Forwards IE Bulletin 79-14,Suppl 2, Seismic Analysis for As-Built Safety-Related Piping Sys
ML19208B919
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 09/07/1979
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
References
NUDOCS 7909240152
Download: ML19208B919 (1)


Text

(

f ga asc,#'o o

![y 3.,, c (,g UNITED STATES NUCLEAR REGULATORY COMMISSION

. \\ " j.

r REGION lil o,('V#'f[

799 ROOSEVELT ROAD

,o 6p-GLEN ELLYN, ILLINOIS 60137

    • ..+

1

'.9 Docket No. 50-266 Docket No. 50-301 Wisconsin Electric Power Company

$TTN:

Mr. Sol Burstein Executive Vice President Power Plants 231 West Michigan Milwaukee, WI 53201 Gentlemen:

The enclosed supplement to IE Bulletin No. 79-14 is forwarded to you to provide added guidance on the intent of the Bulletin.

If you desire additional information regarding this matter, please contact this office.

Sincerely, CL., % gn ~0.

(7 fames G. Ke7pTer~n Director

Enclosure:

Supplement 2 to IE Bulletin No. 79-14 cc w/ enc 1:

Mr. G. A. Reed, Plant Manager Central Files Director, NRR/DPM Director, NRR/ DOR C. M. Trammell, ORB /NRR PDR Local PDR NSIC TIC Sandra A. Bast, Lakeshore Citizens for Safe Energy 983268 7 9 09 2 40Wy$ '

l.

SSINS:

6820 1

Accesstion No.: 7908220109 UNITED STATES NUCLEAR REIULATORY COMMISSION OFFICE OF INS ~ECTION AND ENFORCEMENT WASHINGi0N, D.C.

20555 September 7, 1979 IE Bulletin No. 79-14 Supplement 2 SEISMIC ANALYSIS FOR A5-BUILT SAFETY-RELATED PIPING SYSTEMS Description of Circumstances:

IE Bulletin No. 79-14 was issued on July 2, revised on July 18, and first supplemented on August 15, 1979.

The bulletin requested licensees to take certain actions to verify that seismic analyses are applicable to as-built plants.

Supplement 2 provides the following additional guidance with regard to implementation of the bulletin requirements:

Nonconformances One way of satisfying the requirements of the bulletin is to inspect safety-related piping systems against the specific revisions of drawings which were used as input to the seismic analysis.

Some architect-engineers (A-E) however, are recommending that their customers inspect these systems against the latest revisions of the drawings and mark them as necessary to define the as-built configuration of the systems.

These drawings are then returned to the AE's offices for comparison by the analyst to the seismic analysis input.

For licensees taking this approach, the seismic analyst will be the person who will identify nonconformances.

The first supplement to the bulletin provided guidance with regard to evaluation of nonconformances.

That guidance is appropriate for licensees inspecting against later drawings.

The licensee should assure that he is promptly notified when the AE identifies a nonconformance, that the initial engineering judgment is completed in two days and that the analytical engineering evaluation is completed in 30 days.

If either the engineering judgement or the analytir.al engineering evaluation indicates that system operability is in jeopardy, the licensee is expected to meet the applicable technical specification action statement.

Visual Approximations Some licensees are visually estimatina pipe lengths and other inspection elements, and have not documented wh Visual estimation of dimensions is nh DUPLICATE DOCUMENT where visual estimates are used, the 4 3832(33 ante requirements.

Further, in docurhi Entire document previously entered itally identify those data that were jinto system under: