ML19210B785
| ML19210B785 | |
| Person / Time | |
|---|---|
| Site: | Midland |
| Issue date: | 10/02/1979 |
| From: | Hood D Office of Nuclear Reactor Regulation |
| To: | Varga S Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML19210B784 | List: |
| References | |
| NUDOCS 7911120368 | |
| Download: ML19210B785 (1) | |
Text
=
p* *E%
y, y,
UNITED. TATES
( (,g NUCLEAR REGULATORY COMMISSION y
g
/: E WASHINGTO N. D. C. 20555 V
[
00T 2 W3 Docket Nos.:
50-329 50-330 MEM0P,ANDUM FOR:
Steven A. Varga, Acting Assistant Director for Light Water Reactors Division of Project Management FROM:
Darl Hood, Project Mcnager, Light Water Reactors Branch No. 4, Division of Project Management THRU:
L. S. Rubenstein, Acting Chief, Light Water Reaptors Branch No. 4, Division of Project Management
. fy
SUBJECT:
REVISED ESTIMATE OF CONSTRUCTION COMPLETION DATE FOR MIDLAND The visit by the NRC staff!s Caseload Forecast Panel on September 18-19, 1979, to the site for Midland Plant, Units 1 & 2, has resulted in a further slip in the Panells projected completion date for Midland Unit 2.
The Panel's revised estimate for completion of Unit 2 (the first of the Midland units scheduled for completion) is June 1982. As indicated in previous letters to the hearing boards for previous projections by the Panel, schedular estimates for this plant, although only a rough indication, could potentially be relevant and material to the Midland proceedings. Accordingly, I recommend that both the remand and OL boards be informed of the revised estimate by the Panel.
The revised estimate of June 1982 for Unit 2 completion represents a seven-month slip in the Panel's previous estimate of November 1981* **. The applicantls current estimate is June 1981***.
However, the applicant is currently developing a revised forecast (Forecast No. 6) to reflect recent increases in electrical quantities and the influence of TM1-2 issues and open licensing issues. Forecast No. 6 will be finalized in January 1980.
The estimate by the Forecast Panel does not include TMI-2 effects and is based principally upon the observed status of Midland construction coupled with the experience of previous plants at this construction stage.
Documentation of the September 18-19, 1979 meeting summary is in progress.
Copies will be forwarded upon completion.
t? n h o o f Darl Hood, Project Manager Light Water Reactors Branch No. 4 Division of Project Management R. Hoefling letter to Remand Board dated May 31, 1979 7k7 R. Hoefling letter to OL Board dated May 21, 1979 3