Forwards IE Insp Repts 50-338/79-29 & 50-339/79-37 on 790626-28.No Noncompliance Noted
ML19208A879
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 07/20/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Proffitt W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML19208A880 List:
References
NUDOCS 7909180125
Download: ML19208A879 (2)


See also: IR 05000338/1979029

Text

- l($ _

%

f* * * %q'c.,

UNITED STATES

%

NUCLEAR REGULATORY COMMISSION

6 M',-2

! '*

'

$U/

5.(r' J j

REGION 11

-

'

o, '

h

[

101 MARIE TT A sT., N.W . sulT E 3100

ATL ANT A, GE oRGI A 30303

.....f

In Reply Refer To:

JUL 2 01979

RII:EJV

50-338/79-29

50-339/79-37

Virginia Electric and Power Company

Attn:

W. L. Proffitt

Senior Vice President, Power

Post Office Box 26666

Ricbanond, Virginia 23261

Gentlemen:

This refers to the inspection conducted by E. J. Vallish of this office

on June 26-28, 1979 of activities authorized by h7C Operating License

No. hTP-4 and Construction Permit No. CPPR-78 for the North Anna Power

Station facility, Unit Nos. I and 2, and to the discussion of our

findings held with P. Perry at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room.

If this report contains any information that you (or

your contractor) believe to be proprietary, it is necessary that you

make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is

claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained

in a separate part of the document.

If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document Room.

NM.CO

909180 k5

.

JUL 2 01979

Virginia Electric and Power Company

-2-

.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

-1 -c , /l

l

c

/l' / ?// p t

y

C . E . Mu rphy , Chi'e f

Reactor Construction and

Engineering Support Branch

Enclosures:

Inspection Eeport Nos. 50-338/79-29

and 50-339/79-37

cc w/ enclosures:

W. R. Cartwright, Station Manager

Box 402

Mineral, Virginia 23117

P. G. Perry

Senior Resident Engineer

Post Office Box 38

Mineral, Virginia 23117

)U0$$lIO

.

/pm arcg'c,

UNITED STATES

8*

NUCLEAR REGULATORY COMMISSION

5.k.'J'%

I

'j/

E

REGION 11

-

o,

[

101 MARIE TT A ST., NL , sulT E 3100

6,

g"

AT L ANT A, G E ORGI A 30303

.....

Report Nos. 50-338/79-29 and 50-339/79-37

Licensee: Virginia Electric & Power Company

Post Office Box 27777

Richmond, Virginia 23261

Facility Name:

North Anna Power Station, Units 1 and 2

Docket Nos. 50-338 and 50-339

License Nos. NPF-4 and CPPR-78

InspectionatNorth/nnaSitenearMineral, Virginia

'lI

Add

7-M 2k

/

Inspector:

E. J. Vallish

Date Signed

-

,

_ j' s ,

,

Approvedby:f.'.,

/,

fte.-ps

-,s . s

? -- / [ - /., Y

,A. R. Herdt,4CESB, Section Chief

Date Signed

SUMMARY

Dates of Inspection:

June 26-28, 1979

Areas Inspected

This special, unannounced inspection involved 20 inspector-hours onsite in the

area of concrete expansion bolt anchors in response to IE Bulletin (IEB) 79-02.

Results

No apparent items of noncompliance or deviations were identified.

SU's110

80

'

g9091

.

.

DETAILS

1.

Persons Contacted

Licensee Employees

hP Perry, Site Resident Engineer

  • E. R. Bane, QA Supervisor

'P

A. Slater, Resident QA Engineer

<

R.11. Woodall, Power Station Engineering - Const ruction

R. Barryman, Production Operations Department

Other Organizations

R. De Luca, Consultant Engineer - Stone and Webster Engineering

Corporation (S&W)

J. Crossland, QC Engineer (S&W)

  • R. Spence, Superintendent, Field QC (S&W)
  • W. Whitley, Senior Engineer Field QC (S&W)

R. Lintelman, Construction Engineer (S&W)

NRC Resident Inspector

M. Kidd

  • Attended Exit Interview

2.

Exit Interview

The inspection scope and findings were summarized on June 27, 1979, with

those persons indicated in Paragraph I above.

3.

Licensee Action on Previous Inspection Findings

Not inspected.

4.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Concrete Expansion Anchors - Unit !

The licensee stated that the program used in Unit I was the same as that

used in Unit 2 for the correction of the anchor problems. Unit I was at

power at the time of this inspection and so it was not inspected.

The Procedures reviewed pertained to both Units I and 2.

., 2 . s

-

,g

,, . .p O A 1

'

.

-2-

.

6.

Concrete Expansion Anchors - Unit 2

The history of the North Anna anchor bolt and base plate work was discussed

with the licensee and the following procedures pertaining to the installation

and testing of concrete anchor bolts and reinforcement of base plates were

reviewed:

Project Administration Memorandum #42 titled, " Concrete Anchor Bolts.

a.

b.

" Specification for Installation of Phillip Self Drilling Anchors and

Anchor liardware for North Anna Unit 2."

Field Quality Control Procedure (FQCP) QC-11.4 titled, " Inspection of

c.

Pipe Hangers."

d.

Engineering & Design Coordination Report (E&DCR) No. P 1922 G-1

e.

E&DCR no.

P-1575, P-1575 A-1 and P-1575B-1

The following hanger data packages were reviewed for compliance with IE

Bulletin 79-02 and the field ir.stallation was inspected using the details

of the package to verify orientation, materials, location, and installation

requirements:

a.

2-SI-R-175 on line 8"SI-44-153-Q2

b.

2-FPH-RC-597-1 on line 4"RC-597-153A-Q3

c.

2FPH-RC-600-1 on line RC

d.

2RH-HSSS-702 on line 14"RH-403-602-Q2

e.

2RH-SH-20 on line 14"RH-401-1502-Q1

f.

2RC-HSSS-135 on line 6"RC-462-602-Q3

About 25 other base plates, selected at random in Unit 2, were inspected

for flexibility correction.

This inspection confirmed that the licensee's field activities were as

indicated in his response to the bulletin and will satisfactorily close out

the field inspection requirements of the bulletin.

No items of noncompliance or deviation were identified.

On June 28, 1979, further discus-ions were held in the Richmond Corporate

Office with the licensee's engineers inanaging the Surry and North Anna

anchor bolt programs. It was pointed out that a description of the analyti-

cal model used to verify the accounting for pipe support base plate flexibil-

itv is required to be submitted with the response to the IE Bulletin 79-02.