Responds to NRC Re Violations Noted in IE Insp Repts 50-250/79-11 & 50-251/79-11.Corrective Actions: Will Initiate QC Dept Review of Plant Work Orders on safety-related Equipment
ML19208D487
Person / Time
Site: Turkey Point  
Issue date: 08/17/1979
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19208D483 List:
References
NUDOCS 7909280477
Download: ML19208D487 (1)


Text

P.O. BOX G29100, P.'l AMI, F L 33152 F LORICA POWER A LIGHT COMP ANY August 17, 1979 L-79-227

~

Mr. James P. O'Reilly, Director, Region II

[

fj Office of Inspection and Enforcement N

ZZ U. S. Nuclear Regulatory Ccnmission 101 Marietta Street, Suite 3100 CS

?

Atlanta, Georgia 30303 y

.)

Dear Mr. O'Reilly:

7, Re: RII:PJK

~

50-250/79-11 50-251/79-11 (Supplemental Response)

As requested by Mr. P. J. Kellogg during an August 8,1979 telephone call to members of my staff, Florida Power & Light Company (FPL) submits the following supplement to its July 12, 1979 response to the subject inspection report.

In response to Finding B.1 of the inspection report (Plant Work Orders accomplished without a procedure were not inspected or reviewed by the Quality Control Department), FPL conmitted to initiate a program of Quality Control Department review of Plant Work Orders accomplished without a procedure on nuclear safety related equipment. This program will include review by the Quality Control Department of such Plant Work Orders before the work is performed. This program will provide for inclusion of any required inspection points in the Plant Work Orders.

Very truly yours, cvDW Robert' E. Uhrig Vice President Advanced Systems & Technology REU/DWJ/ MAS:pg cc: Robert Lowenstein, Esquire lt lhb OFFICIALp'OIT 7009280 4'77 PfOPLE. SEltVING PECPLE