Forwards IE Bulletin 79-23, Potential Failure of Emergency Diesel Generator Field Exciter Transformer. Action Required
ML19208C618
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 09/12/1979
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Stampley N
MISSISSIPPI POWER & LIGHT CO.
References
NUDOCS 7909270146
Download: ML19208C618 (1)


Text

.

,pn proo

'o UNITED STATES NUCLEAR REGULATORY COMMISSION

- E REGION 11 101 MARIETTA ST N.W.. SUITE 3100 s

MNEk g

ATLANTA. OEORGIA 30303 In Reply Refer To:

SEP 121979 RII:JPO 024f6 ^-

M 17 Mississippi Power and Light Company Aten:

N. L. Stampley Vice President of Production P. O. Box 1640 Jackson, Mississippi 39205 Gentlemen:

Enclosed is IE Bulletin 79-23 which requires action by you with regard to your power reactor facility (ics) with an operating license or a construction permit.

Should you have questions regarding this Bulletin or the actions required of you, please contact this office.

Sincerely, V

James P. O'Reilly Regional Director

Enclosures:

1.

IE Bulletin No. 79-23 2.

List of IE Bulletins Issued in the Last Six Months

Accession No. 7908220104 SSINS No.:

6820 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHING 10N, D.C.

20555 September 12, 1979 IE Bulletin No. 79-23 POTENTIAL FAILURE OF EMERGENCY DIESEL GENERATOR FIELD EXCITER TRANSFORMER Description of Circumstances:

Florida Power and Light Company recently reported a problem encountered during a 24-hour full load test of the emergency diesel generators (EDG) at their Turkey Point facility. Approximately 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> into the test, the A-EDG tripped due to a differential-relay lockout on B and C phases; the B-EDG was manually stopped, thus interrupting the test at that point in time.

Subsequent investigation and testing by the licensee revealed a design error on both the / and B EDGs which resulted in overheating of the Exciter Power Transformers (EPTs) at sustained high load operation.

The rollowing nameplate data applies to the equipment installed at Turkey Point:

Emergency Diesel Generator General Motors (Electro-Motive Division)

Model EMD-999-20 Engine-turbocharged, 2 cycle, EMD design 20-645E4 Generator-EMD-design Model A-20 Exciter Power Transformer GE-single phase Model-9T24Y1004 Serial-MD Cyclec-60 KVA 15 Im ulation-4160 V The manufacturer's findings and reconne are described below:

DUPLICATE DOCUMENT "A potential problen can exist if ti-ne the primary windings of the excitati:n j Entire document previously to as the control power transformer (CP' entered into system under: