ML19208D121

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-440/79-03 & 50-441/79-03 on 790710-12. Noncompliance Noted:Inadequate Insp of Installation of safety-related Components & Inadequate Protection,Storage & Maint of safety-related Components
ML19208D121
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 08/01/1979
From: Hayes D, Julie Hughes, Maxwell G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19208D122 List:
References
50-440-79-03, 50-440-79-3, 50-441-79-03, 50-441-79-3, NUDOCS 7909280015
Download: ML19208D121 (15)


See also: IR 05000440/1979003

Text

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-440/79-03; 50-441/79-03

~

Docket No. 50-440; 50-441

License No. CPPR-148; CPPR-149

Licensee: The Cleveland Electric Illuminating

Company

P. O. Box 5000

Cleveland, OH 44101

Facility Name: Perry Nuclear Power Plant, Units 1 and 2

Inspection At: Perry Site, Perry, Ohio

Inspection Conducted:

July 10-12, 1979

.l

~

Inspectors:

Hu

s

Af 79

v

i

I/8#/If

F. Ma we11

E.'

e

7

7 77

lEh

4.'TAwptt -

7/30 [~lT

H. H. Livermore

?-Q.9)awsL /

D .' 4fayes, Chief

(' %

N 3 / /'77

Approved By:

Engineering Support Section 1

'

'

Inspection Summary

Inspection on July 10-12, 1979 (Report No. 50-440/79-03; 50-441/79-03)

Areas Inspected:

Licensee action relative to previous items of noncompliance

sad unresolved items (Units 1 and 2); ongoing construction activities

(Units 1 and 2); concrete placement inspection activity (Unit 1); QA

implementing procedures relative to instrumentation components at l systems

(Units

and 2); installation of safety related components; work activities

relative o reactor coolant pressure boundary, safety related pipe and

welding (Units 1 and 2).

The inspection involved a total of 88 onsite

inspector-hours by four NRC inspectors.

Results:

Of the areas inspected, two items of noncompliance were identified

in two areas (infractions - (1) inadequate inspection of installation of

safety related components - Section III, Paragraph 2; (2) inadequate

protection, storage and maintenance of safety related components - Section

III, Paragraph 3).

7909280 OI5

l U .s <J

,!

-,,

.

DETAILS

Persons Contacted

Principal Licensee Employees

.

  • M. Edelman, Managee, Nuclear QA Department
  • G. Groscup, Manager, Nuclear Engineering Department
  • D. Fitzpatrick, Site Construction Manager
  • W. Kacer, CQS General Supervising Engineer
  • A. Kaplan, General Supervisor Construction

S. Tulk, CQS Lead Electrical Quality Engineer

Other Personnel

  • P. Gibson, CQS Quality Control Supervisor (KEI)
  • R. Vondrasek, CQS Quality Engineering Supervisor (GAI)

J. Connelly, CQS Lead Civil Quality Engineer (GAI)

R. Croftman, CQS Lead Piping Quality Engineer (GAI)

W. Ware, CQS Civil Quality Engineer (GAI)

  • G. J. Presby, CQS Mechanical Quality Engineer (GAI)

W. Eiff, CQS, Civil Quality Engineer (GAI)

R. Czyzewski, CQS Civil QC Inspector (KEI)

R. Mauchline,

  • E. V. Knox, Quality Assurance Manager (KEI)

N. R. Barker, Quality Assurance General Manager (GAI)

D. F. Cooper, CQSS Supervisor (KEI)

J. Miller, Quality Assurance Manager (Pullman)

R. Skidmore, Quality Control Supervisor (NNI)

D. Codney, Maintenance Supervisor (NNI)

R. Shelton, Field Engineer (NNI)

J. W. Mehaffey, GAI, QE

T. Bradshaw, GAI, QE

J. Staffiera, NNI, QA Manager

D. Basile, NNI, QC Manager

R. T. Durand, NNI, NSSS Manager

D. Dervay, NNI, NSSS Engineer

T. E. Bond, NNI, QA/QC Operation Manager

W. F. Newell, NNI, Welding Engineer

  • K. S. Zidek, CQE Department Secretary (GAI)
  • Denotes those who attendend the exit interview.

The insper tors also contacted other licensee and contractor employees,

including members of the quality, technical and engineering staffs.

-2-

3-.

ILJO

..

Licensee Action on Previous Inspection Findings

(Closed) Noncompliance (440/77-07-09; 441/77-07-09): Newport News records

for inspection / test devices not containing necessary information to

ascertain traceability to the National Bureau of Standards or equivalent.

The inspector reviewed Newport News revised Instruction 701-NC-S1 (Rev. F)

and spot checked the most current calibration records for inspection / test

equipment and found the records to show traceability to the National

Bureau of Standards. This item is closed.

(Closed) Unresolved Item (440/79-02-02; 441/79-02-02): Numerous Corrective

Action Requests (CARS) writte i against Newport News Industrial Corporation

(NNI); reference CARS numb .ed 0450, 6'52, 0463 and 0464. On March 26

-

and 27, 1979, CEI held a management meeting with NNI and as a result of

the meeting; as of May 10, 1979, all of the concerns noted in the afore-

mentioned CARS have been resolved. This item is closed.

(Closed) Unresolved Item (440/78-13-01; 441/78-12-01): Handling of

returned welding materials. The inspector reviewed the revised Pullman

Power Products (PPP) procedure No. VIII-3 and determined that handling of

returned welding materials was clarified.

-3-

,,_

lUJd

j

.

Section I

Prepared by J. Hughes

G. F. Maxwell

.

Reviewed by D. W. Hayes, Chief

EngineerinF Support

Section 1

1.

Instrumentation - Implementing Procedures (Johnson Controls)

Units 1 and 2

The inspectors compared the below listed Johnson Controls

a.

Incorporated implementing procedures with the Johnson Controls

QA/QC Program, job specifications No. SP90 (Rev. II) and No.

SP709 (Rev. III).

(1) Procedure for " Indoctrination and Training of Key Personnel,"

SP-201-DNPP (Rev. 1).

(2) Procedure for " Auditor Training and Qualification,"

QAS-202-PNPP (Rev. 1).

(3) Procedure for " Design Control," QAS-401-PNPP (Rev. 1).

(4) Procedure for " Preparation and Approval'of Procedures,"

QAS-402-PNPP (Rev. 1).

(5) Procedure for " Document Control," QAS-701-PNPP (Rev. 2).

(6) Procedure for " Control of Field Questions, Field Variance

Authorization and Engineering Change Notices," QAS-702-PNPP

(Rev. 1).

(7) Procedure for " Vendor Evaluation," QAS-501-PNPP (Rev. 1).

(8) Procedure for " Weld-Rod Control," QAS-904-PNPP (Rev. 2).

'

(9) Procedure for " Training and Qualification of Inspection

and Testing Personnel," QAS-201-PNPP (Rev. 1).

(10) Procedure for " Receiving Inspection," QAS-802-PNPP (Rev. 4).

(11) Procedure for " Storage of Items of Materials," QAS-1401-PNPP

(Rev. 1).

(12) Procedure for "Nonconformance Control," QAS-1601-PNPP

(Rev. 2).

-4-

0

. 0f

(13) Procedure for " Visual Inspection," QAS-1001-PNPP (Rev. 5).

(14) Procedure for " Liquid Penetrant Examination," QAS-1002-PNPP

(Rev. 3).

(15) Procedure for " Welding Procedure and Performance Qu,alification,"

QAS-1005-PNPP (Rev. 0)

(16) Procedure for " General Welding Requirements," QAS-1006-PNPP

(Rev. 0).

(17) Procedure for " Training and Qualification of NDE Personnel,"

QAS-1003-PNPP (Rev. 1).

(18) Procedure for " Control and Calibration Program for Measuring

and Test Equipment," QAS-1301-PNPP (Draft).

(19) Procedure for " Pneumatic Testing," QAS-1202-Pnpp (Rev. 1).

(20) Procedure for " Conditional Release of I. ems / Material,"

QAS-803-PNPP (Rev. 0).

(21) Procedure for " Handling, Rigging and Transporting of

Safety Related Items," SP-1402-PNPP (Rev. 0).

(22) Procedure for " Identification and Control of Materials,"

QAS-902-PNPP (Rev. 3).

b.

During review of licensee specifications SP-90 and SP-709, the

inspector was unable to determine how the Class IE instrument

racks were going to be identified to the channel level (example:

color coded). The inspector was informed by the licensee's

Lead Instrument Control Engineer that licensee purchased instru-

ment racks were purchased with color coding of the instrument

tubing on the racks and that all racks purchased by other

contractors will be color coded the same.

This matter will be

reviewed further during subsequent inspections (440/79-03-01;

441/79-03-01).

No items of noncompliance were identified.

2.

Observation of Concrete Work Activities and Related Quality Records

- Units 1 and 2

Pre-Placement Inspection (AX2-W13-650) - On July 11, 1979, the

a.

inspector performed a pre placement inspection of concrete

Placement No. AX2-W13-650. The placement area was located in

the Auxiliary Building II interior wall; contained approximately

200 cubic yards of concrete aid was placed by the National

Engineering Contracting Companj (NECC).

-5-

)bJ

.

The RIII inspector witnessed the pre placement inspection with

the NECC and CEI QC inspectors for cleanliness of the reinforcing

steel, horizontal and vertical construction joints, and formwork

in accordance with NECC procedures. The pre placement inspection

record was signed off by the NECC and CEI QC inspectors after

the pour area was satisfactorily prepared and concrete placement

commenced.

b.

Placement Inspection (AX2-W13-650)

(1) In-Process Concrete Testing

(a) United States Testing field QC personnel performed

slump, temperature and precent entrained air tests as

follows:

Ticket No.

Slump (in.)

Temp. ( F)

% Ent. Air

41030

3

68

4.0

41031

3 1/2

68

5.0

41035

4

69

--

41035

2 3/4

70

--

41044

4 1/2

71

--

41046

3 1/2

70

5.4

41048

4

70

--

41054

3 1/4

70

--

41057

3 1/4

68

--

41067

3

71

--

All test results were within the allowed limits and

performed at the frequencies specified.

(b) Field curing houses which were suitably equipped to

maintain freshly cast compressive strength cylinders

at the intital curing temperature specified by ASTM

C31 were inspected.

(c) The inspector reviewed the calibration data sheets

for the test instruments used for the aforementioned

pour as follows:

Thermometer (TH-113) due date October 9,1979; Unit

weight bucket (UW-6) due date August 3, 1979; Flow

Meter (F/M-16) due date August 8, 1979; Temperature

Record (TR-11) due date November 23, 1979.

(2) Delivery and Placement

(a) Concrete was pumped to the placement area and deposited

via concrete drop chutes which adequately confined

the concrete to a maximum five foot free fall.

bh

.

(b) Concrete was observed to be properly consolidated

using internal concrete vibrators which had been

checked to verify the 8000 VPM required by ACI 301-72,

Chapter 8.

These checks had been documented on the

NECC placement checklist as required by NECC procedures.

c.

Post Placement Inspection

.

On July 12, 1979, the inspector observed that the curing of

pour AX2-W13-650 for moisture, temperatures (concrete and

ambient) were in accordance with specification SP-201.

No items of noncompliance were identified.

3.

Other Areas Inspected

During the inspectors tour of the plant it was observed that several

cable trays when welded to the cable supports (hangers) where burned

through to the inside of the cable pans; the galvanize material was

blistered. The inspector asked the licensee if these blistered

areas would be wire brushed and re painted with galvanizing material.

The licensee informed the inspector, that they would add this item

to there checklist prior to final inspection of the cable tray

systems.

This matter will be reviewed during a subsequent inspection.

(440/79-03-02; 441/79-03-02)

-7-

1010

..

.

Section II

Prepared by E. W. K. Lee

Reviewed by D. H. Danielson, Chief

,

Engineering Support

Section II

1.

Reactor Coolant Pressure Boundary Piping - Review of QA Procedures

(Units 1 and 2)

The inspector reviewed Newport News Industrial arporation (NNI)

Nuclear Quality Assurance Manual, Rev. C, dat a October 10, 1978,

included Perry Addenda B, dated April 18,10.3, nine NNI procedures

and one General Electric Company procedure relative to reactor

coolant pressure boundary piping activities.

The documents reviewed

included document control; receiving inspection; identification;

handling; storage; cleanliness control; erection and installation;

generation and record keeping. The inspector determined that the QA

Manual and the procedures meet the PSAR commitments, 10 CFR 50,

Appendix B and the applicable code requirements.

It was further

determined that the procedures meet the QA Manual requirements.

No items of noncompliance or deviations were identified.

2.

Reactor Coolant Pressure Boundary Piping (Welding) - Review of

QA Procedures (Units 1 and 2)

The inspector reviewed Newport News Industrial Corporation (NNI)

Nuclear Quality Assurance Manual, Rev. C, dated October 10, 1979,

included Perry Addenda B, dated April 18, 1979, 14 NNI procedures

relative to the welding activities of reactor coolant pressure

boundary piping.

The documents reviewed included control of weld

data sheets including hold points; qualification of welding procedures,

welders and inspection personnel, calibration of equipment; repair

of defects and control of welding materials. The inspector determined

that the QA Manual and the procedures meet the PSAR commitments, QA

Manual, 10 CFR 50, Appendix B and the applicable code requirements,

except the following:

a.

Acceptance criteria for undercut of welds needs to be certified.

b.

Qualification requirements for Level III NDE personnel need to

be addressed.

The inspector stated that this matter is considered unresolved

pending a review of the revised procedures.

(50-440/79-03-03;

50-441/79-03-03)

No items of noncompliance or deviations were identified.

-8-

11^7

IbsV

.J

.

3.

Safety Related Piping - Welding Material Control (Units 1 and 2)

,

a.

Review of Documents

The inspector reviewed the following documents:

~

(1) Pullman Power Products (PPP) procedure No. VIII-3, dated

Februa ry 20, 1979, " Control of Welding Materials."

(2) PPP procedure No. VI-5, dated March 27, 1979, " Control of

Process Sheets and Weld Rod Stores Requisitions."

(3) PPP procedure No. IV-502, dated April 29, 1977, " Purchasing

Specification fcr Corrosion - Resisting and Chromium-Nickel

Steel Covered Arc Welding Electrodes."

'

(4) PPP procedure No. X-5, dated May 25, 1978, " Field Receiving

Inspection Procedure."

(5) Receiving Inspection Report, Material Certifications and

Purchase Order for E308L-16 electrodes with Heats No.

761127 and No. 761407; E309-16 electrodes with Heats No.

743288 and No. 743244; ER308L welding rod with Heats No.

776983 and No. 742487; ER309 welding rod with Heats No.

741994 and No. 744153; E70S-2 consumable inserts material

with Heat No. 3789B131; and E7018 electrodes with Heats

No. 401B4021 and No. 432A7641.

It was determined that the above documents met the PSAR, 10 CFR 50,

Appendix B and the applicable code requirements.

b.

Control of Materials

The inspector toured PPP welding material issuing station

located at the control complex.

It was determined that (1) the

welding materials are properly identified and segregated; (2)

the temperature of the rod ovens is maintained; (3) records are

properly kept; and (4) issuance and return of welding materials

are controlled in accordance with approved procedures.

No items of noncompliance or deviations were identified.

4.

Safety Related Piping - Observation of Welding Activities (Unit 1)

The inspector observed the following welding activities:

Essential Service Water System Weld No. 05 on Isometric No.

a.

1-P45-24.

b.

Control Complex Chilled Water System Weld No. 06 on Isometric

No. 0-P47-3.

-9-

- ~,

b)

GJv

.

.

c.

Essential Service Water System Weld No. 07 on Isometric No.

,

1-P45-20.

It was determined that (1) work was conducted in accordance with

traveler; (2) proper welding materials were used; (3) welding procedure

requirements vete met; (4) work area was free of rod-stubs; and (5)

physical appearance was acceptable.

No items of noncompliance or deviations were identified.

5.

Safety Related Piping - Visual Examination of Welds (Unit 1)

a.

Visual Exanination

The inspector visually examined the following completed welds:

(1) Condensate Transfer and Storage System Weld No. 7 on

Isometric No. 1-P11-8.

(2) Essential Service Water System Weld No. 21 on Isometric

No. 1-P45-1.

(3) Low Pressure Core Spray System Weld No. 06 on Isometric

No. 1-E21-6.

(4) High Pressure Core Spray System Welds No. 9 and No. 8 on

Isometric No. 1-E22-7.

It was determined that (1) weld surface finish and appearance

were acceptable and there was no evidence of wall thinning due

to grinding; and (2) arc strikes and weld spatter were not

evident.

b.

Review of Records

The inspector reviewed weld data sheets for the above welds.

It was determined that (1) the records indicated specified

inspections were completed and (2) records are clear and legible.

No items of noncompliance or deviations were identified.

6.

Safety Related Piping - Observation of NDE Work Activities (Unit 1)

The inspector observed liquid penetrant examination of Essential

Service Water System Weld No. 5 on Isometric No. 1-P45-20.

It was

determined that:

(1) surface condition was acceptable, (2) procedure

requirements were met and (3) personnel were properly qualified.

No items of noncompliance or deviations were identified.

- 10 -

GJU

,

j

7.

Safety Related Piping - Welder Qualification (Unit 1)

.

The inspector reviewed the following documents:

PPP procedure No. II-8 dated May 12,1978, " Welder Performance

a.

Qualification."

-

b.

Qualification records of welders performed welJing on welds

stated in Paragraph 4 of this report.

The inspector determined that the above documents met the requirements

of ASME &PV Code,Section IX.

No items of noncompl.ance or deviations were identified.

8.

Safety Related Piping - Observation of Work and Work Activities

(Units 1 and 2)

The inspector toured the pipe storage area.

It was determined that

(1: spools are identified; (2) spools are resting on dunnage and (3)

ends are covered.

No items of noncompliance or deviations were identified.

.

9

- 11 -

o

UJU

'

.

/

Section III

,

Prepared by H. H. Livermore

Reviewed by D. H. Danielson, Chief

.

Engineering Support

Section 2

Functional / Program Areas Inspected

1.

The areas inspected were:

Reviewed four installation procedures of safety related components

a.

to ascertain if installation and inspection signoffs met applicable

specifications and established procedures.

b.

Visually inspected four assemblies of safety related components

to insure compliance with applicable requirements for handling,

storage and maintenance.

Visually inspected two components of safety relattj equipment

c.

and their records to insure required maintenance inspections,

audits, and records are per applicable requirements.

2.

A review of four (4) Newport News Industrial (NNI) installation

procedures revealed the following:

Note: These procedures are for installation / inspection of safety

related equipment in Units 1 and 2

iliary Building.

Procedure 1240-NC-IO10, Manu

ing Installation Instruction

a.

(hII), the installation and

etion of six (6) RHR discharge

heads and suction barrels,

a z LPCI discharge heads and

suction barrels.

(Items 1E12-C002A, B, and C; 2E12C002A, B,

and C and I and 2E21C001.)

(1) In steps 10 through 180 there were 17 instances of a QC

signoff without a prior Trade Supervision signoff (2E21-C001).

(2) In Operation Step 305 where specifically indicated that QC

required, there were no QC signatures on completed work

for Unit 1 RHR A, B, and C and Unit 1 and 2 LPCI (5 instances).

There was no indication on the procedure of any Nonconformance

Report information/ action.

(3) Operation Steps 320-450 indicate "QC Required" for the

complete grout operation. No QC signatures were present

for 37 completed work steps (except noted IE21-C001). No

- 12 -

1 f, s~ V

~ 1I

I

Iv

mg

.

nonconformance information was noted in these steps.

'

Seven (7) steps in the grout operation for LPCI 1E21-C001

were signed off, but were signed one half month prior to

the trade supervision signoffs (June 6,1979, versus

May 17, 1979).

(4) QC Required is indicated on Operation Steps 460, 47'O and

475 alignment of head and barrel for RER 1E12-C002B.

There are no QC sign ffs for the completed work. There is

no indication of any related nonconformances (NCR).

b.

Procedure MII 1240-NC-IOO9, Baseplate Mod / Installation for

Control Complex Chiller, P/N P47B001A, B, and C (Safety Related).

Step 40.

QC signature signed 3 days before Trade Supervision

-

signoff for completed work.

c.

MII Procedure 1240-NC-IO05, Unit 1 Reactor Pressure Vessel

Installation.

(1) Steps 130 and 300 (Vessel alignment and installation

preps) are signed off by QC only.

No Trade Supervision

signoff is present. These steps involve dowel alignment,

lubrication, and completion of vessel preparations for

installation.

(2) From Operation Step 490 and on (through 600 etc.), there

are no signoffs although work is complete.

No reference

to any other document is present.

(The work involved was

reactor vessel alignment.)

(3) Step 610 requires completion of MMI 1240-NC-1006, Anchor

Stud Installation. There is no signoff by Trade or QC,

although this procedure has been completed.

d.

MII Procedure 12' - C-I0O6 Rev. A, Reactor Pressure Vessel

n

Anchor Stud Installation.

Signoffs on this procedure appeared

to be complete.

The above conditions (except Paragraph d.)are considered to be in

noncompliance with Criterion X of 10 CFR 50, Appendix B; Chapter 17

of Perry PSAR Section 17.1.10; and Newport News Industrial ASME

Nuclear QA Manual Rev. C, October 10, 1978, Section 10.1500.

(440/79-03-04; 441/79-03-04)

3.

A visual inspection of safety related equipment installation in

Unit 1 Auxiliary Building indicated the following:

a.

1E12-C002C RHR discharge head and suction barrel.

Two of fcur

connecting flanges were not protected or sealed.

The machined

mating surfaces were not protected by caps or covers of any

- 13 -

ip

n

asu

.

kind. Visible coatings of rust were on all the internal surfaces

,

of the discharge head. Visible rust was present on the two

exposed flange surfaces.

Installation stud threads were exposed

and unprotected from possible damage.

(The stud interfaces

were located on the floor for the barrel and on the discharge

head at motor interface.)

.

b.

1E21-C001 LPCI discharge head and suction barrel. Three of

four connecting flanges were not protected or sealed. Same as

Item a. above. Rust was visible internally and on mating

flanges as previously noted in Item a.

Equipment in same

condition as Item a.

c.

IE51-C001 and C002 RCIC pump and turbine. The equipment was in

a temporary place of storage in a framed plactic enclosure for

temperature stabilization purposes.

The required space heater was not operating at the time of

-

inspection (July 10, 1979 AM). The attached maintenance

record indicated that it was satisfactorily operating that

morning. The heater was working the next day, but the

enclosure was open at one end, thus, cancelling all heat

retention capabilities.

d.

An NNI maintenance inspection on the previously noted equipment

was performed and recorded on the morning of July 10, 1979,

just prior to the NRC visual inspection of July 10, 1979.

The

presence of rust, the exposed unprotected flanges, and the

unsealed internal openings on the RHR and LPCI discharge heads

were not recorded, nor was the absence of heater operation on

the RCIC pump, as is required by NNI Procedure 1240-F-S002

Paragraph 7.1.

There was nothing recorded in the special

comments / problem section of the maintenance form, nor was there

any reference to any Nonconformance Report. The NRC inspector

also observed that the duplicate Maintenance Record Forms 3155

and 2095 attached to the equipment (IE12-C002C and IE21-C001)

were not filled out correctly to the forms requirements (in ink

and full name). Also noted was that the duplicate form attached

to the equipment did not contain the same information as on the

original record copy (office) as required by NNI Procedure

1240-F-S002, Enclosure 1, Paragraph 3.2.5.1.

Recorded entries

were missing on the original, and the inspection dates did not

coincide.

The above conditions are considered to be in noncompliance with

Criterion XIII of 10 CFR 50, Appendix B; the Cleveland Electric

Illuminating (CEI) Corporate QA Manual, Introduction Section and

Section 1300; CEI Contract Specification SP 38-4549-00, Paragraph

5:06.2.c; American National Standard ANSI N45.2.2 Sections 3 and 6;

and Newport News Industrial Equipment Maintenance Instruction

1240-F-S002 Section 7 and Enclosure 1.

(440/79-03-05; 441/79-03-05)

- 14 -

/

3p

,

L

\\CaO

T,

.

Unresolved Items

,

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, items of noncompliance,

or deviations. An unresolved item disclosed during the inspection is

discussed in Section II, Paragraph 2.

-

Exit Interview

The inspectors met with site staff representatives (denoted under Persons

Contacted) at the conclusion of the inspection on July 12, 1979.

The

inspectors summarized the purpose and findings of the inspection.

Each

of the noncompliance items in Appendix A was identitied and discussed.

The licensee acknowledged the findings reported herein.

.

- 15 -

,,

d

&