Forwards Interim Deficiency Rept Re Safety Injection Sys Piping
Date released: 08/12/2019 Download: ML19210D635


Interim Deficiency Rept Re Safety Injection Sys Piping. Weld Between Sump Liner & Process Pipe Found Insufficient to Carry Design Loads During Routine Design Review.Design Investigation Underway to Correct Problem
ML19210D643
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 11/21/1979
From:
HOUSTON LIGHTING & POWER CO.
To:
References
Download: ML19210D643 (5)
Forwards Interim Deficiency Rept Re Safety Injection Sys Piping
ML19210D634
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 11/21/1979
From: Eric Turner
HOUSTON LIGHTING & POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
Download: ML19210D634 (2)