(Y k (

9 O [4-e E(fa accoq[o UNITED STATES y g( ; gg NUCLEAR REGULATORY COMMISSION E

WASHINGTON, D. C. 20555 O Q August 17, 1979

+

Docket No. 50,344 Mr. Charles Goodwin, Jr.

Assistant Vice President Portiand General Electric Company 121 S. W. Salmon Street Portl;ad, Oregon 97204

Dear Mr. Goodwin:

In May 1976, we issued guidelines reflecting the NRC's policy regarding the implementation of General Design Criterion 3 - Fire Protection.

Since that time, you have perforced a fire hazards. analysis for your facility and have compared its fire protection program with the NRC guidelines.

In late 1976, we set October 1980 as the date for completing the implementation of all modifications associated with this program. This implementation schedule recognized that such modifications should be completed as soon as practical, with due consideration of the nature of the modifications. For example, minor modifications, aooption of administrative controls and additional portable equipment would be completed within six man'ths; however, major modifications would require a year or more to complete and some modifications would be coordinated with refueling cutages.

By their Memorandum and Order in the matter of the Union of Concerned Scientists' Petition for Emergency and Remedial Action, dated April 13, 1978, the Commission directed the staff to use their best efforts to maintain this schedule, and also directed that the Commission be advised if any slippage is anticipated, along with suggested corrective actions.

We urge you to apply your best effcrts to maintain your schedules for completion of all of the fire protection modifications at your facility.

Sincerely,

.~

q

. &,.,kN-@'IU Darrell G. Eisenhut, Acting Dire; tor r,P Division of Operating Reactors 6

Office of Nuclear Reactor Regulation ce-See next page

', b b 3b 790919o M9 A

+8 g

Mr. Charles Goodwin, Jr.

Portland General Electric Company cc: Mr. H. H! Phillips Robert M. Hunt, Chairman Portland General Electric Ccmpany Board of County Ccmmissioners 121 S.W. Salmon Street Columbia County Portl and, Oregon 97204 St. Helens, Oregon 97051 Warren Hastings, Esquire Counsel for Portland General Electric Company 121 S.W. Salmon Street Portland, Oregon 97204 Mr. Jack W. Lentsch, Manager Generation Licensing and Analysis Portland General Electric Company 121 S.W. Salmon Street Portland, Oregon 97204 Columbia County Courthouse Law Library, Circuit Court Room St. Helens, Oregon 97501 Director, Oregon Department of Energy Labor and Industries Building, Room 111 Salem, Oregon 97310 Richard M. Sandvik, Esquire Counsel for Oregon Energy Facility Siting Counsel and Oregon Department of Energy 500 Pacific Building 520 S.W. Yamhill Portland, Oregon 97204 Michael Malmrose U. S. Nuclear Regulatory Commission Trojan Nuclear Plant P. O. Box 0 Rainier, Oregon 97048 Mr. Donalc W. Godard, Supervisor Siting and Regulation Oregon Department of Energy Labor and Industries Building, Rocm 111 Salem, Oregen 97310

._.