ML19209C983

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-445/79-19 & 50-446/79-19 on 790809-10 & 13-16.Noncompliance Noted:Failure to Follow Nonconformance Procedures for Electrical Cable
ML19209C983
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 09/05/1979
From: Crossman W, Gilbert L, Martin L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19209C977 List:
References
50-445-79-19, 50-446-79-19, NUDOCS 7910180544
Download: ML19209C983 (7)


See also: IR 05000445/1979019

Text

_ . _ _ .

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Repo r- No . 50-445/79-19; 50-446/79-19

Dociat No. 50-445; 50-t46

Category A2

Lic- m : Texas Utilities Generating Company

2001 aryan lower

Dallas, Texas

75201

Facility Name: Ccoanche Peak, Units 1 and 2

Inspection at: Comanche Peak Site, Glen huse, Texas

Inspectica conducted: August 9, 10 and 13-16, 1979

Inspectors:

_

f/f[7f

'

L. D. G(Ibert, Reactor Inspector, Engineering

4)a:fe

Support Section (Paragraphs 1, 3, 4, 7, & 8)

.

/

&?

f?bb

Ab'//f

L. E. Marting Reactor Inspector, Engineering

/Da r'e

Support Sa;t:on ('aa graphs 2 & 6)

e

(August 13-16, 1979, caly)

&c

sp$ps&

T o f-7 D

@. P.'Todlinson, Reactor Inspector, Engineering

Date

Support Section (Paragraph 5)

Reviewed:

W

78

e

R. G. Taylor, Resident Inspector

Bat'e

Projects Section

il77

Ji9

7910180

_.

_ _ _

..

. . . . _ . _

Approved:

h

_, _

8[f ~/9

W. A. Crossman, Chief, Projects Section

D' ate

'

f0$

'

R. E. Hall, Chief, Engineering Support Section

fafe

Insrec_1:n St==ar :

Insce_ ica on Aunts: 9.10 and 13-16, 1979 (Report No. 50-445/79-19;

50- e 7 -Ic;

Areas r_snected: Roc" 'a, unannounced inspection of cons

, ion activicies

,

i

incic---- site tour; observation of work and review of records for safety

related piping, Unit 1; ebservation of work for Reactor Coolant Pressure

Borm c 7--- _3iping, Unit 1; and review of QA implementing procedures for

elec M eni cable and

follow up review of a previously identified item of

noncompliance.

The inspection involved ninety-two inspector-hours by three

NRC inspectors.

Results: In the four areas inspected, one apparent item of noncompliance

was i:ientified in one area. (infraction - failure to follow nonconformance

proce0.ces for electrical cable

paragraph 6).

.

P00RBRIBiku

.

1177

J20

2

_ _ _ _ . . - . . . _ _ . . . _

DETAILS

1.

Persons Contacted

3-4--4 cal Licensee Personnel

  • R. G. Tolson, TUGCO, Site QA Supervisor
  • J. V. Eawkins, TUGC0/G&H, Product Assurance Supervisor
  • !. Icwry, TUGCO, QA Engineer
  • P

Webb, TUSI, Resident Manager

  • L. M. Popplewell, TUSI, Project Electrical Engineer

C ~~- ?ersacnel

J. Reed, Pipe Foreman, Brown and Root (B&R)

D. Cowart, Lead QC, B&R

R. Bodine, Lead QC, B&R

S. Dodd, QC Inspector, B&R

J. Strickland, QJ Inspector, B&R

J. Dale, QC Training Coordinator, B&R

L. Dick, Electrical QC Supervisor, B&R

The IE inspectors also interviewed other licensee and contractor personnel

during the course of the inspection.

  • Denotes those attending the exit interview.

2.

Licensee Action on Previous Inspection Findings

(Closed) Infraction (50-4l'/79-C'- 50-446/79-06):

Failure to Follow

Inspection Procedure for Class IE Cable Tray Supports. The IE inspector

reviewed ten randomly selected cable tray supports that were Class IE

and previously inspected as non Class IE to ensure that the hangers had

been reinspected as Class IE. The IE inspector reviewed Brown and Root

Procedure QI-QP-ll.3-2, Revision 8, " Cable Tray Hanger Inspection," and

the associated training records for Revision 8.

All Class IE and non IE

hangers have been reinspected and all rework on Class IE hangers initiated

by this reinspection has been completed.

3.

Site Tour

The IE inspectors walked through the Unit 1 Reactor Building and Auxiliary

Building to observe construction activities in progress and to inspect

housekeeping.

No items of noncompliance or deviations were identified.

I177

221

3

_

.

- - . . .

- - - . . - - . . .

. - . - - - . . .

.

..

..

_.

.

l k I hd${13lg]

g:

g

gl p)g)[-

E

INfi

-

4.

Safety Related Piping - Unit 1

The IE inspector observed the piping activities involving identification,

>='dling, installation and quality related inspection of the following

i+=-c:

Spool Pes. 6Q3 and SQ3 from Drawing BRP-BR-1-SB-06; Spool Pcs. 6Q2

and SQ2 frem Drawing BRP-CS-1-SB-10; and Spool Pc. 2Q2 and Valve 1-8400

from Drawing BRP-CS-1-SB-31.

The IE inspec cr verified the fit-up and evidence of QC inspection for

pipe weld numbers I~4-8 on Line 6-CC-1-204-152-3 and FW-5 on Line 3-CS-1-

139-151-R2.

On completion of fit-up and gas purging of FW-5, the IE

'-----tcr abserved the root welding of the joint for compliance with the

wid pr=* m.

The IE inspector observed the welding of two other pipe welds, FW-18 on Line

-EE-X-001-151-R3 and FW-22 on Line ?-CS-1-242-151-R2, for compliance with

t2e weld procedure.

The IE inspector selectively reviewed documentation of receiving inspections,

saterial test reports, welder qualifications, QC personnel certifications

and nondestructive test results for the following pipe spools and welds:

Drawing

Spools

Welds

BRP-CS-1-AB-24

2Q3 & IQ3

FW-1 & FW-se

BRP-AF-1-SB-11

1&2

FW-i & FW-3

.

BRP-CC-1-SB-20

~

FW-7 & FW-la

-

1&3

FL-9

BRP-CT-1-SB-03

-

,

BRP-CT-1-SB-01

-

FW-2

BRP-RH-1-SB-19

2 & 1-8717

FW-3

BRP-RH-1-SB-07

-

FW-5

BRP-SI-1-SB-04

8Q2 & 2

FW-4

BRP-SI-1-SB-14

-

FW-8

In the areas inspected, no discrepancies from the requirements of the

weld procedures; the piping fabrication construction procedure, Procedure

CP-CPM-6.9; or the ASME B&PV Code were noted.

No items of noncompliance or deviations were identified.

I177

J22

4

..

.

._

_-. . . _ _ _ . _ _ _ . _ .

_. __.

. _ .

_ _ _ . __

_ _ . _ _

_

.

l

)

h

f%$.

$ M { {_[

\\

5.

Reactor Coolant Pressure Boundary Piping - Unit I l

v ult

3e IE inspector witnessed the liquid penetrant inspection of one repair

area on each of two pressure boundary piping welds (BRP-CT-1-RB-046

To-1 and BRP-RC-1-520-1 FW-19).

Both areas had been identified by

radiog sphy, escavated by grinding and were being inspected immediately

pri:r to repair weldiag. QC records for both joints were reviewed for

aaacuacy. Personn4 qualification records were also checked for the

welcers perfo + g the , pairs and the inspectors. The record packages and

"~ = =aterial issue cards were checked against the repair procedures to

assu e the correct welding rod and verify that other welding variables were

somCt..

.

_ca II insp- m r wi~ essed the pre-weld fit-up operation on one 4"

cnent cooling system pipe joint (BRP-CC-1-RB-23-2-FW-4).

A physical

cr* was made to verify the joint alignment and fit-up dimensions prior

to velding.

Ihe weld joint record package was reviewed to assure that

QC verification, weld identification and joint location were correct. The

weld procedure was compared to the weld joint data package for agreement

and the welding operation was witnessed to assure compliance with the welding

procedure.

No items of noncompliance or deviations were identified.

6.

Electrical Systems

a.

Cable Identification Deterioration

b

During an inspection of the cable reel storage yard, the IE inspector

noticed that there had been some deterioration in the color of many

i

of the cables in the yard.

Some of the orange colored cables had

faded, some of the white color coding was flaking and peeling off.

'

This color coding is the licensee's principle means of meeting the

identification of Class IE and associated cables required by the

!

FSAR Section 8.3 and IEEE-384, 1974.

The IE inspector asked the licensee representative if any action was

'

under way to evaluate this deterioration of the cable identification

with the A/E and the supplier. The licensee's representative told the

IE inspector that the deterioration in the color coding had been ques-

tiened, but that no formal action had been initiated.

The deterioration of this color coding on Class IE and associated

cables is being considered as an unresolved item pending identification

and qualification of the color coding medium, the determination of

cause of deterioration, and the licensee's action to preclude or

correct the deterioration to ensure proper identificatica of Class IE

and associated cables during and after installation in the plant.

b.

Nonconformance Report Corrective Action

During the inspection of the cable reel yard, the IE inspector noticed

that cable reel No. W-108-1 had a QC hold tag on it which referenced

5

1177

J23

._

_ . _ _ _ _ _ _ _ .

. . _ . . _ . . _ _

. _ _ _ . _

__

-

.

.

NCR E-1570. Af ter review of NCR E-1570, the in inspector was able

to identify numerous other reels of improperly color coded cable in

the reel storage yard, as described and included in the NCR. Reel

No. W-108-1, however, was the only reel which was on QC hold. The

other reels that were improperly color coded were not segregated

or tagged as conconforming. The licensee's representative acknowledged

the nonco

  1. -- 4 g condition of these cable reels and the absence of

QC TEold" tags and/or segregation of this nonconforming material. All

ca',le in the reel yard by procedure is released and acceptable for

installarica taless the material has been identified as nonconf ; ming

and prcperly targed.

Cr'13 7 Assurn,ce Procedure, QAP 15.1, Revision 5, July 18,1979,

"Cantani. of Neucenforming Items," paragraph 3.1.1 requires that, "Non-

c aforsing items shall be identified by a red " Hold" tag and when

practicable segregated trem acceptable items."

Figure 13 of QAP 15.1, Step No. 17 requires, " Disposition: Action

to be taken to resolve /close the nonconformance."

10 CFR 50 Appendix B, Criterien V requires that " Activities affecting

quality .

. shall be accomplished in accordance these instructions,

.

procedures, or drawings."

Contrary to the above:

NCR E-1570 identified two installed cables (E0102531 and E0102532)

'

and cable reel W-105-1 that were color coded orange witi white stripe,

contrary to specification ES 13.B2 which required solid orange colored

jacket. These three items were properly tagged wita QC " Hold" tags.

However, the NCR also stated chat there was a large number of both

orange and green cable in the reel yard which were required to have

solid colored jackets that also have white stripe;. The IE inspector

determined that this large nu.aber turned out to be twenty addir.ional

reels of table that were also nonconforming. On August 14, 1979, only

one reel 5-108-1 had been tagged and placed on hold.

The other twenty

reels were in the reel yard without tags or any identification or

segregation indicating that the cable was not suitable for installation.

The disposition for NCR required the repulling of cab.es E0102531

and E0102532 utilizing orange jacketed cable. This corrective

action is insufficient in that it only addresses these two cables.

The nonconforming condition described a large number of nonconforming

reels of cable and the possibility of more cables having been in-

stalled with improperly colored jackets. The disposition described

above would not have provided a satifactory action to resolve or

close the nonconformance.

I177

J24

6

.

.

.

The above are two examples of failure to comply with 10 CFR 50

Appendix B, Criterion V.

This is an infraction.

c.

Record Review

I

O

!N

i

L*

ne II inspector reviewed the following document packages for power,

c:n rel, and instrumentation cables, for compliance with FSAR

Chapter S, 10 CFR 50, IEEE 323 and 383, IPCEA STDS, and specifications:

"at. .:ial receiving Reports (rRR)-0889, 2553, 2737, 4848, 5215,

2 2 , and 5500.

Receiving Inspection Reports (RIR) - 04129, 06737, 07115, 07429,

10477, 10778, 10787 and 11108.

These packages were reviewed for completeness and for inclusion of

.anufacturer test, qualification reports, and certificates of

compliance.

No ite=s of noncompliance or deviations were identified.

7.

Enresolved Items

Unresolved items are matters about which more information is required

in order to ascertain whether they are acceptable items, items of

noncompliance, or deviations. An unresolved item disclosed during

the inspection is discussed in paragraph 6.

-

8.

Exit Interview

The IE inspectors met with licensee representatives (denoted in para-

graph 1) at the conclusion of tne inspection on August 16, 1979. The

IE inspectors summarized tne purpose, scope and findings of the inspection.

The licensee representatives acknowledged the statemer M b1 the inspectors

with regard to the item of noncompliance and the unreso aed item.

1177

J25

.

7