] Q[:V f* "%:,[0,,

UNITED STATES g,

')

,s g

NUCLEAR REGULATORY COMMISSION r,; ' -

E WASHINGTON, D. C. 20555

  1. j ss AUGUST 2 h 137%
  • s,,*

Docket No. 50-333 t'.r. George T. Berry General Manager & Chief Engineer Power Authority of the State of h)1 yj

} @Ut\\ Udi3.

i!ew York l

N 10 Columbus Circ!e New York, New York 10019

Dear Mr. Berry:

In May 1976, we issued guidelines reflecting the NRC's policy regarding the implementation of General Design Criterion 3 - Fire Protection.

Since that time, you have perforned a fire hazards analysis for your facility and have compared its fire protection program with the NRC guidelines.

In late 1976, we set October 1980 as the date for completing the implementation of all modifications associated with this program.

This inplementation schedule recognized that such modifications should be completed as soon as practical, with due consideration of the nature of the modifications.

For example, minor nodifications, adoption of administrative controls and additional portable equipnent would be completed within six months; however, major modifications would require a year or mcra to complete and some modifications would be coordinated with refueling outages.

By their Memorandum and Order in the matter of the Union of Concerned Scientists' Petition for Emergency and Remedial Action, dated April 13, 1978, the Commission directed the staff to use their best efforts to maintain this schedule, and also directed that the Commission be advised if any slippage is anticipated, along with suggested corrective actions.

Ve urge you to apply your best efforts to maintain your schedules for completion of all of the fire protection modifications at your facility and to submit, on an expedited basis, any information that is still outstanding with regard to cpen itens and required design details.

incerely, kI L(

h (

Acting Director D. Eise ut, Division of Operating Peactors Office of Nuclear Reactor Regulation cc:

see next page 361230 7 9 0017 0 0 q

Mr.' George T. Berry Power Authority of the State of New York 2-cc:

Mr. Vito J. Cassan Assistant General Counsel Power Authority of the State of New York 10 Columbus Circle New York, New York 10019 Mr. Peter W. Lyon Manager - Nuclear Operations Power Authority 'of the State

%% hk fg9{.

of New York N (gb U \\

10 Columbus Circle i

New York, New York 10019 i

Mr. J. D. Leonard, Jr.

Resident Manager James A. FitzPatrick Nuclear Ptwer Plant P. O. Box 41 Lycoming, New York 13093 Director, Technical Development Programs State of New York. Energy Office Agency Building 2 Empire State Plaza Albany, New York 12223 Oswego County Of fice Building 46 E. Bridge Street Oswego, New York 13126 George M. Wilverding, Licensing Supervisor Power Authority o' the State of New York 10 Columbus Circle New York, New York 10019 351231.

.