CP-201900439, (CPNPP) - Flooding Focused Evaluation Summary Report-Additional Information

From kanterella
(Redirected from ML19206A073)
Jump to navigation Jump to search
(CPNPP) - Flooding Focused Evaluation Summary Report-Additional Information
ML19206A073
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 07/23/2019
From: Thomas McCool
Luminant, Vistra Operations Company
To:
Office of Nuclear Reactor Regulation
References
CP-201900439, TXX-19075
Download: ML19206A073 (3)


Text

ENERGY 1*rxu

~ energy I m Luminant Thomas P. McCool Site Vice President Luminant P.O. Box 1002 6322 North FM 56 Glen Rose, TX 76043 o 254.897.6042 CP-201900439 TXX-19075 U.S. Nuclear Regulatory Commission Ref 10 CFR 50.54(f)

ATIN: Document Control Desk Washington, DC 20555-0001 7/23/2019

SUBJECT:

Comanche Peak Nuclear Power Plant (CPNPP)

Docket Nos. 50-445 and 50-446 Flooding Focused Evaluation Summary Report-Additional Information Reference 1. Vistra OpCo letter logged TXX-17076, from Thomas P. McCool to the NRC, dated September 7,.

2017, "Flooding Focused Evaluation Summary Report" (ADAMS No. ML17268A147)

In accordance with io CFR 50.54(f) Vistra Operations Company LLC (Vistra OpCo) submits this letter to provide additional information regarding the previously transmitted Flooding Focused Evaluation Summary Report (Reference 1).

As result of subsequent discussions between the NRC staff (Joe Sebrosky) and Comanche Peak Nuclear Power Plant Staff(Carl Corbin), the items in Attachment 1 are new regulatory commitments. These items were

. previously .discussed in Reference 1 and are now identified as regulatory commitments.

6555 SIERRA DRIVE IRVING, TEXAS 75039 0214-812-4600 VISTRAENERGY.COM

TXX-19075 Page 2 of 2 Should you have any questions, please contact Carl B. Corbin at {254) 897-0121 or carl.corbin@luminant.com.

I state under penalty of perjury that the foregoing is true and correct.

Executed on July 23, 2019.

Sincerely, List of Regulatory Commitments zrfu c- Scott A. Morris, Region IV Mark Haire, Region IV Natreon Jordan, NRR Joe Sebrosky, NRR Resident Inspectors, Comanche Peak to TXX-19075 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to in this document by Vistra Operations Company LLC

{Vistra OpCo) for Comanche Peak Nuclear Power Plant {CPNPP) Unit 1 and Unit 2. Any other statements in this submittal are provided for informational purposes and are not considered to be regulatory commitments.

NUMBER COMMITMENT STATUS 5785951 Procedures are revised to increase the margin for closure of Incorporated pathways {created by removal of Circulating Water components for maintenance) to the squaw creek reservoir for the probable maximum flood {see TXX-17076/ NRCAdams ML17268A147 for additional information).

5785958 The preventative maintenance program is revised to ensure Incorporated that the credited storm drainage piping is adequately maintained, and fuel oil storage tank covers are maintained watertight (see TXX-17076 / NRC Adams Mll 7268A147 for additional information}.

5785962 An evaluation of the available physical margin {APM} for local Open intense precipitation {LIP} using Appendix Bin NEI 16-05 showed that there is adequate margin for Key SSCs and that Scheduled completion date is LIP flood protection features are reliable, noting the exception December 31, 2019.

for the northwest drainage system outlet scour protection that has been entered into the corrective action program {i.e., CR-2017-009030} for resolution. See TXX-17076 / NRC Adams Mll 7268A147 for additional information.