite

Review Committee meeting #399 reflecting that the commit-

ments would not be completed and a update to bulletin

response would be required.

Contrary to the above as of July 13, 1979, the inspections

had not been completed and no update has been received by

the NRC.

(3) Unresolved Items

(a) TS 6.2.B requires a Quorum of Operations Committee

(OC) to consist of a majority of the permanent members

including the Chairman or Vice Chairman.

The inspector noted that 5 ACD 3.3, Rev. 5 allows the

Duty Engineer to act as Chairman in the absence of

both the Chairman and Vice Chairman.

A review of the last years OC minutes shows that this

has not occurred,,but if it did occur Prairie Island

would be in violation of their own Technical

Specifications.

- 24 -

i434 3

. (b) Quality Finding Report #5 was initiated June, 1977 and was not reviewed by the OC committee until February, 1979. The conclusion of the committee that changes may be required to the Work Request Authorization form did not appear to be followed up. 18. Unresolved Items Unrec'nved items are matters about which more information is required in order to ascertain whether they are acceptnble items, items of noncompliance, or deviations. Unresolved items disclosed during the inspection are discussed throughout the report. 19. Exit Interview The inspectors met with the licensee representatives (denoted in Paragraph 1) at the conclusion of the inspection on August 9, 1979. The senior inspector stated that the findings for each area inspected are presented in three parts; items of noncompliance; deviations; and unresolved items. In a letter to NRR dated March 8, 1978, the licensee stated that implementation of certain portions of the Operational Quality Assurance Plan (0QAP) cannot be accomplished until the end of 1979. Unresolved items are items which would be considered to be noncompliance if the problems continue to exist after the end of 1979, and the licensee is requested to consider these items at this time in order to bring their Quality Assurance program into full compliance with the OQAP by the end of 1979. The licensee is also requested to consider the discussion items in the report to decide whether application of these items would result in overall QA program improvement. Actions taken regarding these unresolved items will be reviewed in subsequent followup inspections. Licensee representatives had no significant questions or comments regarding the findings which were discussed. )hbh . ! - 25 - }}