Text
[
uq'o
(
- aro UNITED STATES
!"),
NUCLEAR REGULATORY COMMISSION
~
n
{
.E REGION 111 e*[
799 ROOSEVELT ROAD o,
GLEN ELLYN. ILLINOIS 60137 Docket No. 50-409
$D 9
eM' Dairyland Power Cooperative ATTN:
Mr. F. W. Linder General Manager 2615 East Avenue - South La Crosse, WI 54601 Gentlemen:
Enclosed is IE Bulletin No. 79-23 which requires action by you with regard to your power reactor facility with an operating license or a construction permit.
Should you have questions regarding this Bulletin or the actions required of you, please contact this office.
Sincerely,
(/ James G. k ier bul a v Kepp Director
Enclosure:
IE Bulletin No. 79-23 cc w/ enc 1:
Mr. R. E. Shimshak, Plant Superintendent Central Files Director, NRR/DPM Director, NRR/ DOR PDR Local PDR NSIC TIC Anthony Roisman, Esq.,
Attorney 1049 125 27_3 7909270
Accession No. 7908220104 SSINS No.:
6820 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.
20555 September 12, 1979 IE Bulletin No. 79-23 POTENTIAL FAILURE OF EMERGENCY DIESEL GENERATOR FIELD EXCITER TRANSFORMER Description of Circumstances:
Florida Power and Light Company recently reported a problem encountered during a 24-hour full load test of the emergency diesel generators (EDG) at their Turkey Point facility.
Approximately 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> into the test, the A-EDG tripped due to a differential relay lockout on B and C phases; the B-EDG was manually stopped, thus interrupting the test at that point in time.
Subsequent investigation and testing by the licensee revealed a design error on both the A and B EDGs which resulted in overheating of the Exciter Power Transformers (EPTs) at sustained high load operation.
The following nameplate data applies to the equipment installed at Turkey Point:
Emergency Diesel Generator General Motors (Electro-Motive Division)
Model EMD-999-20 Engine-turbocharged, 2 cycle, EMD design 20-645E4 Generator-EMD-design Model A-20 Exciter Power Transformer GE-single phase Model-9T24Y1004 Serial-MD Cycles-60 KVA 15 Insulation-4160 V The manufacturer's findings and recommendations regarding the above problem are described below:
"A potential problem can exist if the nm prit h l
the primary windings of the excitation to as the control power transformer (CP DUPLICATE DOCUMENT Entire document previously entered into system under:
ANO 790$220/ON 1049 126 No. of pages: