ML19210B987
| ML19210B987 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 10/05/1979 |
| From: | Seidle W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Eric Turner HOUSTON LIGHTING & POWER CO. |
| Shared Package | |
| ML19210B988 | List: |
| References | |
| NUDOCS 7911130116 | |
| Download: ML19210B987 (2) | |
See also: IR 05000498/1979013
Text
--
'
o
UNITED STATES
8)' e
NUCLEAR REGULATORY COMMISSION
- ' "
'. j
REGION IV
?,
4
611 RYAN PLAZA DRIVE, SUITE 1000
D
% .' .b.#
,o
...
October 5, 1979
In Reply Refer To:
RlV
Docket No. 50-498/Rpt. 79-13
50-499/Rpt. 79-13
Houston Lighting and Power Company
ATTN:
Mr. E. A. Turner, Vice President
Power Plant Construction and
Technical Services
Post Office Box.1700
Houston, Texas
77001
Gentlemen:
This refers to the inspection conducted by lk. W. G. Hubacek and other
members of our staff during the period August 6-10, 1979, of activities
authorized by NRC Construction Permits No. CPPR-128 and 129 for South
Texas Project, Units No. I and 2, and to the discussion of our findings
with Mr. R. A. Frazar and other members of your staff at the conclusion
of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection con-
sisted of selective examination of procedures and representative records,
interviews with personnel, and observations by the inspectors.
_
During the inspection, it was found that certain activities under your
license appear to be in noncompliance with Appendix B to 10 CFR 50 of the
NRC Regulations, " Quality Assurance Criteria for Nuclear Power Plants."
The items of noncompliance and references to the pertinent requirements
are identified in the enclosed Notice of Violation.
Nine new unresolved items are identified in paragraphs 3.c, 3.d, 3.k, 3.1,
3.m, 3.n, 6, 9, and 10 of the enclosed report.
This notice is sent to you pursuant to the provisions of Section 2.201 of
the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office, within 30 days of your
receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you, and the results achieved;
(2) corrective steps which will be taken to avoid further noncompliance; and
(3) the date when full compliance will be achieved.
})kh
,
7911130
1
e
Houston Lightir.2 and Power Company
2
October 5, 1979
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room. If the
report contains any information that you believe to be proprietary, it is
necessary that you submit a written application to this office, within 20 days
of the date of this letter, requesting that such information be withheld from
public disclosure.
The application must include a full statement of the reasons
why it is claimed that the information is proprietary. The application should
be prepared so that any proprietary information identified is contained in an
enclosure to the application, since the application without the enclosure will
also be placed in the Public Document Room.
If we do not hear from you in this
regard within the specified period, the report will be placed in the Public
Document Room.
Should you have any questions concerning this inspection, we will be pleased to
discuss them with you.
Sincerely,
-
.. , CD
s'"
'
,, -/. [ L. - -. -
,
-
-
. ...
-
W. C. Seidle,' Chief
Reactor Const'rdction and
Engineering Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
IE Inspection Report No. 50-498/79-13
50-499/79-13
1319
~