Forwards IE Insp Repts 50-266/79-12 & 50-301/79-14 on 790820-24 & Notice of Violation.Notice of Violation & Details of Insp Repts Withheld (Ref 10CFR2.790)
ML19208D820
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 09/12/1979
From: Hind J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
Shared Package
ML19208D821 List:
References
NUDOCS 7910010051
Download: ML19208D820 (2)


See also: IR 05000266/1979012

Text

/

,

'n

f. ansa

c.

.,;

8'3

'on

UNITED STATES

NUCLEAR REGULATORY CFAMISSION

Nb

' $,

E

REGION 111

6

o,

'[

799 ROOSEVELT ROAD

%

j'

GLEN ELLYN. ILLINOIS 60137

SEP 1219B '

Docket No. 50-266

Docket No. 50-301

Wisconsin Electric Power Company

ATIN:

Mr. Sol Burstein

'

Executive Vice President

Power Plants

231 West Michigan

Milwaukee, WI 53201

Gentlemen:

This refers to the inspection conducted by Messrs. J. R. Creed and

T. J. Madeda of this office on August 20- 4, 1979, of activities at the

Point Beach Nuclear Plant, Units 1 and 2, authorized by NRC Operating

Licenses No. DPR-24 and No. DPR-27 and to the discussion of our findings

with Messrs. G. Reed, R. Krukowski, J. Mielke and other members of your

staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these rreas, the inspection consisted of a

selective examination of procedures and representative records, obser-

vations, and interviews with personnel.

During the inspection, certain of your activities appeared to be in

nancompliance with NRC requirements, as described in the enclosed

Appendix A.

The inspection showed that action had been taken to correct

the identified Items 1, 3 and 4 and to prevent recurrence. Consequently,

no reply to those items is required and we have no further questions

regarding Items 1, 3 and 4 at this time. However, we request that you

respond to Item 2.

It should be noted that although adequate compen-

satory measures were taken regarding that item further corrective action

is required.

This notice is sent to you pursuant to the provisions of Section 2.201 of

the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office within twenty days of

your receipt of this notice a written statement or explanation in reply,

,

including for Item 2: (1) corrective action taken and the results achieved;

(2) corrective action to be taken to avoid further noncompliance; and (3)

the date when full compliance will be achieved.

.

i. . a -

v

.

~

w c m 7; ic;i.

.c

1057

354

7910010 @ !

I

.

Wisconsin Electric Power

-2-

p

3 g7g

.

Company

Areas examined during the inspection concern a subject matter which is

exempt from disclosure according to Section 2.790 of the NRC's " Rules of

Practice," Part 2, Title 10, Code of Federal Regulations.

Consequently,

our report of this inspection and your response will not be placed in the

Public Document Room.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

  • h*

J. A. Hind, Chief

Safeguards Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Reports

No. 50-266/79-12 and

No. 50-301/79-14

(Part 2.790(d) Information)