Agrees to Plant Site Visit W/Case Load Forecast Panel on 791127-28.Site Visit Delay Will Not Impact Timing of Acceptance Review or Schedule for OL Application Review
ML19208A972
Person / Time
Site: Callaway  
Issue date: 09/14/1979
From: Schnell D
UNION ELECTRIC CO.
To: Licitra E
Office of Nuclear Reactor Regulation
References
ULNRC-324, NUDOCS 7909180369
Download: ML19208A972 (1)


Text

UNION ELccTnic COMPANY 19 01 G R ATIOT STR CCT - ST. Lou t S September 14, 1979

~^;'go f o 9"c5$-

ST

.O usS. M O. 6 3i6 6 Mr. E.

A.

Licitra Project Manager U.

S. Nuclear Regulatory Commission Light Water Reactors Branch No. 3 Division of Project Management Washington, D. C.

20555 ULNRC-324

Dear Mr. Licitra:

CALLAWAY PLANT SITE VISIT NRC CASE LOAD FORECAST PANEL This confirms our verbal notification that Union Electric and other project personnel will be available for meetings with the Case Load Forecast Panel on November 27-28, 1979.

As discussed in our telephone conversation on September 13, your delay of this site visit from the October 23-24 date previously scheduled will not impact timing of your acceptance review or establishment of the staff review schedule for the Callaway Plant Operating License application.

Very truly yours,

/

-[/

;ca/

m um: - _

/

Donald F.

Schnell Manager - Nuclear Engineering DFS/sla cc:

Messrs:

J. K.

Bryan G. Charnoff N. A.

Petrick B. K.

Kanga 360134

\\

/

\\