Enclosure 3: HEAF Research - Pre-GI-018 Timeline and Milestones
ML19127A204
Person / Time
Issue date: 07/10/2019
From: Michael Cheok
NRC/RES/DRA
To: Raymond Furstenau
Office of Nuclear Regulatory Research
N. Melly 415-2392
Shared Package
ML19127A202 List:
References
Download: ML19127A204 (1)


Text

Enclosure 3 - HEAF Research - Pre-GI-018 Timeline and Milestones 2018 2019 2020 2021 ID Task Name Start Finish Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 1 Stakeholder Engagement, HEAF Public Workshop (ML18108A210) 04/18/2018 04/19/2018 2 Stakeholder Engagement, Public Meeting (ML19046A388) 01/23/2019 01/23/2019 3 Stakeholder Engagement, Public Meeting (ML19108A420) 03/20/2019 03/20/2019 4 Small Scale Testing 06/18/2018 08/15/2018 5 Large MV SWGR Testing (4 Tests) 08/16/2018 09/20/2018 6 LV SWGR & MV duct Testing (9 Tests) 03/20/2019 12/13/2019 7 Equipment Procurement (LV SWGR & MV Duct) 03/20/2019 07/19/2019 8 Equipment Prep 07/22/2019 08/09/2019 9 Testing P2 S2 LV & MV ducts 08/16/2019 09/20/2019 10 Report P2 S2 LV & MV ducts 09/23/2019 12/13/2019 11 Generator Decrement Testing (1-2 Tests) 04/11/2019 08/04/2020 12 Procurement 04/11/2019 07/02/2019 13 Analytics 07/03/2019 01/03/2020 14 Equipment Procurement & Prep 01/03/2020 04/10/2020 15 Testing 04/13/2020 06/23/2020 16 Report 06/24/2020 08/04/2020 17 Confirmatory Power Supply Config. Testing (1-2 Tests) 10/01/2019 08/03/2020 18 Equipment Procurement & Prep 10/01/2019 02/28/2020 19 Testing 04/10/2020 06/22/2020 20 Report 06/23/2020 08/03/2020 21 HEAF Hazard Modeling 01/18/2019 11/30/2020 22 SNL Modeling Development 01/18/2019 12/30/2019 23 SNL Target Fragility 04/02/2019 12/30/2019 24 SNL Model Refinement & Validation 11/01/2019 07/31/2020 25 SNL ZOI Tables 03/30/2020 11/30/2020 26 WG ZOI Methods Development 01/01/2019 01/29/2021 27 Pilot Plant Guidance & Selection 09/30/2020 03/02/2021 28 Risk/Safety/Regulatory Assessment 03/03/2021 08/31/2021 29 Pilot Plant Study 03/03/2021 04/30/2021 30 Risk/Safety Determination 05/03/2021 06/30/2021 31 Complete Assessment Report 07/01/2021 08/31/2021