UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 10, 2019 Mr. Chris T. Terry, Manager Licensing and Safety Analysis BWXT Nuclear Operations Group, Inc.

P.O. Box 785 Lynchburg, VA 24505

SUBJECT:

ACCEPTANCE REVIEW OF REQUEST FOR EXEMPTION FROM 24-HOUR REPORTING REQUIREMENT OF TITLE 10 OF THE CODE OF FEDERAL REGULATIONS, PARAGRAPH 70.50(b)(1) (ENTERPRISE PROJECT IDENTIFIER L-2019-LLA-0103)

Dear Mr. Terry:

By your letter number 19-020 dated April 24, 2019 (Agencywide Documents Access and Management System [ADAMS] Accession Number ML19120A285), you provided a request for exemption from the requirements of Title 10 of the Code of Federal Regulations (10 CFR)

Paragraph 70.50(b)(1).

The U.S. Nuclear Regulatory Commission (NRC) staff has performed an acceptance review of your submittal to determine if the application contains sufficient technical information to allow the NRC staff to conduct the detailed technical review. Based on this review, completed May 20, 2019, the NRC staff concludes the submittal contains information in sufficient detail to enable the staff to conduct its detailed review. Accordingly, the NRC staffs Web Based Licensing program has established a schedule for this review, based on internal milestones, which includes the issuance of any requests for additional information (RAIs) by July 15, 2019.

The NRC staff anticipates completing its review and developing a Safety Evaluation Report to address the submittal by the end of September 2019 or 4 weeks after adequate response to any RAIs, if any. In addition, the NRC staff estimates that completing the review and making an independent assessment of the proposed application will require approximately 60 staff hours.

In accordance with 10 CFR, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs ADAMS.

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

C. Terry 2 If you have any questions, feel free to contact me at (301) 415-7119, or via e-mail at Merritt.Baker@nrc.gov.

Sincerely,

/RA/

Merritt N. Baker, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Cycle, Safety, Safeguards, and Environmental Review Office of Nuclear Material Safety and Safeguards Docket No. 70-27 License No. SNM-42

C. Terry 3

SUBJECT:

ACCEPTANCE REVIEW OF REQUEST FOR EXEMPTION FROM 24-HOUR REPORTING REQUIREMENT OF TITLE 10 OF THE CODE OF FEDERAL REGULATIONS, PARAGRAPH 70.50(b)(1) (ENTERPRISE PROJECT IDENTIFICATION CODE L-2017-PMP-0001)

DATED: June 10, 2019 ADAMS Accession Number: ML19150A460 OFC FCSE/FFLB FCSE/ERB FCSE/FFLB FCSE/FFLB NAME *MNBaker AWalker-Smith JZimmerman MNBaker DATE 06/05/2019 06/06/2019 06/10/2019 06/10/2019 OFFICIAL RECORD COPY