Forwards Request for Addl Info Re Inservice Inps & Testing Program
ML19210A754
Person / Time
Site: Crane Constellation icon.png
Issue date: 09/12/1978
From: Cheek P
Office of Nuclear Reactor Regulation
To: Reid R
Office of Nuclear Reactor Regulation
References
790912, NUDOCS 7910310567
Download: ML19210A754 (7)


Text

.

i M

SEP 121978 MP1'ORANDbH FOR:

R. W. Reid, Chief, Operating Reactors Branch No. 4 Division of Operating Reactors FROM:

P. Check, Chief, Reactors Safety Eranch Division of Operating Reactors

SUBJECT:

THREE MILE ISLAND 1 - IhSERVICE INSPECTICT!

AND TESTING PROGR/Ji Plant Name: Three Mile Island 1 NSSS Vendor: B&)f.

Docket Number: 30- 89 Responsible Branch roject Manager: ORB-4, G. B. Zwetzig Engineering and Projects Branch Involved: Engineering Branch Description of Task: Review and Evaluate Three Mile Island 1, Inservice Inspection and Testing Program Review Status: Requesting Additional Infomation The ISI&T; Review Groa'p, Division of Operating Reactors, has reviewed Three Mile Island 1 Inservice Inppection and Testing Program. We find that we cannot coa:plete our evaluation until the additional infomation requested in the enclosure is provided.

Or!Wnal Signed by Paul S. Check P. Check, Chief Reactor Safety Branch Division of Operating Reactors

Contact:

G. Johnson 49-23060

Enclosure:

As stated cc:

V. Stello, Jr.

V. Nerses

/_

D. Eisenhut A. Wang

~~ ' - - -

~;

~

B. Grimes G. Walton, IE:I G. B. Zwetzig E. J. Brunner, IE:t c

C. Cheng

{

D. R. Haverkamp

?.,

S. Johnson t

R. Hall, BNL i91 i

O,1Ao7 H. Cobb i

T. Taylor,. PNL I 't 7.)

lcl c

y EApR WH!DekM'j RSPgr N TES: DOR CCheng 7 DIE [elton VNoonan PCh'ec M

..-- l

... :. s...

9/(/78 9b /78 9/_ /78 o,.

9/p/78 NRC PORM 313 (94 5) NRCM 0240 D u: s. eOvEmmesENT PWINTING OFFICES 1979-828484 7910810 5 I 7 /

e

-~.

REQUEST FOR ADDITIONAL INFORMATION THREE' MILE ISLAND NUCLEAR' STATION ENGINEERING BRANCH DIVISION OF OPERATING REACTORS I.

Class I Components 1.

For Items B1.2 and B2.1, Examination Category B-8, the ASME Code requires 10% of the longitudinal and 5% of the circumferential welds to be inspected near the end of each inspection interval.

Please supply additional justification to support your request for eliminating examinations. Low calculated stress alone is not sufficient to warrent exception.

2.

For Items B1.4 and B2.2, Examination Category B-D, the ASME Code requires all nozzles to be examined 100% during the inspection interval. Please supply additional justification to support your request for the proposed selection of nozzles for examination.

3.

For Items Bl.6 and B4.1 Examination Category B-F, the ASME Code requires volumetric and surface examinations of 100% of all safe end welds during the inspection interval. Please provide additional justification for not complying with the Code requirements and provide an estimate of the following:

(a) the normal range of expected radiation dose rates in the area of the safe ends, (b) the total number of man-hours invcived in completing the examinations, and (c) the total number of man-rems involved in completing the examinations.

4.

For Items Bl.13, Bl.14, B2.9 and B3.8, Examination Categortes B-I-1 and B-r-2, please provide more information to justify your request for elimination for cladding inspection.

~

5.

Are three housings equal to 10% of the peripheral control rod housings required to be examined under Item B1-18, Examinatton Category B-0?

6.

For Item B3.1, Examination Category B-B, do the examinations intended meet the 5% requirement for the circumferential welds and the 10% requirement for the longitudinal welds?

1493.s22

. 7.

For Item B3.2, Category B-0, volumetric examination is required by the Code. Please provide a more detailed technical justifica-tion for not meeting the Code requirements.

8.

Will the welds chosen to be examined under Items B4.5, B4.'l and B4.

8. Examination Category B-J, meet the 25% requirement of the Code?

II. Class 2 Components 1.

Will the examinations intended for Items C1.1 and C1.2, Examination Categories C-A and C-8, satisfy the requirements for examination over the service life of the plant?

2.

Provide a technical justificatier for examining the bolting of only three decay heat system flanges over the service life of the unit when the Code requires examination of 100% of the bolting during each inspection interval, a period of ten (10) years.

(Items 3.2 and 4.2, Examination Category C-0).

3.

Provide a technical justification for examining only one pumps support component of one decay heat system pump when the Code requires that all support components shall be examined during each inspection interval, a period of ten (10) years.

(Item 3.4, Examination Category C-E-2).

4.

The Code requires that at least part of the required examinations be perfomed by the expiration of one-third, two-thirds, and the end of each inspection interval, ten (10) years, where the number of required examinations are distributed unformly among the number of inspection intervals.

It is not apparent that the following examinations to be performed during this inspection period, as given in Table 8-1 of your submittal, are in compliance with this requirement:

Item C1.1 Examination Category C-A Item C1.2 Examination Category C-8 Item C1.4 Examination Category C-0 Item C2.1 Examination Category C-F, C-G Item C2.2 Examination Category C-F, C-G Item C2.4 Examination Category C-0 Item C2.5 Examination Category C-E-1 Item C2.6 Examination Category C-E-2 III Class 3 Component For the buried piping systems listed on Table C-2, give th'eir operating pressures and consequences that may result from piping failure.

1493 323

--=

. IV. Pump Testing Program These questions apply to the justification notes for Table 0-2.

1) Applies to Note 2:

In most cases where pump bearings are subnerged and cooled by the working fluid, there exists a thrust bearing at theCan bearing te motor c-r driven end which is accessible.

measurements be made at this bearing?

2) Applies to Note 3:

Where flow meters are not installed, it may be possible to estimate flow rate from other p* essure drop components already in the system such as While the absolute accuracy of such a device may el bnws.

be questionable, its repeatability would satisfy the intent of the code. Please re-examine the pump systems affected and comment on these possibilities. In cases where this is no^ practical, power measurements may be useful in estimating flow.

3) Applies to Note 4:

Calculatedinlet static pressure based on height measurements Some method for the measure-of will meet the intent of the code.

system pressure, allowing AP to be calculated, should be proposed.

4) Applies to Note 5:

In cases where bearings are immersed in oil, can oil temperature prior to cooling be obtained?

5) Applies to Table 0-1:

Pleaseindicate which pumps are constant speed. The Table implies that all except turbine drive emergency feedwater.

V.

Valve Testing Program These questions apply to the notes 1 to 6, to Table E-1, and the request for relief paragraphs A to E in the Licensee's submittal, and to drawings and table discrepancies.

1) Applies to Note 1 & Paragraph A:

In the case of normally closed check valves such as BSV30A/B, there exists an upstream vent or drain connection between the This arrangement should valve in question and a block valve.

1493 124

. allow testing, or as a minimum, demonstration of valvt opening or unsesting, using a substitute fluid during cold shutdowns or refueling. Please review all valves in this category and propose such alt'.rnatives where possible.

2) Applies to Note 2:

The drawing does not show valve function. The note implies con-tainment isolation, but the table does not indicate a leak test for these valves. Please clarify.

3) Applies to Note 3:

Only one valve (SF-V23) is tagged with this note. What is the safety-related function of this valve?

4) Applies to Note 5, Paragraph F:

This note applies to one valve (WDL-V362), but Paragraph F is missing. Wh:t is Paragraph F and what is the safety-related function of this valve?

5) For Category A valves, where leak check "L" is listed in table, type of leak test should be noted. The following NRC position on Category A valves may be used as a guide:

a.

Those valves that perfonn both a pressure isolation and contairanent isolation function shall be leak tested to meet both Section XI of the applicable edition of the ASME Code and Appendix J of 10 CFR 50 requirements, b.

Those valves that perform a pressure isolation function only shall be required to meet Section XI of the applicaole edition of the ASME Code.

c.

Those valves that perform a containment isolation function only shall be required to meet Appendix J of 10 CFR 50.

The inservice testing program should clearly identify which valves are applicable to each of the categories listed above.

1493 325

6)

Describe the operations or tests intended under the submittal type "F -- Functional check of valve operation".

In some cases, this may fall under the code as a " partial stroke" test.

Explain why full stroke is impractical or unwarranted.

7)

Category E Valves:

There are no Category E valves listed, but examination of the drawings shows many locked position valves in the flow paths of safety-related systems.

Please review and correct.

8) All relief valves in safety-related systems should be listed.

Particular 9)

Reactor Building Spray System:

Please review for containment isolation function. Valves selected should be Category A and leak checked.

(FSAR shcws Type 1 arrangement, indicating BSV1A/B & BSV30A/B are containment isolation valves, CIV.)

10)

Decay Heat Removal System: Please review for containment isolation function.

(FSAR shcws Type 1 arrancement, indicating for penetration 310 & 503 that valves DH-4A/B and DH-22A/B are CIV, and Type 4 arrangement for penetration 320, indicating valves DH54 and CH69 are CIV.) Also review for pressure isola-tion, and using guide outlined in Question 5) above, specify leak check required.

11)

Decay Heat River Water System: Where are valves DR-V21A/B and DR-V22A/B located and what is their safety-related function?

12)

Core Flooding System: Valves CF-V4A/B and CF-VSA/B serve a pressure isolation function and should be reclassified AC and leak checked as outlined in Question 5 above. Valves CF-VIA/B should be classified and listed, and or.her valves in this system should be reviewed for their safety-related function.-

13)

React:r Building Emergency Cooling System: What is the safety-related function of valves RR-V3A/B/C and RR-V4A-D? Also, please review function of RR-V9A/B/C and NS-VII to determine whether these valves should also be listed and categorized.

14)

Nuclear Service River Water System:

Drawing missing.

15) Screen Wash and Sluice System: What is safety-related function of these valves?

10 Make-Up System:

Please review function of valves " -V16A-D and I'.U-V107A-D to determine correct classification. Also review all ulves on drawing C-300-017 to determine if they shculd be cate-gorized and listed.

1493 326

_S.

17).In'termediate Cooling System: Please review function of valves IC-V16 and IC-V18 to determine if they should be listed and categorized.

18)

Reactor Coolant System: What is safety-related function of RC-V2 and RC-RV2?

19)

Emergency Feedwater System:

Please review all valves shown on drawing C-300-009 GNI to determine safety-related function and whether or not they should be listed and categorized.